OAC 252:100-10-5
Requirements for ERC Generators
Cite as Okla. Admin. Code § 252:100-10-5
(a) Eligible facilities. Offsets may only be generated by the owners and operators of facilities that
meet criteria (1) and (2) below.
(1) Facilities that are currently operating under either of the following permit types
(A) A Title V operating permit or
(B) An individual facility operating under a FESOP.
(2) To be eligible to generate ERCs, a facility must have been operating for at least 24 months
prior to the date the owner or operator of the facility submits an application for an NSR permit
that will generate ERCs.
(b) Eligible emission reduction strategies. ERCs may be awarded for either of the following
emission reduction strategies:
(1) The permanent shutdown of a facility, resulting in the elimination of actual emissions
associated with the facility; or
(2) The adoption of a limitation on the emission of an eligible pollutant that results in a
permanent reduction in actual emissions.
(c) Ineligible emission reduction strategies. ERCs may not be awarded for any of the following
strategies:
AQAC_2026_JUL_SC_7_8_10_RUL
19
June 15, 2026
(1) A reduction of emissions from a facility due to the shifting of activity from one emission
unit to another emission unit at the same facility;
(2) A reduction of emissions from a facility that is required by an otherwise applicable federal
rule; or
(3) A reduction of emissions from a facility that is due to an enforcement action.
(d) Permitting requirements and public review. The generation of ERCs may be accomplished
through issuance of a permit that meets the requirements of (1) or (2) below.
(1) A facility currently operating under a FESOP shall obtain a construction permit that meets
the requirements of either (A), (B), or (C) below.
(A) The facility shall obtain an individual facility construction permit that meets the
requirements of OAC 252:100-7-15. In addition, the permit must undergo Tier II public
review in accordance with OAC 252:4-7-13(g); or
(B) The facility shall obtain a major source construction permit that meets the requirements
of OAC 252:100-8-4(a). In addition, the permit must undergo Tier II or Tier III public
review in accordance with OAC 252:4-7-13(g); or
(C) The facility shall obtain a PSD construction permit that meets the requirements of OAC
252:100-8-4(a) and all applicable requirements of Part 7 of OAC 252:100-8. In addition,
the permit must undergo Tier II or Tier III public review in accordance with OAC 252:4-
7-13(g).
(2) A facility currently operating under a Title V operating permit shall obtain a construction
permit that meets the requirements of either (A) or (B) below.
(A) The facility shall obtain a major source construction permit that meets the requirements
of OAC 252:100-8-4(a). In addition, the permit must undergo Tier II or Tier III public
review in accordance with OAC 252:4-7-13(g); or
(B) The facility shall obtain a PSD construction permit that meets the requirements of OAC
252:100-8-4(a) and all applicable requirements of Part 7 of OAC 252:100-8. In addition,
the permit must undergo Tier II or Tier III public review in accordance with OAC 252:4-
7-13(g).