OAR 411-062-0070
OAR 411-062-0070. Approval and Payment
(1) All prior authorization requests must be approved by the Department in writing to be eligible for reimbursement. The Department will notify facilities in writing if their Project is not approved.
(2) Once work on a Project is completed, the facility must submit a request for reimbursement for the actual cost paid to complete the Project. A request for reimbursement submitted pursuant to this paragraph shall include receipts for actual costs.
(3) The Department will reimburse actual costs, up to 110% of the prior authorized amount, subject to the maximum reimbursement amount described in OAR 411-062-0060. The Department will issue payment within thirty (30) days of receipt of a request for reimbursement submitted pursuant to this rule.
(4) All requests for reimbursement must be received no later than June 30, 2024.