Regl. 6302, art. 405(b)(9)-6.3
of this method, or shall void the
Length: 5,118 wordsOfficial source
Cite as Reglamento Núm. 6302, Art. 405(b)(9)-6.3
sampling run.
Immediately after component changes,
leak-checks are optional; if such leak-checks
are done, the procedure outlined in Section
4.1.4.1 above shall be used.
4.1.4.3 Post-test Leak-Check. A leakcheck is mandatory at the conclusion of each
sampling run. The leak-check shall be done
in accordance with the procedures outlined
in Section 4.1.4.1, except that it shall be conducted at a vacuum equal to or greater than
the maximum value reached during the sampling run. If the leakage rate is found to be
no greater than 0.00057 m 3/min (0.02 cfm) or 4
percent of the average sampling rate (whichever is less). the results are acceptable. and
no correction need be applied to the total
volume of dry gas metered. If. however, a
higher leakage rate is obtained, the tester
shall either record the leakage rate and correct the sample volume as shown in Section
6.3 of this method, or shall void the sampling
run.
4.1.5 Particulate Train Operation. During
the sampling run, maintain an Isokinetic
sampling rate (within 10 percent of true
isokinetic unless otherwise specified by the
Administrator) and a temperature around
the filter of 120±14 °C (248±25 °F), or such
other temperature as specified by an applicable subpart of the standards or approved by
the Administrator.
For each run. record the data required on
a data sheet such as the one shown in Figure
5-2. Be sure to record the initial dry gas
meter reading. Record the dry gas meter
readings at the beginning and end of each
sampling time increment, when changes in
flow rates are made, before and after each
leak-check, and when sampling is halted.
Take other readings required by Figure 5-2
at least once at each sample point during
each time increment and additional readings
when significant changes (20 percent variation in velocity head readings) necessitate
additional adjustments in flow rate. Level
and zero the manometer. Because the manometer level and zero may drift due to vibrations and temperature changes, make
periodic checks during the traverse.
Clean the portholes prior to the test run to
minimize the chance of sampling deposited
material. To begin sampling, remove the
nozzle cap, verify that the filter and probe
heating systems are up to temperature, and
that the pitot tube and probe are properly
positioned. Position the nozzle at the first
traverse point with the tip pointing directly
Into the gas stream. Immediately start the
pump and adjust the flow to isokinetic conditions. Nomographs are available, which aid
in the rapid adjustment of the Isokinetic
sampling rate without excessive computations. These nomographs are designed for use
when the Type S pitot tube coefficient is
0.85±0.02, and the stack gas equivalent density (dry molecular weight) is equal to 29±4.
APTD-0576 details the procedure for using
the nomographs. If Cₚ and Md are outside the
above stated ranges do not use the
nomographs unless appropriate steps (see Citation 7 in Bibliography) are taken to compensate for the deviations.
FIGURE 5-2-PARTICULATE FIELD DATA
Environmental Protection Agency, EPA
Plant
Location
Operator
Date
Run No
Sample box No
Meter box No
Mater A H@
C factor
Pitot tube coefficient, Cp
Ambient temperature
Barometric pressure
Assumed moisture, %
Probe length, m. (ft.)
Nozzle identification No.
Average calibrated nozzle diameter, CM (in.)
Probe heater setting
Leak rate, m3/min, (cfm)
Probe liner material
Static pressure, mm. Hg (in. Hg)
Filter No.
SCHEMATIC OF STACK CROSS SECTION
173
Gas sample temperature at
Temperature of
Traverse point
Sampling
number
time
Vacuum
Stack term-
Pressure differenperature
Velocity head
tial across orifice
Gas sample
dry gas meter
Filter holder
gas leaving conmeter
volume
temperature
denser or last im-
Inlet
Outlet
pinger
(e). min.
mm Hg (in.
(Ts). °C (°F)
(A Ps). mm
mm H2O (in. H20)
m³ (ft3)
°C (°F)
°C (°F)
°C (F)
°C (°F)
Hg)
(in.) H2O
Total
Average
Pt. 60, App. A, Meth. 5
Pt. 60, App. A, Meth. 5
When the stack is under significant negative pressure (height of impinger stem), take
care to close the coarse adjust valve before
inserting the probe into the stack to prevent
water from backing Into the filter holder. If
necessary, the pump may be turned on with
the coarse adjust valve closed.
