Regl. 7998, art. 15.2.1
Condiciones Generales Uniformes para la Contratación de Obras Pública en Puerto Rico. Incluye Analisis de Flexibilidad
Length: 2,972 wordsOfficial source
Cite as Reglamento Núm. 7998, Art. 15.2.1
13.2.4. Payments Becomes Due
13.2.4.1. Unless otherwise specified in the Contract Documents, forty (40) days after Owner's approval of the
Application for Payment, with Owner's Representative's recommendation, the amount recommended will become
due, and when due, shall be paid by Owner to Contractor.
- 83 -
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
13.2.5. Reduction in Payment
13.2.5.1. The Owner's Representative, without incurring in liability, may decline to approve any Application for
Payment or, because of subsequently discovered evidence or subsequent inspection, he may nullify the whole or
any part of any Application for Payment previously issued, to such extent as may be necessary in his opinion to
protect the Owner from loss because of:
13.2.5.1.1. Deficient Work not remedied; or
13.2.5.1.2. Failure of the Contractor to comply with any requirements of the Contract Documents.
13.2.5.2. Owner may refuse to make payment of the full amount recommended by Owner's Representative
because:
13.2.5.2.1. claims have been made against Owner on account of Contractor's performance or furnishing of the
Work;
13.2.5.2.2. Liens have been filed in connection with the Work, except where Contractor has delivered a specific
Bond satisfactory to Owner to secure the satisfaction and discharge of such Liens;
13.2.5.2.3. there are other items entitling Owner to a set-off against the amount recommended; or
13.2.5.2.4. Owner has actual knowledge of the occurrence of any of the events enumerated in Article 13.2.3.6 or
15.2.1.
13.2.5.3. If Owner refuses to make payment of the full amount recommended by Owner's Representative,
Owner must give Contractor immediate written notice (with a copy to Owner's Representative) stating the
reasons for such action and promptly pay Contractor any amount remaining after deduction of the amount so
withheld.
13.2.5.3.1. Owner shall promptly pay Contractor the amount so withheld, or any adjustment thereto agreed to
by Owner and Contractor, when Contractor corrects to Owner's Representative's satisfaction the reasons for
such action.
13.2.5.3.2. If it is subsequently determined that Owner's refusal of payment was not justified, the amount
wrongfully withheld shall be treated as an amount due as determined by Article 13.2.4.
13.2.5.4. Partial payments may be suspended when in the judgment of the Owner the Work has not proceeded
according to the terms of the Contract Documents.
13.2.5.5. If at any time during the construction of the Project, the Owner receives proper notice from a third
party stating a claim under Civil Code Article 1489, the Contractor shall settle the claim with the third party within
fifteen (15) calendar days from the notice to the Owner and inform the Owner of said settlement or otherwise if
Contractor disputes the validity of said claim, post a bond, acceptable to Owner, for the benefit of Owner to protect
Owner against liability for payment to the third party under Civil Code Article 1489 in which case partial payment
therefore will not be withheld. This will apply in any project where there is no Payment or Performance Bond, or the
penal sum of such bond is an amount less than one hundred (100) percent of the Contract Sum.
- 84 -
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
13.2.5.5.1. If no settlement is reached or a bond is not posted and accepted, the Owner, the Contractor, and
the claimant third party shall meet within thirty (30) days after the expiration of the fifteen (15) calendar days to
ascertain the amount of the alleged debt.
13.2.5.5.2. Contractor shall then pay within five (5) calendar days the undisputed amount. If no payment is
made, the Owner shall retain said amount from the next partial payment and proceed to pay directly the
undisputed amount to the third party. If the Contractor posts a bond as provided in Article 13.2.5.5 the Owner
will not withhold said amount from Contractor and will not pay the amount to the third party claimant until the
Contractor or the third party claimant notify Owner that the dispute among them has been resolved at which
time Owner will act accordingly.
13.2.6. Scope of Payment
13.2.6.1. The payment of any partial estimate or of any retained percentage, in no way shall release the
obligation of the Contractor to renew or repair any deficient materials used in the construction, or to be responsible
for all damage due to such deficiencies.
