No. 2
OFFICIAL OPINION No. 2
Cite as Pa. Op. Att'y Gen. No. 2 (1974)
OFFICIAL OPINION No. 2
Coal Contracts -
Increased compensation to coal vendors.
1. The Department of Prop~rty and Supplies may not negotiate an increase in
payments to be paid to coal vendors without receiving additional consideration.
2. The performance of a previously existing legal duty is not consideration.
3. Coal vendors who have contracts with the Commonwealth have a legal duty to
deliver coal at the agreed upon contracted price.
4. Article III, §26 of the Pennsylvania Constitution enunciates a policy that dis-
courages the payment of additional compensation once a contract has been made.
This policy should be adhered to by the Executive branch of government.
8
OPINIONS OF THE ATTORNEY GENERAL
5. A renegotiation of the existing coal contracts .would frustrate the intent of Arti.cle
III,§ 22 of the Pennsylvania Constitution, which provides for compet1t1ve bidding
of such contracts.
Honorable Frank C. Hilton
Secretary
Property and Supplies
Harrisburg, Pennsylvania
Dear Mr. Hilton:
Harrisburg, Pa.
January 14, 1974
We have received a request for an opinion from your department
asking whether the Department of Property and Supplies can
negotiate a price increase for vendors of coal who have contracted to
supply coal for the Commonwealth. Since the price of coal has in-
creased substantially in recent months the vendors will sustain
losses on their contracts unless the contract prices are renegotiated.
It is our opinion, and you are so advised, that a renegotiation of the
contract so as to increase the vendor's compensation is not legal.
A renegotiation of a contract implies the creation of a new con-
tractual relationship which changes the rights and responsibilities
of all parties involved. In this case, the only changed rights in the
contract would involve an increase in compensation to the coal ven-
dors. The vendor would get an increase in his price, while the
Department of Property and Supplies would receive nothing in
return, other than continued delivery of coal, which the vendors are
legally bound to deliver in any event. It is a general principle of con-
tract law that the performance of an act which one party is legally
bound to render to another is not legal consideration. Sum. Pa. Jur. ,
Contracts §118. An increase in compensation to the coal vendors
would result in an expenditure of public funds by the Department of
Property and Supplies without the Deparment or the Com-
monwealth receiving any consideration in exchange.
The only circumstances where a renegotiation of a contract could
be considered is where unforeseen circumstances make perfor-
mance impossible or impractical. In a case such as that, however, a
renegotiation of the contract could not result in an increase in com-
pensation, but could only involve a mutual agreement to terminate
the contractual relationship.
An increase in expense, such as evidenced by the circumstances
facing coal vendors today, is not such a change in circumstances suf-
ficient to warrant a termination of the contractual relationship. In
Commonwealth v. Bader, 271 Pa. 308 (1921), a vendor sought to be
released from his contract because of increased costs due to the out-
break of World War I. The vendor contended that resultant short-
ages made his performance impractical, if not impossible. The
Court ruled that the vendor must supply the goods at the agreed
OPINIONS OF THE ATTORNEY GENERAL
9
upon price, and that an increase in costs was not a valid reason for
termination of the contractual relationship.
A case somewhat in point is Dockett v. Old Forge Borough, 240 Pa.
98 ( 1913). In that case, a borough entered into a contract with a con-
tractor for construction of a sewer. Shortly after work began, the
contractor's employees struck, and eventually obtained an increase
in salary. Because of the resultant salary increase, the contractor
notified the borough that he could not complete the work. The
borough agreed to pay the contractor additional compensation
because of these "unforeseen expenses". Suit was brought by a tax-
payer to enjoin such payments. The Court ruled that the borough
had no right to pay additional compensation, even under the threat
of non-performance. The Court went on to say that the contractor
had a previously existing legal obligation which the borough could
enforce at law, and to expend public funds to insure performance of
this previously existing legal obligation was illegal. See also Quar-
ture v. Allegheny County, 141 Pa. Superior Ct. 356, 364(1940), where
the Court stated: "When a party merely does what he has already
obligated himself to do, he cannot demand additional compensation
therefor .... "
The question of what constitutes changed conditions that are suf-
ficient to render a contract impossible or impracticable is dealt with
in Section 2-615 of the Uniform Commercial Code, 12A P.S. §615.
That section, however, does not sanction additional compensation
when difficult or changed circumstances arise, but, rather, notes
that such changed circumstances can be the basis for delay or non-
performance on the part of a vendor. In addition, Comment4 to Sec-
tion 2-615, provides:
"Increased cost alone does not excuse performance unless
the rise in cost is due to some unforeseen contingency which
alters the essential nature of the performance.Neither is a
rise or a collapse in the market in itself a justification, for
that is exactly the type of business risk which business con-
tracts made at fixed prices are intended to cover. But a
severe shortage of raw materials or of supplies due to a con-
tingency such as war, embargo, local crop failure, unfore-
seen shutdown of major sources of supply or the like, which
either causes a marked increase in cost or altogether
prevents the seller from securing supplies necessary to his
performance, is within the contemplation of this section."
Such is not the case here.
Additionally, Article III, §26 of the Pennsylvania Constitution
provides, in part,:
"No bill shall be passed giving any extra compensation to
any ... contractor, after services shall have been rendered or
contract made .... "
10
OPINIONS OF THE ATTORNEY GENERAL
Any increase in compensation granted to the vendor would in-
volve additional expenditures by the Department of Property and
Supplies. Although Article III, § 26 of the Constitution does not ex-
pressly bar the Executive branch from increasing compensation to
a contractor after a contract has been made, the policy expressed
therein is sound and, in view of the case law cited above, should be
adhered to by the Executive branch of government.
Finally, there are, of course, the constitutional and statutory re-
quirements of competitive bidding. See Article III,§ 22 of the Penn-
sylvania Constitut10n and 71P.S.§633. The clear intention of these
provisions would be frustrated if vendors would be allowed to
renegotiate contract prices in contracts awarded as a result of com-
petitive bids.
In conclusion, therefore, it is our opinion, and you are so advised,
that the Department of Property and Supplies may not negotiate an
increase in the price of coal to be supplied to the Commonwealth by
vendors who have contracts with the State.
Sincerely yours,
Theodore A. Adler
Deputy Attorney General
Israel Packel
Attorney General