When the probe is In position. block off the
openings around the probe and porthole to
prevent unrepresentative dilution of the gas
stream.
Traverse the stack cross-section, as required by Method 1 or as specified by the Administrator. being careful not to bump the
probe nozzle into the stack walls when sampling near the walls or when removing or Inserting the probe through the portholes; this
minimizes the chance of extracting deposited
material.
During the test run, make periodic adjustments to keep the temperature around the
filter holder at the proper level; add more ice
and, If necessary, salt to maintain a temperature of less than 20 °C (68 °F) at the condenser/silica gel outlet. Also, periodically
check the level and zero of the manometer.
If the pressure drop across the filter becomes too high, making isokinetic sampling
difficult to maintain, the filter may be replaced in the midst of a sample run. It is recommended that another complete filter assembly be used rather than attempting to
change the filter itself. Before a new filter
assembly is installed, conduct a leak-check
(see Section 4.1.4.2). The total particulate
weight shall Include the summation of all
filter assembly catches.
A single train shall be used for the entire
sample run, except in cases where simultaneous sampling is required in two or more
separate ducts or at two or more different locations within the same duct, or, in cases
where equipment failure necessitates a
change of trains. In all other situations, the
use of two or more trains will be subject to
the approval of the Administrator.
Note that when two or more trains are
used, separate analyses of the front-half and
(if applicable) impinger catches from each
train shall be performed, unless identical
nozzle sizes were used on all trains, in which
case, the front-half catches from the individual trains may be combined (as may the
impinger catches) and one analysis of fronthalf catch and one analysis of Impinger
catch may be performed. Consult with the
Administrator for details concerning the calculation of results when two or more trains
are used.
At the end of the sample run, turn off the
coarse adjust valve, remove the probe and
nozzle from the stack, turn off the pump.
record the final dry gas meter reading, and
conduct a post-test leak-check, as outlined
in Section 4.1.4.3. Also, leak-check the pitot
lines as described in Method 2, Section 3.1;
the lines must pass this leak-check, in order
to validate the velocity head data.
4.1.6 Calculation of Percent Isokinetic.
Calculate percent Isokinetic (see Calculations, Section 6) to determine whether the
run was valid or another test run should be
made. If there was difficulty in maintaining
Isokinetic rates due to source conditions.
consult with the Administrator for possible
variance on the isokinetic rates.
4.2 Sample Recovery. Proper cleanup procedure begins as soon as the probe is removed from the stack at the end of the sampling period. Allow the probe to cool.
When the probe can be safely handled. wipe
off all external particulate matter near the
tip of the probe nozzle and place a cap over
it to prevent losing or gaining particulate
matter. Do not cap off the probe tip tightly
while the sampling train is cooling down as
this would create a vacuum in the filter
holder, thus drawing water from the
impingers into the filter holder.
Before moving the sample train to the
cleanup site, remove the probe from the sample train, wipe off the silicone grease, and
cap the open outlet of the probe. Be careful
not to lose any condensate that might be
present. Wipe off the silicone grease from the
filter Inlet where the probe was fastened and
cap it. Remove the umbilical cord from the
last Impinger and cap the impinger. If a
flexible line is used between the first impinger or condenser and the filter holder, disconnect the line at the filter holder and let
any condensed water or liquid drain into the
impingers or condenser. After wiping off the
silicone grease. cap off the filter holder outlet and impinger inlet. Either ground-glass
stoppers, plastic caps, or serum caps may be
used to close these openings.
Transfer the probe and filter-impinger assembly to the cleanup area. This area should
be clean and protected from the wind so that
the chances of contaminating or losing the
sample will be minimized.
Save a portion of the acetone used for
cleanup as a blank. Take 200 ml of this acetone directly from the wash bottle being
used and place It in a glass sample container
labeled "acetone blank."
Inspect the train prior to and during disassembly and note any abnormal conditions.