13.2.6.2. No payment will be made for any unauthorized work.
13.2.6.3. No certificate for a progress payment, nor any progress payment, or any partial or entire use or
occupancy of the Project by the Owner shall constitute an acceptance of any Work not in accordance with the
Contract Documents.
13.3 Contractor's Warranty of Title
13.3.1. Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any
Application for Payment, whether incorporated in the Project or not, will pass to Owner no later than the time of
payment, and will pass free and clear of all Liens, Claims, security interests or encumbrances. Contractor also
warrants and guarantees that no Work, materials, or equipment covered by an Application for Payment has been
acquired by the Contractor, subject to an agreement under which an interest therein, or an encumbrance
thereon, is retained by the seller or otherwise imposed by the Contractor or such other person. This will also apply
to any other person performing the Work for the Project on behalf of Contractor , or furnishing materials and
equipment for the Project.
13.4 Substantial Completion
13.4.1. When Contractor considers the entire Work ready for its intended use Contractor shall notify Owner and
Owner's Representative in writing that the entire Work is Substantially Complete (except for items specifically listed
by Contractor as incomplete) and request that Owner's Representative issue a Certificate of Substantial
Completion. Owner may, at its sole option, request that part of the Work be declared Substantially Complete
as provided in Article 13.5.1.
13.4.1.1. Within five (5) working days after such request, Owner, Contractor and Owner's Representative shall
make an inspection of Work to determine the state of completion. If within this time period, the Owner's
Representative fails to make objections or respond, the Contractor shall request the approval of the Chief of
Construction or equivalent division head of Owner which shall have fifteen (15) working days to issue its approval
or disapproval of the Certificate of Substantial Completion.
85 - -
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
13.4.1.1.1. If Owner's Representative does not consider the Work substantially complete, Owner's
Representative will notify Contractor in writing, within five (5) working days after the inspection, giving the
reasons therefore.
13.4.1.1.2. If Owner's Representative considers the Work substantially complete, Owner's Representative will
prepare and deliver to Owner, within ten (10) working days after the inspection, a tentative certificate of Substantial
Completion which shall fix the date of Substantial Completion.
13.4.1.1.3. There shall be attached to the certificate a tentative list of items (punch list) to be completed or
corrected before final payment.
13.4.1.2. Owner shall have ten (10) working days after receipt of the tentative certificate during which to make
written objection to Owner's Representative as to any provisions of the certificate of Substantial Completion or
attached list.
13.4.1.3. If, after considering such objections, indicated on Article 13.4.1.2, Owner's Representative concludes
that the Work is not substantially complete, Owner's Representative will within fifteen (15) working days after
submission of the tentative certificate of Substantial Completion to Owner notify Contractor in writing, stating the
reasons therefore.
13.4.1.4. If, after consideration of Owner's objections, indicated on Article 13.4.1.2, Owner's Representative
considers the Work Substantially Complete, Owner's Representative will, within said fifteen (15) working days,
execute and deliver to Owner and Contractor a definitive certificate of Substantial Completion (with a revised final
punch list of items to be completed or corrected). Such final certificate will reflect such changes from the tentative
certificate as Owner's Representative believes justified, after consideration of any objections from Owner.
13.4.1.5. At the time of issuance of the certificate of Substantial Completion, Owner will assume all
responsibilities with respect to security, operation, safety, and protection of the Work, maintenance, utilities,
insurance, and Contractor warranties and guarantees periods will start to run.
13.4.1.6. Unless Owner and Contractor agree otherwise in writing and inform Owner's Representative also in
writing prior to Owner's Representative's issuing the definitive certificate of Substantial Completion, Owner's
Representative's aforesaid recommendation will be binding on Owner and Contractor until final payment is made.
13.4.2. Owner shall have the right to exclude Contractor from the Site after the date of Substantial Completion,
but Owner shall allow Contractor reasonable access to complete or correct items on the final punch list.
