OAR 860-082-0040

OAR 860-082-0040. Insurance

Last amended: 2024Length: 88 wordsOfficial source
(1) A public utility may not require an applicant or an interconnection customer with a small generator facility with a nameplate rating of 200 kilowatts or less to obtain liability insurance in order to interconnect with the public utility’s transmission or distribution system. (2) A public utility may require an applicant or an interconnection customer with a small generator facility with a nameplate rating greater than 200 kilowatts to obtain prudent amounts of general liability insurance in order to interconnect to the public utility’s transmission or distribution system.