Treat the samples as follows:
Container No. 1. Carefully remove the filter
from the filter holder and place It in Its identified petri dish container. Use a pair of
tweezers and/or clean disposable surgical
gloves to handle the filter. If it is necessary
to fold the filter, do so such that the particulate cake is inside the fold. Carefully transfer to the petri dish any particulate matter
and/or filter fibers which adhere to the filter
holder gasket. by using a dry Nylon bristle
brush and/or a sharp-edged blade. Seal the
container.
Environmental Protection Agency, EPA
Container No. 2. Taking care to see that
dust on the outside of the probe or other exterior surfaces does not get into the sample,
quantitatively recover particulate matter or
any condensate from the probe nozzle, probe
fitting, probe liner, and front half of the filter holder by washing these components with
acetone and placing the wash in a glass container. Distilled water may be used instead
of acetone when approved by the Administrator and shall be used when specified by
the Administrator: in these cases, save a
water blank and follow the Administrator's
directions on analysis. Perform the acetone
rinses as follows:
Carefully remove the probe nozzle and
clean the inside surface by rinsing with acetone from a wash bottle and brushing with a
Nylon bristle brush. Brush until the acetone
rinse shows no visible particles, after which
make a final rinse of the inside surface with
acetone.
Brush and rinse the inside parts of the
Swagelok fitting with acetone in a similar
way until no visible particles remain.
Rinse the probe liner with acetone by tilting and rotating the probe while squirting
acetone Into its upper end so that all inside
surfaces will be wetted with acetone. Let the
acetone drain from the lower end into the
sample container. A funnel (glass or polyethylene) may be used to aid on transferring
liquid washes to the container. Follow the
acetone rinse with a probe brush. Hold the
probe in an inclined position, squirt acetone
Into the upper end as the probe brush is
being pushed with a twisting action through
the probe; hold a sample container underneath the lower end of the probe, and catch
any acetone and particulate matter which is
brushed from the probe. Run the brush
through the probe three times or more until
no visible particulate matter is carried out
with the acetone or until none remains in
the probe liner on visual inspection. With
stainless steel or other metal probes, run the
brush through in the above prescribed manner at least six times since metal probes
have small crevices in which particulate
matter can be entrapped. Rinse the brush
with acetone, and quantitatively collect
these washings in the sample container.
After the brushing, make a final acetone
rinse of the probe as described above.
It is recommended that two people clean
the probe to minimize sample losses. Between sampling runs, keep brushes clean and
protected from contaminations.
After ensuring that all joints have been
wiped clean of silicone grease, clean the inside of the front half of the filter holder by
rubbing the surfaces with a Nylon bristle
brush and rinsing with acetone. Rinse each
surface three times or more if needed to remove visible particulate. Make a final rinse
of the brush and filter holder. Carefully rinse
out the glass cyclone, also (if applicable).
After all acetone washings and particulate
matter have been collected in the sample
container, tighten the lid on the sample container so that acetone will not leak out when
it is shipped to the laboratory. Mark the
height of the fluid level to determine whether or not leakage occured during transport.
Label the container to clearly identify its
contents.
Container No. 3. Note the color of the indicating silica gel to determine if it has been
completely spent and make a notation of its
condition. Transfer the silica gel from the
fourth Impinger to its original container and
seal. A funnel may make it easier to pour
the silica gel without spilling. A rubber policeman may be used as an aid in removing
the silica gel from the impinger. It is not
necessary to remove the small amount of
dust particles that may adhere to the impinger wall and are difficult to remove.
Since the gain in weight is to be used for
moisture calculations, do not use any water
or other liquids to transfer the silica gel. If
a balance is available in the field, follow the
procedure for container No. 3 in Section 4.3.
Impinger Water. Treat the impingers as follows; Make a notation of any color or film in
the liquid catch. Measure the liquid which is
in the first three Impingers to within +1 ml
by using a graduated cylinder or by weighing
It to within +0.5 g by using a balance (if one
is available). Record the volume or weight of
liquid present. This information is required
to calculate the moisture content of the effluent gas.
Discard the liquid after measuring and recording the volume or weight, unless analysis of the impinger catch is required (see
Note, Section 2.1.7).
If a different type of condenser is used,
measure the amount of moisture condensed
either volumetrically or gravimetrically.
Whenever possible. containers should be
shipped in such a way that they remain upright at all times.
4.3 Analysis. Record the data required on
a sheet such as the one shown in Figure 5-3.