13.5 Partial Utilization
13.5.1 Use by Owner, at Owner's option, of any substantially completed part of the Work which has specifically
been identified in the Contract Documents, or which Owner, Owner's Representative, and Contractor agree
constitutes a separately functioning and usable part of the Work that can be used by Owner for its intended
purpose, without significant interference with Contractor's performance of the remainder of the Work, may be
effected (put to such use) prior to Substantial Completion of all the Work subject to the following:
13.5.1.1. Owner at any time may request Contractor in writing to permit Owner to use any such part of the
Work which Owner believes to be ready of its intended use and substantially complete.
- 86 -
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
13.5.1.1.1. If Contractor agrees that such part of the Work is substantially complete, Contractor will certify to
Owner and Owner's Representative that such part of the Work is substantially complete and request Owner's
Representative to issue a certificate of Substantial Completion for that part of the Work.
13.5.1.1.2. Contractor at any time may notify Owner and Owner's Representative in writing that Contractor
considers any such part of the Work ready for its intended use and substantially complete and request Owner's
Representative to issue a certificate of Substantial Completion for that part of the Work.
13.5.1.1.2.1. Within a reasonable time (not more than fifteen (15) days) after either party's request, Owner,
Contractor, and Owner's Representative shall make an inspection of that part of the Work subject to the request to
determine its state of completion.
13.5.1.1.2.2. If Owner's Representative does not consider that part of the Work to be substantially complete,
Owner's Representative will notify Owner and Contractor in writing giving the reasons therefore.
13.5.1.1.2.3. If Owner's Representative issues a certificate of Substantial Completion for said part of the
Work thereupon all applicable provisions of Article 13.4 shall apply.
13.5.1.1.3. No occupancy or separate operation of part of the Work may occur prior to compliance with the
requirements of Article 13.4.1.5 regarding property insurance.
13.6 Final Inspection
13.6.1. Upon written notice from Contractor that the entire Work or an agreed portion thereof is complete,
Owner's Representative will, within five (5) working days, make a final inspection with Owner and Contractor and
will notify Contractor in writing of all particulars this inspection reveals with regard to incomplete or deficient Work.
13.6.1.1. Contractor shall immediately take measures to complete such Work and remedy such deficiencies.
13.7 Final Payment
13.7.1. Application for Payment
13.7.1.1. After Contractor has, in the opinion of Owner's Representative, satisfactorily remedied all incomplete
and deficient Work identified during the final inspection and has delivered, in accordance with the Contract
Documents, all maintenance and operating instructions, schedules, guarantees, Bonds, certificates or other
evidence of insurance, certificates of inspection, marked-up record documents, and other documents required
by the Contract, Contractor may make application for final payment following the procedure for progress payments.
13.7.1.2. The final Application for Payment shall be accompanied, except if previously delivered to Owner's
Representative, by:
13.7.1.2.1. all documentation, guarantees, Bonds and insurance called for in the Contract; and.
13.7.1.2.2. consent of the surety, if any, to final payment; and
13.7.1.2.3. complete and legally effective releases, or waivers, (satisfactory to Owner) of all Lien rights arising
out of or Liens filed in connection with the Work.
- 87 -
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
13.7.1.3. In lieu of the releases or waivers of Liens specified in Article 13.7.1.2.3, if approved by Owner,
Contractor may furnish payment receipts or releases in full as part of an affidavit executed by Contractor to the
effect that:
13.7.1.3.1. the releases and receipts include all liabilities related to labor, services, material, and equipment
for which a Lien could be filed; and
13.7.1.3.2. all payrolls, material and equipment bills, and other indebtedness connected with the Work for
which Owner and Owner's property might in any way be responsible, have been paid or otherwise satisfied.
13.7.1.3.3. If any Subcontractor or Supplier fails to furnish such a release or receipt in full, Contractor may
furnish a Bond or other collateral satisfactory to Owner to indemnify Owner against liability related to any such Lien.
13.7.2 Review of Final Application for Payment and Acceptance of the Work.
13.7.2.1. If, on the basis of Owner's Representative's observation of the Work during construction and final
inspection, and Owner's Representative's review of the final Application for Payment and accompanying
documentation as required by the Contract Documents, Owner's Representative is satisfied that the Work has
been completed and Contractor's other obligations under the Contract Documents have been fulfilled, Owner's
Representative will, within fifteen (15) days after receipt of the final Application for Payment, indicate to Owner in
writing Owner's Representative's recommendation regarding payment and if payment is recommended
present the Application for Payment to Owner, for payment.
