8.1 Owner's Right to Award Separate Contract, Perform Work with Owner's Employees and Utility
Workers. Related Work at Site
8.1.1. Owner's Right to Award Separate Contract, Perform Work with Owner's Employees and Utility Workers.-
Owner may perform other work related to the Project at the Site with Owner's employees, or by awarding separate
contracts, or by having the work performed by utility workers. Written notice thereof will be given to Contractor
prior to starting any such other work.
8.1.1.1. If the terms and conditions of the work to be performed by Owner's employees, separate contractors or
by others, are not described in the Contract Documents prior to the bid, the Contract Time and Sum will be
equitably adjusted as a result of said work and any other work to the extent that such work performed by Owner's
employees, separate contracts or by others affects the Contractor's Work.
8.1.1.2. If the terms and conditions of the work to be performed by Owner's employees, separate contractors or
by others are described in the Contract Documents prior to the bid, then the Contract Time and Sum will be
equitably adjusted but only to the extent that said work differs from the work indicated in the Contract
Documents that is to be performed by Owner's employees, separate contractors or by others.
8.1.1.3. Should the performance of other work related to the Project at the Site by Owner's employees,
58 -
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
separate contractors, utility workers, that was not indicated in the Contract Documents, cause damages, delays
or interferes with the Work being performed by the Contractor, the Owner will assume full responsibility and pay
for all costs, expenses, and delays to which the Contractor is subjected caused by the execution and/or
performance of said other work described herein if the critical path is adversely affected.
8.1.1.4. In the event one or more contracts are awarded related to the Project, the "contractor" in the contract
document in each case, will be the contractor who signs each separate contract.
8.1.1.5. If there is under construction other work for Owner,by written contract or otherwise, adjacent to the
limits of the site, the Contractor, if so ordered by the Owner, shall permit access to others performing such
work through the Site.
8.1.1.5.1. If Owner authorizes the other contractors performing work adjacent to the Site to use said access
Owner shall prescribe limitations and conditions for such use as required to protect Contractor's operations
and the Work.
8.1.1.5.1.1. In accordance with this Article 8.1, the Owner will be responsible for any damages, costs, or
delays caused to the Contractor by such order.
8.1.1.6. If Owner and Contractor are unable to agree on entitlement to or on the amount or time, if any, of any
adjustment in the Contract Price or Contract Time necessary as a result of such other work, a Claim may be
made therefore as provided in Article 11.5.
8.1.2. Coordination of the Separate Contracts and Work by Others.
8.1.2.1. Unless otherwise specified in accordance with Article 8.1.2.4, Owner shall be responsible for the
coordination of the Work between the Contractor, Owner's employees, the separate contractors and any others,
as to the interaction and scheduling of the various work and the proper and safe access to the Site and storage
of the equipment and materials of the Contractor, the Owner's employees, the separate contractors and others
contracted by Owner.
8.1.2.2. Contractor shall fully cooperate with the Owner in the coordination of the Contractor's Work with that
of the Owner's employees, the separate contractors and any work by others as to the interaction and
scheduling of the various work and the proper and safe access to the Site and storage of the equipment and
materials of the Contractor, the separate contractors and others.
8.1.2.3. The Owner may delegate this coordination, in whole or in part, to a Construction Manager or separate
contractor and must give prior notice to Contractor in writing, containing the terms and conditions of this
delegation.
8.1.2.3.1. The Construction Manager or the separate contractor will act on behalf of Owner strictly within the
limits of such delegation.
8.1.2.4. The Owner may delegate this coordination responsibility in whole or in part to one of the separate
contractors or to the Contractor as follows:
8.1.2.4.1. If prior to the bid opening date, the Owner requires that the Contractor be responsible for the
coordination of the Owner's employees, separate contracts or any work by others, the Owner will indicate the
- 59 -
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
terms and conditions of such obligation in the bid documents and it shall be the Contractor's responsibility to
include in the Contract Price whatever costs are required for this coordination of the work.
8.1.2.4.2. If the Owner requires that Contractor be responsible for the coordination of Owner's employees,
separate contracts or work by others after the bid has been awarded, the Owner will indicate the terms and
conditions of such obligation as a Change Order.
8.1.2.5. Contractor Coordination Meetings:
8.1.2.5.1. If the Owner, or the party with the coordinating responsibility so requires it, the Contractor shall
attend coordination meetings with the Owner's employees, separate contractors or others performing work at a
site to be determined by the coordinator.
8.1.2.5.1.1. The purpose of the coordination meeting shall be for the Contractor and all separate contractors
and/or others performing work to coordinate schedules and construction activities to enable the construction of
the different work under the separate contracts to occur on a coordinated, efficient and expeditious manner.
8.1.2.5.1.2. The coordination meeting shall also serve as forum for the Contractor and all separate contractors
and/or others performing work at the site to discuss, and try to avoid and try to resolve between and among
themselves any conflicts in their respective schedules or construction activities and prevent delays in one
contractor's activities caused by another.