Handle each sample container as follows:
FIGURE 5-3-ANALYTICAL DATA
Plant
Date
Run No.
Filter No.
Amount liquid lost during transport
Acetone blank volume, ml
Acetone wash volume, ml
Acetone blank concentration, mg/mg (Equation 5-4)
Container
Weight of particulate collected, mg
number
Final weight
Tare weight
Weight gain
1.
Acetone wash blank, mg (Equation 5-5)
Pt. 60, App. A, Meth. 5
Container
Weight of particulate collected. mg
number
Final weight
Tare weight
Weight gain
2.
Total.
Less acetone
blank.
Weight of
particulate
matter.
Volume of liquid water collected
Impinger vol-
Silica gel
ume, ml
weight, 9
Final.
Initial.
Liquid collected.
Total volume collected
9*
ml
*Convert weight of water to volume by dividing total weight
increase by density of water (1 g/ml).
EC16NO91.124
Container No. 1. Leave the contents in the
shipping container or transfer the filter and
any loose particulate from the sample container to a tared glass weighing dish. Desiccate for 24 hours in a desiccator containing
anhydrous calcium sulfate. Weigh to a constant weight and report the results to the
nearest 0.1 mg. For purposes of this Section,
4.3, the term "constant weight" means a difference of no more than 0.5 mg or 1 percent
of total weight less tare weight, whichever is
greater, between two consecutive weighings,
with no less than 6 hours of desiccation time
between weighings.
Alternatively. the sample may be oven
dried at 105 °C (220 °F) for 2 to 3 hours, cooled
in the desiccator, and weighed to a constant
weight, unless otherwise specified by the Administrator. The tester may also opt to oven
dry the sample at 105 °C (220 °F) for 2 to 3
hours, weigh the sample, and use this weight
as a final weight.
40 CFR Ch. I (7-1-99 Edition)
Container No. 2. Note the level of liquid in
the container and confirm on the analysis
sheet whether or not leakage occurred during transport. If a noticeable amount of
leakage has occurred, either void the sample
or use methods, subject to the approval of
the Administrator, to correct the final results. Measure the liquid In this container elther volumetrically to +1 ml or gravimetrically to ±0.5 g. Transfer the contents to a
tared 250-ml beaker and evaporate to dryness
at ambient temperature and pressure. Desiccate for 24 hours and weigh to a constant
weight. Report the results to the nearest 0.1
mg.
Container No. 3. Weigh the spent silica gel
(or silica gel plus impinger) to the nearest 0.5
g using a balance. This step may be conducted in the field.
"Acetone Blank" Container. Measure acetone in this container either volumetrically
or gravimetrically. Transfer the acetone to a
tared 250-ml beaker and evaporate to dryness
at ambient temperature and pressure. Desiccate for 24 hours and weigh to a constant
weight. Report the results to the nearest 0.1
mg.
NOTE: At the option of the tester, the contents of Container No. 2 as well as the acetone blank container may be evaporated at
temperatures higher than ambient. If evaporation is done at an elevated temperature,
the temperature must be below the boiling
point of the solvent; also, to prevent "bumping." the evaporation process must be closely supervised, and the contents of the beaker
must be swirled occasionally to maintain an
even temperature. Use extreme care. as acetone is highly flammable and has a low flash
point.
4.4 Quality Control Procedures. The following quality control procedures are suggested to check the volume metering system
calibration values at the field test site prior
to sample collection. These procedures are
optional for the tester.
4.4.1 Meter Orifice Check. Using the callbration data obtained during the calibration
procedure described in Section 5.3, determine
the A H@ for the metering system orifice.
The 4 H@ Is the orifice pressure differential
in units of In. H2O that correlates to 0.75 cfm
of air at 528° R and 29.92 in. Hg. The A H@ is
calculated as follows:
EC16NO91.125
Where:
AH=Average pressure differential across the
orifice meter, in. H 20.
Tₘ=Absolute average dry gas meter temperature, R.
Pta.=Barometric pressure. in. Hg.
e=Total sampling time, min.
Y=Dry gas meter calibration factor.
dimensionless.
Vₘ=Volume of gas sample as measured by
dry gas meter, dcf.
