Regl. 7998, art. 11.5 dup3
if said delay impacts the critical path.
Length: 7,341 wordsOfficial source
Cite as Reglamento Núm. 7998, Art. 11.5 dup3
6.7 Patent, Fees and Royalties
6.7.1. Contractor shall pay all license fees and royalties and assume all costs incident to the use, in the performance
of the Work or the incorporation in the Work, of any invention, design, process, product, or device which is the
subject or patent rights or copyrights held by others.
6.7.2. If a particular invention, design, process, product, or device is specified in the Contract Documents for use in the
performance of the Work and if to the actual knowledge of Owner or Architect/Engineer its use is subject to patent
rights or copyrights calling for the payment of any license fee or royalty to others, the existence of such rights shall be
disclosed by Owner in the Contract Documents.
6.7.3 To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless
Owner, Architect/Engineer, Architect/Engineer's Consultants, and the officers, directors, partners, employees or
agents, and other consultants of each and any of them from and against all claims, costs, losses, and damages
(including but not limited to all fees and charges or engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to any infringement of patent rights or
copyrights incident to the use in the performance of the Work or resulting from the incorporation in the Work of any
invention, design, process, product, or device not specified in the Contract Documents.
6.8 Permits
6.8.1. Unless otherwise indicated in the Contract Documents, the responsibilities for securing and paying for permits,
governmental fees and licenses for work to be performed are as follows:
6.8.1.1. To obtain the Construction Permit, the Contractor shall pay the premiums to secure the State insurance
Fund policy and the Municipal Construction Taxes, at the rate that is in effect at bid date, unless the Contractor is
explicitly not obligated to pay said taxes under the terms and provisions of the Contract Documents, in which
case, shall so be specifically stated in the Contract Documents. The Owner shall secure all the Architect or
Engineer's and Owner's Representative's certificates necessary and pertinent needed to secure the Construction
Permit as well as submit applications and secure the permits for the Plan CES and for the Federal Storm Water
Drainage plan, if same is required for the Project.
6.8.1.2. To obtain the Use Permit, the Contractor shall secure the endorsements required for said Use Permit from all
government agencies, unless one or more of these cannot be obtained due to circumstances beyond the control of the
- 40
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
Contractor. The Owner must ascertain that the reports required for the Use Permit from the Architect or Engineer
and Owner's Representative are duly filed with "Oficina de Gerencia de Permisos" and must also obtain any of
the above mentioned endorsements that cannot be obtained due to circumstances beyond the control of Contractor.
6.8.1.3. All payments due, or to become due, to any agency, public or private, for connection to, or improvement of
any of said agencies' infrastructure (Impact Fees) shall be paid by the Owner with sufficient time so as not to
adversely affect the critical path of the Work.
6.8.1.4. The Contractor shall secure and pay for all incidental permits required for the completion of the Work,
unless such incidental permits deviate from the normal procedures, or costs, of the requiring agency and shall do
so in a timely manner so as not to adversely affect the critical path of the Work.
6.8.1.5. Any other fees or charges related to permitting to be paid by the Contractor will be indicated in the special
conditions.
6.8.1.6. The duties of Owner and of Contactor stated in this Article 6.8 shall be performed in a timely manner as to not adversely
affect the critical path of the Work.
6.9 Laws and Regulations
6.9.1. Contractor shall give all notices and comply with all Laws and Regulations applicable to the performance
of the Work.
6.9.1.1. Except where otherwise expressly required by applicable Laws and Regulations, neither Owner, nor
Owner's Representative nor Architect/Engineer shall be responsible for monitoring Contractor's compliance
with any Laws or Regulations.
6.9.1.2. Should the Contractor observe that the Contract Documents are at variance with any Federal,
Commonwealth and Municipal laws, ordinances, rules, regulations, by-laws, and all orders or decrees, he shall
promptly notify the Owner's Representative in writing and the Owner's Representative shall instruct the Contractor,
also in writing, as to how Contractor is to proceed. Any additional cost and /or extra time incurred by the
Contractor to comply with Laws and Regulations enacted after the bid opening date, it may file a claim for
equitable adjustment of the Contract Price or the Contract Time or both, as shall any decrease in cost or time
resulting therefrom.
6.9.1.3. If the Contractor performs any work knowing it to be contrary to Federal, Commonwealth and Municipal
laws, ordinances, rules, regulations, by-laws, orders or decrees, the Contractor shall assume full responsibility therefore,
and shall bear all cost arising there from.
6.9.1.4. The Contractor shall save the Owner and its authorized representatives harmless from any claim or
liability arising from or based on the infraction or violation of any such laws, ordinances, rules, regulations, by-laws, all
orders or decrees, except if the infractions or violations are caused by acts of the Owner, or of Owner's authorized
representatives.
6.9.1.5. If Contractor performs any Work knowing or having reason to know that he is acting contrary to said Laws or
Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not limited to all fees and
charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute
resolution costs) incurred as a consequence thereof. It shall not be Contractor's primary responsibility to make certain
41 -
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
that the Specifications and Drawings are in accordance with Laws and Regulations, but this shall not release
Contractor of Contractor's obligations hereunder.
6.10 Taxes
6.10.1. Contractor shall pay all sales, consumer, use, and other similar taxes required to be paid by Contractor
in accordance with the Laws and Regulations of the place of the Project which are applicable during the performance
of the Work and which were in effect at the bid opening date.
6.10.1.1. Among said taxes, the Contractor shall pay the municipal construction taxes applicable to the Project in
a timely fashion, but no later than fifteen (15) calendar days after the first partial (certification) payment is made by the
Owner to Contractor.
6.10.1.2. If specifically stated in the Contract Documents, the Municipal Construction tax rate may be determined
between Owner and the municipal government where the project is to be located, in such case a specific rate shall
be established by the mayor and the municipal legislature, and notified to the Contractor before bid time. If no
such rate is indicated in the Contract Documents regarding such arrangement between Owner and the municipal
government, then the Contractor shall pay at the rates prevailing at the time of the bid.
6.10.1.1.1. The Contractor shall furnish and deliver to the Owner written evidence that said payment(s) was
made before the second partial (certification) payment is made by the Owner to Contractor.
6.10.1.1.2. In case that the Contractor does not furnish and deliver said evidence of payment, the Owner shall
deduct from said partial (certification) payments the undisputed amount of municipal tax plus any penalties and fines
and pay it directly to the municipality.
6.10.1.1.2.1. If the amount of the second partial (certification) payment is not enough to cover the total amount of
the municipal tax, the Owner shall continue to deduct from the following partial (certification) payments until the
undisputed amount is paid in full.
6.10.1.1.2.2. The direct payment provided for in Article 6.10.1.1.2 shall be effected after the retainage
required in Article 13.2.2 is deducted.
6.11 Use of Site and Other Areas
6.11.1. Limitation on Use of Site and Other Areas.
6.11.1.1. Contractor shall confine construction equipment, the storage of materials and equipment, and the
operations of workers to the Site and other areas permitted by Laws and Regulations, and shall not unreasonably
encumber the Site and other areas with construction equipment or other materials or equipment.
6.11.1.1.1. Contractor shall assume full responsibility for any damage to any such land or area, or to the Owner
or occupant thereof, or of any adjacent land or areas, resulting from the performance of the Work.
6.11.1.1.2. Should any claim be made by any such owner or occupant because of the performance of the Work,
Contractor shall promptly resolve the dispute with such other party by negotiation or otherwise resolve the claim by
arbitration or other dispute resolution proceeding or at law.
- 42 -
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
6.11.1.1.3. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold Owner,
Architect/Engineer, Architect/Engineer's Consultant, and the officers, directors, partners, employees, agents, and
other consultants of each and any of them harmless from and against all claims, costs, losses, and damages
(including but not limited to all fees and charges or engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to any claim or action, legal or equitable,
brought by any such owner or occupant against Owner, Architect/Engineer, or any other party indemnified hereunder
to the extent caused by or based upon Contractor's performance of the Work.
6.11.2. Removal of Debris during Performance of the Work.
6.11.2.1. During the progress of the Work, Contractor shall keep the Site and other areas free from excessive
accumulations of waste materials, rubbish, and other debris caused by his operations on the Site.
6.11.2.1.1. Removal and disposal of such waste materials, rubbish, and other debris shall conform to
applicable Laws and Regulations.
6.11.3. Cleaning.
6.11.3.1. Prior to Substantial Completion of the Work Contractor shall clean the Site and make it ready for
utilization by Owner.
6.11.3.1.1. At the completion of the Work Contractor shall remove from the Site all tools, appliances,
x
construction equipment and machinery, and surplus materials and shall restore to original condition all property
not designated for alteration by the Contract Documents.
6.11.3.1.1.1. If the Contractor fails to clean up as indicated above, the Owner may do so and the cost thereof shall
be charged to the Contractor.
6.11.4. Loading Structures.
6.11.4.1. Contractor shall not load nor permit any part of any structure to be loaded in any manner that will
endanger the structure, nor shall Contractor subject any part of the Work or adjacent property to stresses or
pressures that will endanger it.
6.11.4.2. Owner's Representative shall not permit any of the Owner's Other Contractors, his personnel, or any
other entity performing work for him directly at the Site, to load any part of any structure in any manner that will endanger
the structure, nor shall Owner's Representative subject any part of the Work or adjacent property to stresses or
pressures that will endanger it.
6.11.5. Rights To and Use of Materials Found On the Work.
6.11.5.1. The Contractor, with the prior written approval of the Owner's Representative, may use to perform
the Work materials obtained from existing structures at the Site which are to be removed that are determined by the
Owner's Representative to be acceptable for a use approved in writing by Owner's Representative.