13.7.2.1.1. At the same time, Owner's Representative will also give written notice to Owner and Contractor that
the Work is acceptable subject to the provisions of Article 13.9.
13.7.2.1.2. Otherwise, within the time specified in Article 13.7.2.1, Owner's Representative will return the
Application for Payment to Contractor, indicating in writing the reasons for refusing to recommend final payment, in
which case Contractor shall make the necessary corrections and resubmit the Application for Payment. If within said
fifteen (15) days after submittal of the final Application for Payment by Contractor the Owner's Representative fails
to make objections or respond, the Contractor shall request approval directly from the Owner who shall have
fifteen (15) working days to issue approval or disapproval, provided Contractor has also given the same timely
notice directly to Owner as required in Article 17.3.2. If no reply is forthcoming from the Owner within the stated
time, the final Application for Payment shall be deemed approved.
13.7.3. Final Payment Becomes Due
13.7.3.1. Unless otherwise specified in the Contract Documents, forty (40) days after Owner's approval of the
Application for Final Payment, with accompanying documentation, the amount recommended by Owner's
Representative will become due, and when due, shall be paid by Owner to Contractor.
13.7.3.2. If payment is not made within the time stated in Article 13.7.3.1., thereafter Owner will pay
Contractor interest at the legal rate on the amount due.
13.8 Final Completion Delayed
13.8.1. If, through no fault of the Contractor, final completion of the Work is significantly delayed, and if Owner's
88 -
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
Representative so confirms, Owner shall, upon receipt of Contractor's final Application for Payment and
recommendation of Owner's Representative, and without terminating the Agreement, make payment of the
balance due for that portion of the Work fully completed and accepted.
13.8.2. If the remaining balance to be held by Owner for Work not fully completed, or corrected, is less than the
retainage stipulated in the Agreement, and if Bonds have been furnished as required in Article 3, the written
consent of the surety to the payment of the balance due for that portion of the Work fully completed and accepted
shall be submitted by Contractor to Owner's Representative with Application for such payment.
13.8.2.1. Such payment shall be made under the terms and conditions governing final payment, except that it
shall not constitute a waiver of any claim or of any right under the Contract.
13.9 Waiver of Claims
13.9.1. The making and acceptance of final payment will constitute:
13.9.1.1. a waiver of all Claims by Owner against Contractor, except for Claims arising from unsettled Liens, from
deficient Work appearing after final inspection as the result of failure to comply with the Contract Documents, from
special guarantees or from Contractor's continuing obligations under the Contract Documents; and
13.9.1.2. a waiver of all other unsettled Claims by Contractor against Owner, other than those previously made
in a timely manner in writing.
13.10 Unilateral Liquidation
13.10.1. The procedures established in this section will be applicable whenever the Contractor is not available
in order for the Owner to issue the final payment in accordance with Article 13.7.
13.10.1.1. For purposes of this section, the term "unavailable" shall meant that the Contractor repeteadly fails
to answer Owner's requests to meet with the Owner and/or to submit the required documentation under Article
&
13.7 in order to proceed with the final payment and Project liquidation.
13.10.2. If Contractor is unavailable, Owner shall proceed to issue and process the final application for
payment. In order to accomplish this, whenever possible, the Owner will seek to obtain the documentation
required under Article 13.7.1.2 and 13.7.1.3.
13.10.2.1. When Owner can not obtain documentation required under Article 13.7.1.2 and 13.7.1.3 such
documentation it may be waived by Owner in order to proceed to the issuance of final payment. However, in case
of such waiver, Owner may impose those reasonable conditions Owner deems relevant in order to protect
Owner's interests and safeguard against claims by third parties.
13.10.3. If after finalizing liquidation of the Contract, payment is due Contractor and Contractor remains
unavailable, Owner will retain such payment until Contractor is available to collect such payment. If the Final
Payment is negative (i.e., the balance is in favor of the Owner), the Owner shall compensate such amount from
any other payment in favor of Contractor, if any, and/or proceed to collect it by any means available.
- - 89 -
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS