OAR 918-515-0150
OAR 918-515-0150. Manufactured Dwelling Installer License Requirements
(1) An installer must:
(a) Work for a business with a valid Construction Contractors Board license; or
(b) The installer is a business with a valid Construction Contractors Board license.
(2) Work covered by an installer’s license is limited to:
(a) Preparing the site and stand for the installation of the manufactured dwelling or cabana;
(b) Installing manufactured dwellings, cabanas, skirting, underfloor vapor retarder, ventilation, access, and temporary steps;
(c) Installing the support, tie-down, ERB’s, and the structural connections for manufactured dwellings and cabanas;
(d) Providing setbacks, clearances, and fire life and safety protection;
(e) Providing plumbing and electrical utility connections;
(f) Providing plumbing, electrical, and mechanical crossover, appliance, and fixture connections of and to the manufactured dwelling or cabana as permitted by these rules;
(g) Install appliance exhaust ducts and terminations when required;
(h) Performing plumbing, mechanical, and electrical tests when required; and
(i) Serving as the supervisor of individuals licensed by the division as limited installers.
(3) An installer must, at a minimum:
(a) Assure the manufactured dwelling or cabana stand is in compliance with the Oregon Manufactured Dwelling Installation Specialty Code prior to the installation of the manufactured dwelling or cabana;
(b) Assure all setbacks, clearances, and fire life and safety installations are in compliance with the Oregon Manufactured Dwelling Installation Specialty Code;
(c) Perform electrical and plumbing tests if the respective plumbing and electrical connections were made by the installer;
(d) Close and secure all access panels and covers on or under the manufactured dwelling or cabana;
(e) Assure the underfloor dryer and range exhaust ducts are roughed in if the manufactured dwelling is equipped with or provides for the installation of such an appliance requiring exhaust ducts;
(f) Assure that all doors and windows are adjusted, secured in place, and operational;
(g) Assure all ship-loose flue vents and chimneys are installed, secured in place, and capped according to their listing;
(h) Where the installer also installs the skirting, comply with OAR 918-515-0490(1);
(i) Affix a certification tag to each manufactured dwelling or cabana installed;
(j) Complete all reporting and application forms required by these rules; and
(k) Leave the manufacturer’s installation instructions at the installation site to be available at the time of the inspection if used for any part of the installation;
(l) Assure all portions of the manufactured dwelling installation performed by the installer are in compliance with the Oregon Manufactured Dwelling Installation Specialty Code ; and
(m) Correct all applicable nonconformances within 30 days of receipt of a correction notice .
[Publications: Publications referenced are available from the agency.]