6.11.5.2. Unless otherwise provided in the Contract Documents, material from any existing structures to be removed
may be used temporarily by the Contractor in the erection of new structures.
43
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
6.11.5.2.1. If the material is to be salvaged for the Owner, its modification will not be permitted except as approved by
the Owner's Representative.
6.11.5.2.2. Unless otherwise specified in the Contract Documents, all soil existing at the Project Site will be considered
fit to be used as fill in the performance of the Work if such soil meets the Project's field fill criteria.
6.12 Record Document
6.12.1. Contractor shall maintain in a safe place at the Site one (1) record copy of all Drawings, Specifications,
Addenda, Written Amendments, Change Orders, Extra Work Orders, Work Change Directives, Field Orders, permits,
and written interpretations and clarifications in good order and annotated showing changes made during construction.
6.12.1.1. Said documents together with all approved Samples and a counterpart of all approved Shop
Drawings will be available to Architect/Engineer and the Owner's Representative.
6.12.1.2. If not previously submitted, prior to Final Acceptance, said documents, Samples, and Shop Drawings
will be delivered to Owner's Representative for delivery to Owner.
6.13 Safety and Protection
6.13.1. Contractor shall be solely responsible for initiating, maintaining and supervising all safety precautions
and programs in connection with the Work. Contractor shall take all necessary precautions for the safety of, and shall
provide the necessary protection to prevent damage, injury or loss to:
6.13.1.1. all persons on the Site or who may be affected by the Work;
6.13.1.2. all the Work and materials and equipment to be incorporated therein, whether in storage on or off the
Site; and
6.13.1.3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks, pavements,
roadways, structures, utilities, and Underground Facilities not designated for removal, relocation, or replacement
in the course of construction.
6.13.2. Contractor shall comply with all applicable Laws and Regulations relating to the safety of persons or
property, or to the protection of persons or property from damage, injury, or loss; and shall erect and maintain all
necessary safeguards for such safety and protection.
6.13.2.1. Contractor shall notify owners of adjacent property and of Underground Facilities and utility owners when
prosecution of the Work may affect them, and shall cooperate with them in the protection, removal, relocation,
and replacement of their property.
6.13.2.2. All damage, injury, or loss to any property referred to in Articles 6.13.1.2 or 6.13.1.3 caused, directly or
indirectly, in whole or in part, by Contractor any Subcontractor, Supplier, or any other individual or entity directly or
indirectly employed by any of them to perform any of the Work, or anyone for whose acts any of them may be liable,
shall be remedied by Contractor (except damage or loss attributable to the fault of Drawings or Specifications or
to the acts or omissions of Owner or Architect/Engineer or Architect/Engineer's Consultant, or anyone employed by
any of them, or anyone for whose acts any of them may be liable, and not attributable, directly or indirectly, in whole or
in part, to the fault or negligence of Contractor or any Subcontractor, Supplier, or other individual or entity directly or
- 44 -
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
indirectly employed by any of them).
6.13.2.3. Contractor's duties and responsibilities for safety and for protection of the Work shall continue until
such time as all the Work is completed and Owner's Representative has issued a notice to Owner and Contractor of
Final Acceptance of the Work (except as otherwise expressly provided in connection with Substantial
Completion).
6.13.3. If so provided in the bid documents, the Owner has the right to establish any reasonable monetary
penalties for violations of this Section 6.13.
6.14 Safety Representative
6.14.1. Contractor shall designate a qualified and experienced safety representative at the Site whose duties and
responsibilities shall be the prevention of accidents and the maintaining and supervising of safety precautions and
programs. The safety representative at the Site may have other duties assigned to him.
6.15 Hazard Communication Programs
6.15.1. Contractor shall be responsible for coordinating any exchange of material safety data sheets or other hazard
communication information required to be made available at the Site in accordance with Laws or Regulations.
6.16 Plans and Working Drawings; As-Built Plans.
6.16.1. Plans and Working Drawings.
6.16.1.1. The detail Plans and Specifications for the Project have been prepared by licensed and collegiate
competent Architect/Engineer exercising reasonable care and are intended to show as clearly as is practicable the
Work required to be performed. Contractor will rely on the accuracy of said drawings, specifically in their compliance
with all applicable codes and regulations in effect on the bid opening date.
6.16.1.1.1. The Contractor realizes, however, that construction details cannot always be accurately anticipated and
that in executing the Work, field conditions may require reasonable minor modifications in the details of plans and
quantities of Work.
6.16.1.1.1.1. Therefore, all Work must be carried out taking into account the mentioned considerations as well as
field conditions, to the satisfaction of the Owner's Representative, and in accordance with his instructions and
with the Contract Documents.
6.16.2 Working Drawings
6.16.2.1. The Plans will be supplemented by such Working Drawings as are necessary to adequately control the
Work.
6.16.22. Working Drawings for structures shall be furnished by the Contractor and shall consist of such
detailed Plans as may be required to adequately control the Work and to complement the Plans furnished by the
Owner.
