OAR 632-037-0095

OAR 632-037-0095. Permitting Agency Action on a Consolidated Application

Last amended: 2014Length: 88 wordsOfficial source
(1) Within 225 days of the issuance of a Notice to Proceed and not sooner than 60 days after the submittal of a complete environmental evaluation, each permitting agency shall submit to the Department its draft permit and permit conditions or permit denial document. (2) If a permitting agency includes in its draft permit a condition that is inconsistent with the environmental evaluation, the agency shall include with its draft permits a written explanation of the conditions setting forth the findings of the agency that support the condition.
OAR 632-037-0095: OAR 632-037-0095. Permitting Agency Action on a Consolidated Application | Justis AI