OAR 141-089-0720

OAR 141-089-0720. Waterway Bank Stabilization Using Bioengineering – Purpose

Last amended: 2024Length: 85 wordsOfficial source
OAR 141-089-0720 to 141-089-0735 set forth the conditions under which a person may, without an individual removal-fill permit, general removal fill permit, or DEQ remedial action permit waiver from the Department, fill or remove material in waterways for the purpose of stabilizing the actively eroding banks of waterways using bioengineering methods. Temporary impacts to wetlands or waterways associated with a project may be authorized by combining this GA (OAR 141-089-0720, et seq.) with the Temporary Impacts to Wetlands and Waterways GA (OAR 141-089-0700, et seq.).
OAR 141-089-0720: OAR 141-089-0720. Waterway Bank Stabilization Using Bioengineering – Purpose | Justis AI