OAC 310:667-47-1
Submission of plans and specifications and related
Cite as Okla. Admin. Code § 310:667-47-1
requests for services
(a) Submission of plans. Before construction is begun, plans and
specifications covering the construction of new buildings or major
alterations to existing buildings shall be submitted to the Department
as provided in OAC 310:667-47-2 or OAC 310:667-47-10.
(1)
Plans and specifications are required for the following
alterations:
(A) Changes that affect path of egress;
(B) Change of use or occupancy;
(C) Repurposing of spaces;
(D) Structural modifications;
(E)
Heating,
ventilation
and
air
conditioning
(HVAC)
modifications;
(F)
Electrical
modifications
that
affect
the
essential
electrical system;
(G) Changes that require modification or relocation of fire
alarm initiation or notification devices;
(H) Changes that require modification or relocation of any
portion of the automatic fire sprinkler system;
(I) Replacement of fixed medical equipment if the alteration
requires any work noted in (A) through (H) of this paragraph;
(J) Replacement of or modifications to any required magnetic
or radiation shielding;
(K) Changes to or addition of any egress control devices or
systems.
(2)
Plans and specifications are not required for the following
alterations:
(A) Painting,
papering,
tiling,
carpeting,
cabinets,
counter tops and similar finish work provided that the new
finishes shall meet the requirements of this Chapter;
(B) Ordinary repairs and maintenance;
(C) Modifications
to
nurse
call
or
other
hospital
signaling/communication/information
technology
systems
provided the modifications meet the requirements of this
Chapter; or
(D) Replacement of fixed or moveable medical equipment
that does not affect electrical, HVAC, or shielding
requirements noted above.
(b)
Fees. Each construction project submitted for approval
OAC 310:667
OKLAHOMA STATE DEPARTMENT OF HEALTH
115
September 13, 2019
under OAC 310:667-47-2 shall be accompanied by the appropriate
review fee based on the cost of design and construction of the
project. Review fees are as follows:
(1) Project cost less than $10,000.00:
$250.00 Fee
(2) Project cost $10,000.00 to $50,000.00: $500.00 Fee
(3) Project cost $50,000.00 to $250,000.00: $1000.00 Fee
(4) Project cost $250,000.00 to $1,000,000.00: $1500.00 Fee
(5) Project cost greater than $1,000,000.00: $2000.00 Fee
(c)
Fees when greater than two (2) submittals required. The
review fee shall cover the cost of review for up to two (2) stage
one and two (2) stage two submittals and one final inspection. If
a stage one or stage two submittal is not approved after two (2)
submissions, another review fee based on the cost of the project
shall be required with the third submittal. Fast-track projects
shall be allowed two reviews for each package submitted. If a
fast-track stage package is not approved after the second
submittal, another review fee based on the cost of the project
shall be required with the third submittal of the package.
(d)
Review
process.
Design
and
construction
plans
and
specifications shall be reviewed in accordance with the following
process.
(1)
Unless otherwise provided in this Subchapter, the
Department shall have ten (10) calendar days in which to
determine if the filed application is administratively
complete
(A) Upon determining that the application is not
administratively
complete,
the
Department
shall
immediately notify the applicant in writing and shall
indicate with reasonable specificity the inadequacies and
measures necessary to complete the application. Such
notification shall not require nor preclude further
review of the application and further requests for
specific information. If the Department fails to notify
the applicant as specified in this Paragraph, the period
for technical review shall begin at the close of the
administrative
completeness
review
period.
Upon
submission of correction of inadequacies, the Department
shall have an additional ten (10) calendar days to review
the application for completeness.
(B)
Upon
determination
that
the
application
is
administratively
complete,
the
Department
shall
immediately notify the applicant in writing. The period
for technical review begins.
(2)
The Department shall have forty-five (45) calendar
days from the date a completed application is filed to review
each application for technical compliance with the relevant
regulations and reach a final determination.
(A)
The time period for technical review is tolled
(the
clock
stops)
when
the
Department
has
asked
for
supplemental information and advised the applicant that
the time period is tolled pending receipt.
(B)
To make up for time lost in reviewing inadequate
OAC 310:667
OKLAHOMA STATE DEPARTMENT OF HEALTH
116
September 13, 2019
materials, a request for supplemental information may
specify that up to 30 additional calendar days may be
added to the deadline for technical review, unless the
request for supplemental information is a second or later
request that identifies new deficiencies not previously
identified
(C)
An application shall be deemed withdrawn if the
applicant fails to supplement an application within 90
calendar days after the Department's request, unless the
time is extended by agreement for good cause.
(D)
Extensions may be made as provided by law.
(e)
Fees for other services. Fees for other services related to
construction projects are as follows:
(1) Request for exception to or temporary waiver of FGI Guidelines
fee: Five Hundred Dollars ($500.00);
(2) Application for self-certification fee: One Thousand Dollars
($1,000.00);
(3) Courtesy inspection, prior to final inspection for approval of
occupancy, fee: Five Hundred Dollars ($500.00);
(4) Professional consultation or technical assistance fee: Five
Hundred Dollars ($500.00) for each eight staff hours or major
fraction thereof. For technical assistance requiring travel, the
fee may be increased to include the Department's costs for travel.