6.16.2.3. They shall include, among others, stress sheets, shop drawings, erection plans, false work plans,
45 -
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
cofferdam plans, bending diagrams for reinforcing steel or any other supplementary plans or similar data required of
the Contractor.
6.16.3. Working Drawings and related documents submitted for manufactured and shop-fabricated products shall be
accompanied by a certification from the manufacturer that the materials and/or equipment meet all the requirements
of the Specifications.
6.16.3.1. In the event that any item is not exactly in accordance with the requirements of the Plans and
Specifications, the certificate shall identify and explain each such difference.
6.16.4. Unless otherwise indicated, all Working Drawings are subject to review and acceptance by the Owner's
Representative.
6.16.4.1. Such review and acceptance shall not release the Contractor from any of his responsibilities for the
safe and successful completion of the Work.
6.16.4.2. The cost of preparing and furnishing all required Working Drawings is included in the Contract Price and no
separate payment will be made for such Drawings.
6.17 As Built Record Drawings
6.17.1. The Contractor shall keep at the Site a copy of the Drawings marked in a neat manner that record all
changes made during construction.
+
6.17.1.1. The set of provisional record Drawings shall be kept up to date and submitted for the inspection and approval
of the Owner's Representative, at least five (5) days prior to any partial monthly payment, unless otherwise required
in the Contract Documents.
6.17.2. Prior to Final Acceptance, the Contractor shall deliver the as built Drawings to the Owner's Representative.
6.17.2.1. These Drawings will be used as the draft for the preparation of the final As Built Drawings for the
Project by Architect/Engineer.
6.17.3. The Architect/Engineer will, with the full cooperation of Contractor and of the Owner's representative prepare
final as-built record drawings in reproducible form as reasonably required by Owner, to be delivered to the Owner.
6.17.3.1. The Owner will cause the Architect/Engineer to submit, with enough time so as not to adversely alter
the critical path of the Work, the revised as-built drawings to the required governmental entities and obtain the
approval of an amended Construction Permit, if same is required, and deliver the same to Owner and Contractor. This
amended Construction Permit will be used to obtain the Use Permit for the project.
6.18 Notice to Proceed.
6.18.1. After the Agreement has been executed, the Contractor will be formally notified to proceed with the Work or
service provided in the Contract Documents.
6.18.1.1. The Notice to Proceed will stipulate the date on which Owner expects the Contractor will begin
construction and the date on which Contract Time will commence to run.
46
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
6.18.1.2. Pre-Construction Conference.
6.18.1.2.1. Prior to the start of the Project the Owner will summon all interested parties to a Pre-construction
Conference in order to organize the start of the work and other matters. If no such conference is summoned by the
Owner, and in any event, the Contractor may start the Work on the date stated in the Notice to Proceed.
6.18.2. Prosecution and Progress.
6.18.2.1. After obtaining written permission issued by the Owner, the Contractor may assemble materials and
equipment and start preliminary Work as soon as he is notified of the award, but no responsibility for acceptance
and payment of the Work so performed shall be assumed by the Owner until and unless the Contract has been
executed and the order to proceed issued.
6.18.2.2. The rate of progress in the prosecution of the Work shall be compared in accordance with Articles
4.2 and 4.3 with approved Progress Schedule as the Work progresses.
6.18.2.2.1. If the Contractor is at fault for falling thirty (30) working days or more behind the approved schedule
or ten percent (10%) of Contract Time, whichever is less, Contractor shall submit a revised schedule for
completion of the Work within the Contract Time and modify his operations, including, but not limited to, working
overtime and on Saturdays, Sundays and legal holidays, to providing such additional materials, equipment and labor
as necessary to comply with the revised schedule. Any additional cost caused by the modified schedule will be
at Contractor's expense.
6.18.2.3. Should the prosecution of the Work be discontinued for any reason, the Contractor shall notify the
Owner's Representative at least twenty-four (24) hours in advance of resuming operations.
6.18.3. Conformity with Plans and Specifications.
6.18.3.1. All work performed and materials furnished shall be in reasonably close conformity with the Plans and
other Contract Documents requirements.
6.18.3.2. Plan dimensions and Contract Specification values are to be considered the target values to be
strived for and complied with as the design values to which any allowed tolerances are applied.
6.18.3.2.1. Materials and workmanship shall be uniform in character and shall be reasonably close to the
prescribed target value or to the middle portion of the tolerance range.
6.18.3.3. When the Specifications include an acceptance plan for any construction or characteristic of
materials, the acceptance plan will be used by the parties to determine the attainment of Reasonably Close
Conformity with plans and specifications and to assign a value to the non-conforming work which does not meet
that standard.
6.18.4 Cooperation with Utilities.
6.18.4.1. The Owner will notify all utility companies, all pipe line owners, or other parties affected, and
endeavor to have all necessary adjustments of the public or private utility fixtures, pipe lines, and other
47
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
appurtenances within or adjacent to the limits of construction, which are not to be performed by the Contractor,
made in accordance with the Project construction schedule.
