No. 11
OFFICIAL OPINION No. 11
Cite as Pa. Op. Att'y Gen. No. 11 (1973)
OFFICIAL OPINION No. 11
Federal Office of Ernergency Preparedness ( OEP) Regiilations-Cornpleted
construction-Requirernent of acceptance
1. Under Pennsylvania law construction of a facility, as intended by OEP
regulations, is complete when it has been put together and made ready
for use.
2.
A facility can be considered to have been completed even though not for-
mally accepted by the contractin State agency.
Dr. Richard Gerstell
Director of Civil Defense
Harrisburg, Pennsylvania
Dear Dr. Gersten:
Harrisburg, Pa.
January 25, 1973
You have requested an opinion as to whether construction of
the Rausch Creek Water Treatment Plant can be considered to
have been completed at the time of the June flood. This opinion
is requested in order to determine how the assistance eligibility
provisions of the Federal Disaster Relief Act, 42 U.S.C.A. §4482,
and regulations provided in Circular 4000.5c of the Federal
Office of Emergency Preparedness (OEP) are to be applied to
the Rausch Creek Plant. The Act and OEP regulations provide
that reimbursement shall be made in full for any publicly-
owned utilities damaged in the flood. (See 42 U.S.C.A. §4482, and
OEP Circular 4000.5c, pp 32 and 33). The Acts, however, pro-
vide that where a public facility is "under construction" at the
time of a natural disaster, Federal reimbursement shall be made
24
OPINIONS OF THE ATTORNEY GENERAL
in an amount not to exceed fifty ( 50 % ) per cent of the resulting
damage.
·w hile the opinion you request appears to turn on an interpre-
tation of Federal statutes and regulations, you have further ~d
vised that the Office of Emergency Preparedness, through its
Federal Coordinating Officer, Francis X. Carney, has determin-
ed that an interpretation of the applicable State la~ by the
Attorney General would effectively settle the quest10~ as to
what amount of compensation is due under the regulat10ns. A
letter from OEP to that effect has been appended to this opinion.
Records of the Depar tment of Environmental Resources indi-
cate that with the exception of four minor, punch list items, all
elements of the plant had been completed prior to May 22, 1972,
and that the plant itself was successfully operated from June
14 to June 16, 1972. In addition, it appears that all items on the
punch list had been completed by June 18, 1972, prior to the
June flood. The question you have presented, therefore, is
whether the Rausch Creek Plant, which had been completed in
every major respect, but had not been formally accepted by the
Department of Environmental Resources, was "under construc-
tion" at the time of the flood, as intended by the OEP regula-
tions. It is our opinion and you are advised that construction of
the Rausch Creek Plant can be considered to have been com-
pleted by the date of the flood.
The P ennsylvania Superior Court has ruled that construction
is complete "when it [is] lawfully usable for the purpose intend-
ed." See Versailles Township v. Ulm et ux, 152 Pa. Super. 384,
389 ( 1943). The Rausch Creek Plant was usable and, in fact,
had been operated satisfactorily prior to the flood. In referring
to the meaning of construction, an earlier Superior Court de-
cision stated that it meant "putting together, ready for use."
Eichleay v. W ilson, 8 Pa. Super. 14, 16 ( 1898). On the date of
the flood, the Rausch Creek Plant appears to have been "ready
for use" and, consequently, met the Court's definition as to
completed construction. In view of these two Pennsylvania court
decisions, therefore, it is apparent that the plant had been com-
pleted at the time of the June flood.
The Federal courts have reached similar conclusions. In Clauss
v. American Insurance Co., 214 F. Supp. 442 (E.D. Pa. 1963),
J udge J oseph Lord III ruled, in effect, that construction could
be completed without fonnal acceptance. In that case, plaintiff
entered into a contract with the City of Philadelphia to construct
a sewer. After work on the sewer had been completed, but before
formal acceptance had been made by the City of Philadelphia,
an accident occurred near the site where the work had been
done. Suit was commenced on an insurance policy covering lia-
bility arising from plaintiff's activities with regard to the con-
struction of the sewer. The policy included an exclusionary
clause which provided that "products hazards" occurring after
OPINIONS OF THE ATTORNEY GENERAL
25
construction had been completed were not covered under the
policy. Suit was brought on the policy, and the Court ruled that
the work had been completed within the meaning of the insur-
ance policy. Judge Lord ruled that the operation was completed
because nothing further was needed in the way of construction.
In dealing with the question of acceptance, the Court ruled that
this was not a necessary requisite of the insurance policy, since
the policy only called for completion and did not refer to ac-
ceptance. The OEP regulations, in a similar manner, simply call
for completion. No reference is made to formal acceptance. A
similar conclusion was reached in Continental Illinois National
Bank v. United States, 115 F. Supp. 892 (Ct. Cl. 1953), where
the Court of Claims ruled that formal acceptance was not a re-
quirement in determining whether construction had been com-
pleted.
For these reasons, it is our opinion that the Rausch Creek
Plant was not "under construction," within the meaning of the
OEP regulations, but rather had been completed in all signifi-
cant respects. Hence, the Rausch Cre.ek Plant is eligible to re-
ceive reimbursement in full for damages caused by the flood of
June, 1972.
Very truly yours,
THEODORE A. ADLER
Deputy Attorney General
ISRAEL PACKEL
Attorney General