0.0319=(0.0567 in. Hg/ R) x (0.75 cfm)2.
Before beginning the field test (a set of three
runs usually constitutes a field test). operate
the metering system (i.e., pump, volume
meter, and orifice) at the A H@ pressure differential for 10 minutes. Record the volume
collected, the dry gas meter temperature,
and the barometric pressure. Calculate a dry
gas meter calibration check value, Y., as follows:
Environmental Protection Agency, EPA
Pt. 60, App. A, Meth. 5
EN30AU93.032
Eq. 5-10
Where:
Ye=Dry gas meter calibration check value,
dimensionless.
10=10 minutes of run time.
Compare the Y. value with the dry gas meter
calibration factor Y to determine that:
0.97Y< Ye<1.03Y
If the Y. value is not within this range, the
volume metering system should be investigated before beginning the test.
4.4.2 Calibrated Critical Orifice. A callbrated critical orifice, calibrated against a
wet test meter or spirometer and designed to
be inserted at the inlet of the sampling
meter box may be used as a quality control
check by following the procedure of Section
7.2.
5. Callbration
Maintain a laboratory log of all calibrations.
5.1 Probe Nozzle. Probe nozzles shall be
calibrated before their initial use in the
field. Using a micrometer, measure the Inside diameter of the nozzle to the nearest
0.025 mm (0.001 in.). Make three separate
measurements using different diameters
each time, and obtain the average of the
measurements. The difference between the
high and low numbers shall not exceed 0.1
mm (0.004 in.). When nozzles become nicked,
dented, or corroded, they shall be reshaped.
sharpened, and recalibrated before use. Each
nozzle shall be permanently and uniquely
identified.
5.2 Pitot Tube. The Type S pitot tube assembly shall be calibrated according to the
procedure outlined in Section 4 of Method 2.
5.3 Metering System.
5.3.1 Calibration Prior to Use. Before its
initial use in the field, the metering system
shall be calibrated as follows: Connect the
metering system inlet to the outlet of a wet
test meter that is accurate to within 1 percent. Refer to Figure 5.5. The wet test meter
should have a capacity of 30 liters/rev (1 ft 3/
rev). A spirometer of 400 liters (14 ft3) or
more capacity. or equivalent, may be used
for this calibration, although a wet test
meter is usually more practical. The wet test
meter should be periodically calibrated with
a spirometer or a liquid displacement meter
to ensure the accuracy of the wet test meter.
Spirometers or wet test meters of other sizes
may be used, provided that the specified accuracles of the procedure are maintained.
Run the metering system pump for about 15
minutes with the orifice manometer indicating a median reading as expected in field
use to allow the pump to warm up and to
permit the interior surface of the wet test
meter to be thoroughly wetted. Then, at
each of a minimum of three orifice manometer settings. pass an exact quantity of gas
through the wet test meter and note the gas
volume indicated by the dry gas meter. Also
note the barometric pressure, and the temperatures of the wet test meter, the inlet of
the dry gas meter, and the outlet of the dry
gas meter. Select the highest and lowest orlfice settings to bracket the expected field operating range of the orifice. Use a minimum
volume of 0.15 m³ (5 cf) at all orifice settings.
Record all the data on a form similar to Figure 5.6, and calculate Y, the dry gas meter
calibration factor, and AH@. the orifice calibration factor, at each orifice setting as
shown on Figure 5.6. Allowable tolerances for
Individual Y and AH@. values are given in
Figure 5.6. Use the average of the Y values in
the calculations in Section 6.
EC01JN92.102
EC01JN92.103
Before calibrating the metering system. it
is suggested that a leak-check be conducted.
For metering systems having diaphragm
pumps, the normal leak-check procedure will
not detect leakages within the pump. For
these cases the following leak-check procedure is suggested: make a 10-minute calibration run at 0.00057m 3/min (0.02 cfm): at the
end of the run, take the difference of the
measured wet test meter and dry gas meter
volumes: divide the difference by 10, to get
the leak rate. The leak rate should not exceed 0.00057 /min (0.02 cfm).