6.18.4.2. Water lines, gas lines, wire lines, service connections, water and gas meter boxes, water and gas valve
boxes, light standards, cableways, signals, and all other utility appurtenances within the limits of the proposed
construction which are to be relocated or adjusted, are to be moved by their respective owners except for those to be
moved by the Contractor as specifically provided in the Contract Documents.
6.18.4.3. It is understood and agreed that the Contractor has considered in his proposal all of the permanent and
temporary utility appurtenances in their present or relocated positions as if same are shown on the plans and that no
additional compensation will be considered for any delays, inconvenience, or damages sustained by Contractor due
to any interference from the said known utility appurtenances or the operations of moving them, except in the case
of failure by a utility to reasonably comply with its responsibility in relocating or adjusting its facility as required.
6.18.4.4. Prior to commencing Work, the Contractor shall make arrangements to protect the properties of all public
and private utilities and other property within and adjacent to the Work area, if indicated in the Contract
Documents, from damage by his construction operations.
6.18.4.5. Contractor shall cooperate with the utility owners in the removal and rearrangement of any underground or
overhead utility lines or facilities to minimize interruption to service and duplication of work by the utility owners.
6.18.4.6. In the event of interruption to water or other utility services as a result of accidental breakage, or as a
result of being exposed or unsupported, the Contractor shall promptly notify the proper authorities and shall
cooperate with them in the restoration of service as promptly as possible.
6.18.4.7. Fire hydrants shall be kept accessible to the Fire Department at all times and no Work shall be
undertaken near fire hydrants until provisions for continued service have been made.
6.18.4.8. Contractor shall be responsible for the repair costs of any damage to utility facilities caused by his
equipment or operations, except for underground facilities whose existence or approximate location was
previously unknown.
6.18.5. Materials.
6.18.5.1. Source of Supply and Quality Requirements.
6.18.5.1.1. The materials used in the Work shall meet all quality requirements of the Contract Documents.
6.18.5.1.2. Unless otherwise provided in the Contract Documents, all materials used in the Work shall be
furnished by the Contractor from sources selected by the Contractor.
6.18.5.1.3. Materials will be tested and approved when delivered to the Project or in their final position after
incorporation to the Work as provided by the individual specifications.
6.18.5.1.4. At the option of the Owner's Representative, sources of materials may be given preliminary approval
before delivery is started.
6.18.5.2. Procurement and Delivery of Materials.
48 -
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
6.18.5.2.1. The Contractor shall schedule the delivery at the Site of all materials and equipment required for the
execution and completion of the Work at a time convenient to him SO as to avoid delays in the prosecution of the Work
and to allow completion of the Work within the Contract Time specified in the Contract Documents.
6.18.5.3. Earthwork Material Sources.
6.18.5.3.1. Designated Sources.
6.18.5.3.1.1. Specific sources of materials from offsite or onsite locations may be designated on the Plans
and described in the Contract Documents.
6.18.5.3.1.2. Unless otherwise provided in the Contract Documents, direct payment will be made for
development, preparation, erosion control, hauling and restoration of material sources or related work areas and
sites.
6.18.5.3.2. Contractor Sources.
6.18.5.3.2.1. When no materials sources are designated in the Contract Documents, or if the Contractor desires
to use materials from sources other than those designated, the Contractor shall be responsible for acquiring the
necessary rights to take materials from the sources selected, for determining that the materials meet the specified
requirements, and he shall bear all expenses for the exploration, development, erosion control and restoration of such
sources, and for all costs of hauling the materials. Contractor will make sure that his sources of materials have the
required permits.
6.18.5.4. Contractor's Quality Control.
6.18.5.4.1. The Contractor is responsible for the quality of all materials and workmanship furnished in the
construction of the Project.
6.18.5.4.1.1. If specifically required in the Supplementary General Conditions, the Contractor shall provide his own
quality control system and procedures including all personnel, equipment, supplies and facilities necessary to obtain
samples, perform tests, evaluate test results and adequately control his work in order to insure that all such
materials and workmanship meet the Contract requirements.
6.18.5.4.2. The Contractor shall, in all instances, perform his own process control sampling, testing and
inspection during all phases of the Work as often and at a rate sufficient to assure that the Work conforms to the
Contract requirements.
6.18.5.4.2.1. The Contractor shall insure that all of the testing equipment to be used is properly calibrated and
meets the specifications applicable to each specified test procedure.
6.18.5.4.3. The cost of complying with Contractor's quality control obligations referred to in Article 6.18.5.4 is
included in the Contract Price and no additional payment will be made therefore.
6.18.5.5. Storage of Materials.
49 -
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
6.18.5.5.1. Materials shall be so stored as to assure the preservation of their quality and fitness for
incorporation to the Work.
6.18.5.5.1.1. Stored materials, even though approved before storage, may again be inspected at any time
prior to or during their incorporation to the Work.
