OAC 252:656-3-1
Permitting process
Cite as Okla. Admin. Code § 252:656-3-1
(a) This Subchapter implements the permitting process of Part 4, Wastewater and
Wastewater Treatment Systems, 27A O.S. § 2-6-401 et seq., and the Oklahoma Uniform
Environmental Permitting Act, 27A O.S. § 2-14-101 et seq.
(b) Permits are required for the construction or modification of non-industrial wastewater
and water reuse systems.
(c) The permit application is a two-step process:
(1) The first step is the submission of an engineering report (as described in 252:656-
3-4); and
(2) The second step is the submission of the final design report along with the
required application forms and fees. The final design report shall:
(A) include 2 sets of plans and specifications, with at least one set of plans
printed on 11" x 17" paper and at least one set of specifications loosely bound
and suitable for scanning, and
(B) reflect any changes from the approved engineering report.
(C) Provided, an authorized design-build project may use the flexible permitting
process upon approval by DEQ as provided in these rules. If design-build is used,
the final design package must encompass the entire completed project.
(d) Unless an extension is granted, a construction permit expires if construction does not
begin within one year from the date the permit is issued.
(e) Permits to construct or modify non-industrial wastewater and water reuse systems shall
only be issued to public entities unless all components of the proposed systems, including
all service lines, are located on property:
(1) owned by the applicant, or
(2) dedicated to the applicant through a recorded easement for the installation and
operation of the system.