5.3.2 Calibration After Use. After each
field use, the calibration of the metering system shall be checked by performing three
calibration runs at a single, intermediate
orifice setting (based on the previous field
test), with the vacuum set at the maximum
value reached during the test series. To adjust the vacuum, insert a valve between the
wet test meter and the Inlet of the metering
system. Calculate the average value of the
dry gas meter calibration factor. If the value
has changed by more than 5 percent, recalibrate the meter over the full range of orifice
settings, as previously detailed.
Alternative procedures. e.g., rechecking
the orifice meter coefficient may be used,
subject to the approval of the Administrator.
5.3.3 Acceptable Variation in Calibration.
If the dry gas meter coefficient values obtained before and after a test series differ by
more than 5 percent, the test series shall elther be voided, or calculations for the test
series shall be performed using whichever
meter coefficient value (i.e., before or after)
gives the lower value of total sample volume.
5.4 Probe Heater Calibration. The probe
heating system shall be calibrated before its
initial use in the field.
Use a heat source to generate air heated to
selected temperatures that approximate
those expected to occur in the sources to be
sampled. Pass this air through the probe at
a typical simple flow rate while measuring
the probe inlet and outlet temperatures at
various probe heater settings. For each air
temperature generated, construct a graph of
probe heating system setting versus probe
outlet temperature. The procedure outlined
in APTD-0576 can also be used. Probes constructed according to APTD-0581 need not be
calibrated if the calibration curves in APTD-
0576 are used. Also, probes with outlet temperature monitoring capabilities do not require calibration.
5.5 Temperature Gauges. Use the procedure in Section 4.3 of Method 2 to calibrate
In-stack temperature gauges. Dial thermometers, such as are used for the dry gas meter
and condenser outlet, shall be calibrated
against mercury-in-glass thermometers.
5.6 Leak Check of Metering System
Shown in Figure 5-1. That portion of the
sampling train from the pump to the orifice
meter should be leak checked prior to initial
use and after each shipment. Leakage after
the pump will result in less volume being recorded than is actually sampled. The following procedure is suggested (see Figure 5-
4): Close the main valve on the meter box.
Insert a one-hole rubber stopper with rubber
tubing attached into the orifice exhaust
pipe. Disconnect and vent the low side of the
orifice manometer. Close off the low side orifice tap. Pressurize the system to 13 to 18 cm
(5 to 7 in.) water column by blowing into the
rubber tubing. Pinch off the tubing and observe the manometer for one minute. A loss
of pressure on the manometer indicates a
leak in the meter box; leaks. if present. must
be corrected.
5.7 Barometer. Calibrate against a mercury barometer.
6. Calculations
Carry out calculations, retaining at least
one extra decimal figure beyond that of the
acquired data. Round off figures after the
final calculation. Other forms of the equations may be used as long as they give equivalent results.
EC01JN92.104
6.1 Nomenclature
An=Cross-sectional area of nozzle. m²(ft2 ).
Bws=Water vapor in the gas stream. proportion by volume.
Ca=Acetone blank residue concentration, mg/
mg.
40 CFR Ch. I (7-1-99 Edition)
Pt. 60, App. A, Meth. 5
c₂=Concentration of particulate matter in
stack gas, dry basis, corrected to standard conditions, g/dscm (g/dscf).
/=Percent of isokinetic sampling.
La=Maximum acceptable leakage rate for either a pretest leak check or for a leak
check following a component change;
equal to 0.00057 m 3/min (0.02 cfm) or 4 percent of the average sampling rate, whichever is less.
L,Individual leakage rate observed during
the leak check conducted prior to the
"th" component change (/=1, 2, n),
m3/min (cfm).
Lₙ=Leakage rate observed during the posttest leak check. m³/min (cfm).
ma=Mass of residue of acetone after evaporation, mg.
mₙ=Total amount of particulate matter collected, mg.
Mw=Molecular weight of water. 18.0 g/g-mole
(18.01b/lb-mole).
Phar=Barometric pressure at the sampling
site. mm Hg (in. Hg).
P,=Absolute stack gas pressure. mm Hg (in.
Hg).
Pstd=Standard absolute pressure. 760 mm Hg
(29.92 in. Hg).
R=Ideal gas constant. 0.06236 mm Hg-m 3/K-g-
mole (21.85 in. Hg-ft 3/R-lb-mole).
Tₘ=Absolute average dry gas meter temperature (see Figure 5-2). °K (°R).