6.18.5.5.1.2. Stored materials shall be located so as to facilitate their prompt inspection.
6.18.5.5.2. When authorized by the Owner's Representative, portions of the Project Site may be used for storage
purposes and for the placing of the Contractor's plant/facilities and equipment provided that they are located so as not
to constitute a hazard to the construction of the Project or otherwise.
6.18.5.5.2.1. Any additional space required therefore must be provided by the Contractor at his expense.
6.18.5.5.3. Private property may be used for storage purpose with written permission of the Owner or lessee,
and, if requested by the Owner's Representative, copies of such written permission shall be furnished to him.
6.18.5.5.4. All temporary storage areas and plant sites shall be restored to their original condition by the
Contractor, at his expense, in a manner acceptable to the Owner's Representative.
6.18.5.6. Handling of Materials.
+
6.18.5.6.1. All materials shall be handled in such manner as to preserve their quality and fitness for incorporation
to the Work.
6.18.5.7. Materials Furnished by the Owner.
6.18.5.7.1. The Contractor shall furnish all materials required to complete the Work, except those indicated in
the Contract Documents to be furnished by the Owner.
6.18.5.7.2. Except as provided in Article 6.18.5.7.4, if the material to be furnished by the Owner is to be
delivered to the jobsite, the Owner, unless specified otherwise in the Contract Documents, will furnish the material to
the Contractor at no cost to the Contractor and the Owner will pay for all transportation, insurance, taxes and other
cost related to the furnishing of the material to the jobsite. Cost of unloading is included in the Contract Price and
Contractor shall receive no additional compensation for unloading.
6.18.5.7.3. If the material to be furnished by the Owner is to be delivered to the jobsite, the Contract Documents
will indicate the delivery schedule. If no such schedule is indicated, the delivery will be made as agreed by the
parties. Owner shall program the delivery schedule as not to adversely affect the critical path.
6.18.5.7.4. If the material to be furnished by the Owner is not to be delivered to the jobsite the Contract Documents
will indicate the terms and conditions of said delivery. If no terms and conditions are included in the Contract
Documents then the cost of delivery to the jobsite is not included in the Contract Price.
6.18.5.7.5. If the material to be furnished by the Owner is not to be delivered to the jobsite the Contract Documents will
indicate the date and time of availability of the material. If no such date and time is indicated, the material will be
available by agreement as not to impact the critical path.
- 50
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
6.18.5.7.6. The material to be furnished by the Owner will include all ancillary items included in the Technical
Specification that describes the material to be furnished by the Owner, unless indicated otherwise in the Contract
Documents.
6.18.5.7.7. The Owner warrants that the materials furnished by the Owner to the Contractor are of a quality
sufficient for the purpose of their use. The Owner further warrants that the material to be furnished is Equal or Similar
to that specified in the Technical Specification that describes the material to be furnished by the Owner.
6.18.5.7.8. The material furnished by the Owner will be of sufficient quantity including normal construction breakage,
waste and shrinkage to complete the Work, unless the Contract Documents indicate otherwise.
6.18.5.7.9. The Contractor will be responsible for all Owner furnished materials delivered or made available to him
in accordance with the terms and conditions of this section. If due to the fault of the Contractor, the Owner has to
supply more material to the Contractor than indicated in the Contract Documents, the Owner may deduct this cost
from any Partial Payment or Retainage due to the Contractor.
6.18.5.7.10. If the Owner's Representative has informed in a timely manner, the date or schedule of delivery of the
material, the Contractor will be liable for all demurrage charges if he fails to receive the Owner furnished material
within the time limit or schedule specified.
+
6.18.5.7.11. Unless otherwise indicated in the Contract Documents, all costs at jobsite including unloading, handling,
warehousing and Installation of the Owner furnished material are included in the Contract Price and Contractor
shall not receive additional compensation therefore.
6.18.5.8. Certification of Compliance.
6.18.5.8.1. When a certification of a material or assembly is required by the Contract, each lot of such materials or
assemblies delivered to the Site shall be accompanied by certificate of compliance in which the delivered material or
assembly is clearly identified.
6.18.5.8.2. Commercially manufactured products shall be accompanied by certificates signed by the manufacturer
and, when required, supported by tests performed by the manufacturer. Certified copies of such test results shall
be furnished to the Owner's Representative.
6.18.5.8.3. Materials or assemblies accompanied by certificates of compliance may be sampled and tested at
any time and if found not to be in conformity with Contract Documents will be subject to rejection at any time
whether incorporated to the Work or not.
6.18.5.8.3.1. Removal of such rejected materials will be at the Contractor's expense, unless such materials have
been supplied by the Owner and it was Owner's duty to test for conformity with the Contract Documents.
6.18.6 Contractor shall carry on the Work and adhere as reasonably as possible to the Progress Schedule during all
Disputes or disagreements with Owner.
