(a) Eligible pollutants. An emission reduction credit (ERC) may only be obtained for a reduction
in nitrogen oxides (NOX) or volatile organic compounds (VOCs).
(b) No inter-pollutant ERC substitution. ERCs are pollutant specific.
(1) An ERC generated for a reduction in NOX emissions may not be used to offset an emissions
increase in VOCs.
(2) An ERC generated for a reduction in VOC emissions may not be used to offset an emissions
increase in NOX.
(c) ERC requirements.
(1) To establish an ERC the emission reduction must meet all of the following criteria:
(A) The emission reduction must be permanent.
(B) The emissions reduction must be verifiable.
(C) The emission reduction credit must be federally enforceable.
(D) The emission reduction credit must represent actual emissions as defined in OAC
252:100-10-4(a)(1).
(E) The emission reduction credit must be surplus at the time of generation and at the time
of use.
(F) The emission reduction credit must be generated by a facility located within the state
of Oklahoma.
(2) Ineligible uses of ERCs.
(A) ERCs generated under the requirements specified in this Subchapter may not be used
to offset emissions in nonattainment areas as required in OAC 252:100-8-51.1, emissions
reductions and offsets.
(B) [RESERVED]
(d) Permit and public notice requirements. The generation of an ERC must occur through the
issuance of a construction (NSR) permit that establishes requirements in accordance with OAC
AQAC_2026_JUL_SC_7_8_10_RUL
17
June 15, 2026
252:100-10-3(c) above and which meets the public review and permit content requirements of
paragraph (1) or (2) below.
(1) The generation of an ERC by a facility currently operating under a Title V operating permit
shall be established through issuance of a construction permit that meets the requirements of
OAC 252:100-8-5(d), the content requirements for construction permit applications, and which
has undergone Tier II or Tier III public review.
(2) The generation of an ERC by a facility currently operating under an individual facility
FESOP shall be established through issuance of a construction permit that meets the
requirements of OAC 252:100-7-15(c), the content requirements for a construction permit for
an individual facility. In addition, the construction permit must undergo Tier II or Tier III
public review.
(e) Severability. If any provision of this Subchapter is held invalid, the remainder of this
Subchapter, including any permits issued under the provisions of this Subchapter other than those
which are held invalid, shall not be affected thereby.