Ohio Admin. Code 5501:2-7-02

Rule 5501:2-7-02. Determination of incentive/disincentive time

Last amended: 2018Year: 2026Length: 76 wordsOfficial source
119.03 Prior to including incentive/disincentive provisions in a contract, the director shall conduct an engineering analysis in order to determine realistic critical and non-critical time frames. The time frames, including critically identified work phase, shall be clearly set out in the construction contract. The analysis should involve a review of industry past performance and a critical path method schedule. Last updated March 24, 2023 at 1:12 PM Supplemental Information Authorized By: 5525.20 Amplifies: 5525.20 2/14/2028 9/29/1989