6.18.6.1. If the Dispute or disagreement hinders the ability of the Contractor to carry on the Work, the Contractor
shall so inform the Owner.
51 -
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
6.18.6.2. If the Dispute allows more than one course of action to be followed in the prosecution of the Work,
the Owner's Representative may instruct the Contractor on the course of action to be followed.
6.18.6.3. No Work shall be delayed or postponed pending resolution of any Disputes or disagreements, except
as permitted in section 15.4 or as Owner's Representative and Contractor may otherwise agree in writing.
6.18.7. Limitations on Operations.
6.18.7.1. Unless otherwise specified in the Contract Documents, the Contractor shall not open up new Work to
the prejudice or detriment of Work already started.
6.18.7.1.1. In lineal projects, the Owner's Representative may require the Contractor to finish a section on which
Work is in progress before Work is started on any additional section, if the opening of such section is essential to
public safety or convenience.
6.18.7.1.2. If said order causes the Project to be delayed, the Contract Price and/or Contract Time shall be
equitable adjusted.
6.19 Contractor's General Warranty and Guarantee
6.19.1. Contractor warrants and guarantees to Owner that all Work will be in accordance with the Contract Documents
+
and will not be deficient. Contractor's warranty and guarantee hereunder excludes defects or damage after
substantial, or partial completion and occupancy caused by:
6.19.1.1. abuse, modification, or improper maintenance or operation by persons other than Contractor,
Subcontractors, Suppliers, or any other individual or entity for whom Contractor is responsible; or
6.19.1.2. normal wear and tear under normal usage by Owner or individuals or entities for whom Owner is
responsible.
6.19.2. Contractor's obligation to perform and complete the Work in accordance with the Contract Documents
shall be absolute. None of the following will constitute an acceptance of Work that is not in accordance with the
Contract Documents or a release of Contractor's obligation to perform the Work in accordance with the Contract
Documents:
6.19.2.1. observations by Architect/Engineer and/or Owner's Representative;
6.19.2.2. recommendation by Owner's Representative or payment by Owner of any progress or final payment;
6.19.3. the issuance of a certificate of Substantial Completion by Owner's Representative or any payment related
thereto by Owner;
6.19.4. use or occupancy of the Work or any part thereof by Owner;
6.19.3. The Contractor warrants to the Owner that all materials and equipment furnished under this Contract
will be new unless otherwise specified, and that all Work will be free from faults and defects and in conformance with
the Contract Documents for the time periods specified in the Contract Documents or for one (1) year, whichever is
52 -
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
longer, unless otherwise specified in the Contract Documents.
6.19.3.1. If required by the Owner's Representative, the Contractor shall furnish satisfactory evidence as to the kind
and quality of materials and equipment.
6.20 Indemnification
6.20.1. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless
Owner, Architect/Engineer, Architect/Engineer's Consultants, and the officers, directors, partners, employees, agents,
and other consultants and subcontractors of each and any of them from and against all claims, costs, losses, and
damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals
and all court or arbitration or other dispute resolution costs) arising out or relating to the performance of the Work,
provided that any such claim, cost, loss, or damage:
6.20.1.1. is attributable to bodily injury, sickness, disease, or death, or to injury to or destruction of tangible
property (other than the Work itself), including the loss of use resulting there from; and
6.20.1.2. only to the extent caused by any negligent act or omission of Contractor, any Subcontractor, any
Supplier, or any individual or entity directly or indirectly employed by any of them to perform any of the Work or
anyone for whose acts any of them may be liable.
6.20.2. The indemnification obligations of Contractor under section 6.20.1 shall not extend to the Architect/Engineer
and Architect/Engineer's Consultants or to their officers, directors, partners, employees, agents, and other
consultants and subcontractors of each and any of them arising out of:
6.20.2.1. errors and/or omissions in the preparation or approval of, or the failure to prepare or approve, maps,
Drawings, opinions, reports, surveys, Change Orders, designs, or Specifications; or
6.20.2.2. giving directions or instructions, or failing to give them, if that is the primary cause of the injury or
damage.
6.21 Subcontractors, Suppliers and Others
6.21.1. Award of Subcontracts for Portions of The Work.
6.21.1.1. Unless otherwise specified in the Contract Documents the Contractor, as soon as practicable after the
signing of the Contract, shall furnish to the Owner's Representative in writing for his acceptance a list of the names of
the main Suppliers and Subcontractors proposed for the principal portions of the Work.
6.21.1.1.1. The Owner's Representative shall promptly notify the Contractor in writing if he, after due
investigation, has reasonable objection to any Supplier or Subcontractor on such list and does not accept him. Said
reasonable objection may include, but are not limited to, previous default by said Subcontractor or Supplier
with Owner, a record of flagrant safety violations or an unsatisfactory past performance with Owner.