8.1.2.5.2. If the different contractors cannot reach an agreement on the coordination of the construction activities
and schedule to be followed, the Owner, or his designated coordinating representative, will decide on the
course of action to be followed and shall provide the necessary instructions to the Contractor, Owner's
employees, separate contractors and others performing work on how to proceed, as a Field Order or, if required,
as a Change Order.
8.1.3. Contractor, and any other entity contracted by the Owner to perform direct work related to the Project, shall
do all cutting, fitting, and patching of the Work that may be required to properly connect or otherwise make its
several parts come together and properly integrate such other work with the work of the Contractor or any other
entity contracted by the Owner to perform related work on the Project.
8.1.3.1. Contractor, or any other entity contracted by the Owner to perform related work on the Project, shall not
endanger any work of others by cutting, excavating, or otherwise altering their work and will only cut or alter their
work with the written consent of Owner and the others whose work will be affected.
8.1.4. The duties and responsibilities of Contractor under this Article are for the benefit of such utility owners and
separate contractors to the extent that there are comparable provisions for the benefit of Contractor, including
general, supplemental and special conditions, as well as similar insurance and hold harmless clauses, in said direct
contracts between Owner and such utility owners and separate contractors.
8.1.4.1. Furthermore, the Owner will verify that the schedule of others contracted to perform related work on the
Project does not interfere with the Project Schedule.
8.1.4.1.1. If in order to accommodate the work performed by others contracted by the Owner to perform related
work in the Project, the critical path is adversely affected and/or any damage to the Work occurs, the Owner will
compensate the Contractor in time and/or adjustment to Contract Price.
- 60 -
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
8.1.5. If the proper execution or results of any part of Contractor's Work depends upon work performed by
others under this Article, Contractor shall promptly inspect such other work and, within ten (10) working days, report
to Owner in writing any delays, defects, or deficiencies in such other work that, in his opinion, render it unavailable
or unsuitable for the proper execution and results of the Work.
8.1.5.1. Contractor's failure to report will constitute acknowledgement that said work is suitable, except for
hidden latent defects in such work.
8.1.5.2. The same rules stated herein will apply if other entities contracted by the Owner to perform related work
in the Project depend on Work performed by the Contractor.
8.2 Owner's Right to Award Separate Contract.
8.2.1. The Owner may award separate contracts in connection with other portions of the Project or additional
work to the Work covered by the Contract, and if such work affects the Work, Contractor will be notified by Owner
in a timely manner of the award of such separate contract.
8.2.1.1. The Owner may assign these separate contracts, as a Change Order, to the Contractor for a fee, as
indicated on Article 10.5.
8.2.2. When Separate Contracts are let within the limits of any project, the Owner shall coordinate the work of
each contractor SO as not to interfere with or hinder the progress or completion of the Work being performed by
Separate Contractors.
8.2.2.1. Contractors working on the same Project shall fully cooperate with each other.
8.2.2.2. Furthermore, the Owner will be responsible to verify that the schedule of the Separate Contractors
contracted to perform Work on the Project does not interfere with the Contractor's Project Programmed Schedule
previously approved for the Project.
8.2.2.2.1. Owner will compensate the Contractor, in time and/or adjustment to Contract Price, if his schedule
has to be varied, and/or any damage occurs, to accommodate the work performed by other entities contracted by
the Owner to perform related work in the Site.
8.3 Mutual Responsibility of Contractors
8.3.1. Each Contractor involved shall assume all liability, financial or otherwise, in connection with his Contract and
shall protect and save harmless the Owner from any and all damages or claims that may arise out of the
performance of the Contractor's Work.
8.3.1.1. The Owner will require from each Separate Contractor and other entities working on the Project,
Contract Documents, including General, Supplemental and Special Conditions, similar to those executed with the
Contractor and to include similar insurance clauses and hold harmless clauses.
8.3.1.2. The Owner will also be responsible to verify that the schedule of the Separate Contractors) and other
entities working on the project do not interfere with the Contractor's Project Programmed Schedule previously
approved for the Project.
- 61 -
UNIFORM GENERAL CONDITIONS FOR PUBLIC WORKS CONTRACTS
8.3.2. Should the Contractor cause damage to the work or property of any separate contractor and/or others
working on the Project, the Contractor shall, be liable for said damage.
8.3.2.1. If such other separate contractor files a claim against Owner on account of any such damage alleged to
have been so sustained, Contractor shall have the right to defend Owner, either by itself or in conjunction with
Owner, and Contractor shall compensate Owner for damages, costs and expenses sustained therefore by
Owner which are attributable to Contractor.
8.3.2.1.1. If the Contractor is found to be responsible for the alleged defects claimed by the separate contractor
and any judgment or award against the Owner arises therefrom, the Contractor shall pay or satisfy it and shall
reimburse the Owner for all attorney's fees and court, arbitration costs or other costs which the Owner has
therefore incurred.
8.3.2.1.2. If the Contractor is found not to be responsible for the alleged defects claimed by the separate
contractor, then the Owner shall pay for any judgment or award against him as well as reimburse the Contractor
for all attorney's fees and court or arbitration costs incurred in defending the Owner.