OAC 310:667-47-3
Construction and inspection
Cite as Okla. Admin. Code § 310:667-47-3
(a)
Construction other than minor alterations, shall not be commenced
until Stage Two plan-review deficiencies have been satisfactorily
resolved.
(b)
Prior to commencing construction, the contractor shall submit a
construction schedule which includes, as a minimum, the start date,
dates that the heating-ventilation air-conditioning (HVAC), plumbing,
and medical gas installation shall commence, and projected date of
completion.
(c)
The completed construction shall comply with the approved drawings
and specifications, including all addenda or modifications approved for
the project.
(d)
A final construction inspection of the facility shall be conducted
by the Department for the purpose of verifying compliance with these
requirements and the approved plans and specifications. The facility
shall not allow patient occupancy until a final approval is granted by
the Department.