6.21.1.1.1.1. The Owner's Representative shall specify in writing the reasons for such objection
53 -
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
6.21.1.1.1.2. If within fifteen (15) calendar days from submittal by the Contractor, the Owner's Representative
fails to make objections to any Supplier or Subcontractor on the list, the Contractor shall request the approval of
the list by the Owner's Representative who shall have ten (10) days to issue his decision. If no reply is forthcoming
from the Owner's Representative within the stated time, the list of Suppliers or Subcontractors shall be deemed
approved.
6.21.1.1.2. The Contractor shall not contract with any Supplier or Subcontractor or any person or organization
(including those who are to furnish materials or equipment fabricated to a special design) that has been rejected by the
Owner's Representative in the manner indicated in Article 6.21.1.1.1, above.
6.21.1.1.3. If the Owner's Representative refuses to accept any Supplier, Subcontractor, person, or organization
on a list submitted by the Contractor in response to the requirements of the Contract Documents, the Contractor
shall submit an acceptable substitute.
6.21.1.1.3.1. No increase in the Contract Sum shall be allowed for any such substitution of a rejected Subcontractor
and/or Supplier or other in accordance with Article 6.21.
6.21.1.1.3.2. No acceptance by Owner's Representative of any such Subcontractor, Supplier, or other individual
or entity, whether initially, or as a replacement, shall constitute a waiver of any right of Owner's Representative or
Engineer to reject defective Work.
6.21.1.1.4. Unless otherwise specified in the Contract Documents, the Contractor shall execute, with his own
forces and organization, Work amounting to not less than twenty-five percent (25%) of the original total Contract Price.
6.21.1.1.4.1. Any items designated in the Contract Documents as "Specialty Trades or Items" shall be
deducted from original total cost before computing the amount of the work required to be performed by the
Contractor with his own forces and organization
6.21.2. Payments to Subcontractors.
6.21.2.1. The Contractor shall pay each Subcontractor for work performed in the Project in accordance with
the terms and conditions stipulated in the contract executed by and between the Contractor and the Subcontractor.
6.21.2.1.1. The Contractor shall also require the Subcontractor to make similar payments to his Sub-
Subcontractors.
6.21.3. Flow Down of Applicable Agreement Provisions.
6.21.3.1. The Contractor shall cause the inclusion, in all agreements executed by contractor with
Subcontractors and Suppliers, of all applicable provisions of the Agreement with which Subcontractors and
Suppliers need to comply for their proper performance on behalf of Contractor, of the duties and obligations
imposed by the Contract Documents. Contractor shall also cause Subcontractor and Suppliers to include in
their respective agreements with Sub-Subcontractors, and Sub-Suppliers the same duties to flow down to all
lower tier agreements such applicable Agreement provisions.
6.21.4. The Contractor shall be considered as an independent contractor for all purposes under the Contract, and no
persons engaged or contracted by the Contractor for the performance of Contractor's obligations shall be considered
an employees or agents of the Owner.
54 -
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
6.21.5. Contractor shall be fully responsible to Owner's Representative, Owner and Architect/Engineer for all acts
and omissions of the Subcontractors, Suppliers, and other such individuals or entities performing or furnishing any of
the Work.
6.21.5.1. Nothing in the Contract Documents shall create for the benefit of any Subcontractor or Supplier a
contractual relationship between Owner's Representative, Owner or Architect/Engineer, nor shall it create any
obligation on the part of Owner's Representative, Owner or Architect/Engineer to pay or to see to the payment of any
moneys due any such Subcontractor, Supplier, or other individual or entity except as may otherwise be required
by Laws or Regulations.
6.21.6. Contractor shall be solely responsible for scheduling and coordinating the Work of Subcontractors, Suppliers,
and other such individuals or entities performing or furnishing any of the Work under a direct or indirect contract
with Contractor.
6.21.7. Contractor shall require all Subcontractors, Suppliers, and such other individuals or entities performing or
furnishing any of the Work to communicate with Owner's Representative only through Contractor.
6.21.8. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an appropriate
agreement between Contractor and the Subcontractor or Supplier that specifically binds the Subcontractor or Supplier
to the applicable terms and conditions of the Contract Documents for the benefit of Owner's Representative, Owner
and Architect/Engineer, including required contract provisions applicable to Federal Agency funded projects.
6.21.8.1. Whenever any such agreement is with a Subcontractor or Supplier who is listed as an additional
insured on the property insurance provided in section 3.6, the agreement between the Contractor and the Subcontractor
or Supplier will contain provisions whereby the Subcontractor or Supplier waives all rights (including subrogation) against
Owner, Contractor, Architect/Engineer, Architect/Engineer's Consultants, and all other individuals or entities identified
in the Contract Documents to be listed as insured or additional insured (and the officers, directors, partners,
employees, agents, and other consultants and subcontractors of each and any of them) for all losses and damages
caused by, arising out of, relating to, or resulting from any of the perils or causes of loss covered by such policies and any
other property insurance applicable to Work.
6.21.8.1.1. If the insurers underwriting any such policies require separate waiver forms to be signed by any
Subcontractor or Supplier, Contractor will obtain the same.