T.=Absolute average stack gas temperature
(see Figure 5-2), °K (°R).
Tatd=Standard absolute temperature, 293°K
(528° R).
Va=Volume of acetone blank, ml.
Vaw=Volume of acetone used in wash, ml.
Vₖ=Total volume of liquid collected in
impingers and silica gel (see Figure 5-3).
ml.
Vₘ=Volume of gas sample as measured by
dry gas meter. dem (dsef).
Vm(sta)=Volume of gas sample measured by
the dry gas meter, corrected to standard
conditions, dscm (dscf).
Vw(sta)=Volume of water vapor in the gas
sample, corrected to standard conditions.
scm (scf).
v-Stack gas velocity. calculated by Method
2. Equation 2-9, using data obtained from
Method 5. m/sec (ft/sec).
Wo=Weight of residue in acetone wash, mg.
Y=Dry gas meter calibration factor.
AH-Average pressure differential across the
orifice meter (see Figure 5-2). mm H₂O
(in. H₂O).
Density of acetone, mg/ml (see label on
bottle).
*wDensity of water, 0.9982 g/ml (0.002201 lb/
ml).
ε=Total sampling time, min.
ε,-Sampling time interval, from the beginning of a run until the first component
change. min.
ε=Sampling time interval. between two successive component changes, beginning
with the interval between the first and
second changes, min.
&=Sampling time interval, from the final
(nth) component change until the end of
the sampling run, min.
13.6=Specific gravity of mercury.
60=Sec/min.
100=Conversion to percent.
6.2 Average Dry Gas Meter Temperature
and Average Orifice Pressure Drop. See data
sheet (Figure 5-2).
6.3 Dry Gas Volume. Correct the sample
volume measured by the dry gas meter to
standard conditions (20 °C, 760 mm Hg or 68
°F. 29.92 in. Hg) by using Equation 5-1.
EC01JN92.105
Where:
K1=0.3858 °K/mm Hg for metric units
=17.64 °R/in. Hg for English units
NOTE: Equation 5-1 can be used as written
unless the leakage rate observed during any
of the mandatory leak checks (i.e., the posttest leak check or leak checks conducted
prior to component changes) exceeds La. If
Lp or , exceeds La Equation 5-1 must be
modified as follows:
(a) Case I. No component changes made
during sampling run. In this case, replace Vₘ
in Equation 5-1 with the expression:
(b) Case II. One or more component
changes made during the sampling run. In
this case, replace Vₘ in Equation 5-1 by the
expression:
EC01JN92.106
and substitute only for those leakage rates
(L, or Lp) which exceed L₂
6.4 Volume of Water Vapor.
EC01JN92.107
Where:
K₂=0.001333 m 3/ml for metric units
=0.04707 ft3/ml for English units.
6.5 Moisture Content.
Environmental Protection Agency, EPA
EC16NO91.126
NOTE: In saturated or water droplet-laden
gas streams, two calculations of the moisture content of the stack gas shall be made,
one from the Impinger analysis (Equation 5-
3). and a second from the assumption of saturated conditions. The lower of the two values
of Bws shall be considered correct. The procedure for determining the moisture content
based upon assumption of saturated conditions is given in the Note of Section 1.2 of
Method 4. For the purposes of this method,
the average stack gas temperature from Figure 5-2 may be used to make this determination. provided that the accuracy of the Instack temperature sensor is + 1 °C (2 °F).
6.6 Acetone Blank Concentration.
EC16NO91.127
6.7 Acetone Wash Blank.
EC16NO91.128
6.8 Total Particulate Weight. Determine
the total particulate catch from the sum of
the weights obtained from Containers 1 and
2 less the acetone blank (see Figure 5-3).
NOTE: Refer to Section 4.1.5 to assist in calculation of results Involving two or more fllter assemblies or two or more sampling
trains.
6.9 Particulate Concentration.
c₁=(0.001 gimg) (m/Vm(sxi)
6.10 Conversion Factors:
Eq. 5-6
From
To
Multiply by
scf
m³
0.02832.
9
mg
0.001
g/ft³
gr/ft³
15.43.
g/ft3
lb/ft3
2.205x10-3
g/ft³
g/m³