OAC 252:100-49-5
Program criteria and qualification determination
Cite as Okla. Admin. Code § 252:100-49-5
(a) Applying for rebate eligibility. An applicant responsible for the implementation of a qualified
Emission Reduction Project may submit a rebate claim to DEQ for review and determination
whether the project qualifies under the program.
(1) The rebate claim shall be submitted on forms provided for this purpose, or as otherwise
specified by DEQ.
(2) The rebate claim shall be submitted to DEQ no later than six (6) months after the end of
the fiscal year in which the expenditures were made. The fiscal year ends on June 30 each year.
(3) Project documentation shall include:
(A) a project description that provides information in sufficient detail to determine that it
qualifies as an Emission Reduction Project (ERP) as defined in 68 O.S. § 55008;
(B) an estimation of actual resulting emission reductions;
(C) a statement that the project has been designed, installed, and operated as described in
the claim and in accordance with good engineering practices and the requirements of this
Chapter, and that implementation of the project is complete; and
(D) an itemization of expenses, with invoices, for all equipment installed to implement the
project;
(E) a statement that specifically identifies whether the ERP pertains to refining activities,
or does not pertain to refining activities.
(4) Project documentation shall state the amount of expenditures made in this state directly
related to the implementation of the qualified Emission Reduction Project.
(5) The applicant shall certify that the project is not required to address an enforcement action
or undertaken as a supplemental environmental project to offset an enforcement penalty.
(6) The applicant shall provide a certification from OTC that it has filed all Oklahoma tax
returns and tax documents which are required by the laws of this state.
(7) The applicant shall provide evidence of a certificate of general liability insurance with a
minimum coverage of One Million Dollars ($1,000,000.00) and a workers' compensation
policy pursuant to the laws of this state which shall include coverage of employer's liability.
(8) The rebate claim shall include certification, signed by a responsible official, attesting to
the truth, accuracy, and completeness of the claim. This certification shall contain the
following language: "I certify that, based on information and belief formed after reasonable
inquiry, the statements and information in the document are true, accurate, and complete."
(9) The applicant will be assessed a one-time fee of $1,000 that must accompany the rebate
claim. A rebate claim without the appropriate fee is incomplete.
(b) DEQ review of rebate claim. DEQ will review the rebate claim information to determine if
the described project is a qualified Emission Reduction Project, and will the notify the applicant
and OTC of its final approval or disapproval of the claim for a rebate payment from available funds
in either the Oklahoma Emission Reduction Technology Upstream and Midstream Incentive
Revolving Fund or the Oklahoma Emission Reduction Technology Downstream Incentive
Revolving Fund, as appropriate.
(c) Early submittal of rebate claim documentation for preliminary review. An applicant may
submit documentation for a planned ERP and corresponding rebate claim, for preliminary review
by DEQ prior to the expenditure of project funds. Such submittal shall include a payment for the
fee required under paragraph (9). Any resulting preliminary approval of the technical merits of the
project shall be subject to final review and approval, once the project is complete and invoices are
received per (a)(3)(C) and (D) above, prior to notifying OTC of a final determination under
subsection (b).
(d) Effect on OTC authority. Nothing in this section shall limit or otherwise affect OTC's
authority or responsibilities under the Act, including the authority to request submittal of additional
information by the claimant.