Regl. 8682, art. 1.05 dup2
DEFINITIONS
Length: 1,168 wordsOfficial source
Cite as Reglamento Núm. 8682, Art. 1.05 dup2
Allocation of Funds - ESPCs may be extended beyond the fiscal year in which they are awarded,
subject to the allocation of funds for expenses incurred in subsequent fiscal years. The allocation
of funds is guaranteed for the duration of the contract. The Office of Management and Budget
(OMB) and/or the corresponding Government Unit, in those cases in which the Government Unit
is not subject to OMB oversight, shall allocate funds for payment of public utilities of each
Government Unit in accordance with the terms and conditions set forth in the ESPC.
Conservation Measures - Refers to any Energy Conservation Measures and Water Conservations
Measures, as such terms are defined herein, implemented by a Government Unit in a Public
Building with the purpose of achieving meaningful reductions in energy and water consumption
in compliance with this Regulation.
2 I Page
Energy Savings Performance Contract Program Amended Regulation
Contract Sum - Refers to the sum of all materials, labor, auditing, design, engineering, project
construction management fees, overhead, profit, contingency, tax, bonds, and subcontracted
services related to an ESPC Project.
Contract Administrator - Refers to the Professional Engineer (PE), and Certified Measurement
and Verification Professional (CMVP) designated by the Government Unit to oversee an ESPC.
Energy Savings Performance Contract (ESPC) - Refers to a contract between a Government
Unit and a Qualified ESCO for the evaluation, recommendation and implementation of one or
more Conservation Measures.
Energy Service Company (ESCO) Refers to an entity with the experience and technical,
management and financial capabilities required for the discovery, engineering, procurement,
installation, financing, savings guarantee, maintenance and monitoring of energy and water saving
measures that will result in energy conservation and efficiency for the Government Unit.
Energy Conservation Measure (ECM) Refers to any improvement, repair or alteration,
equipment, fixtures, training program or strategy of any other kind implemented or used in a
building, facility or on any system that consumes energy in order obtain savings related to energy
consumption by reducing operational costs or increasing operational efficiency during the useful
life cycle. All measures must meet or exceed applicable state building codes.
ESCO's Professional Engineer - Refers to the Puerto Rico licensed professional engineer (PE)
retained by the ESCO with the purpose of ensuring that all services provided pursuant to this
Regulation complies with applicable laws and regulations. The Professional Engineer (PE) must
also be certified as a Certified Measurement and Verification Professional (CMVP).
Financing- Act 19-2012 allows the Government Unit to finance the improvements via third party,
direct from the ESCO, or other financing mechanism available, in coordination and with the
financial advice of the Government Development Bank (GDB).
Government Unit - Any agency, instrumentality, office or department of the Executive Branch
authorities or political subdivisions of the Government of Puerto Rico, or any other defined or
identified by the Administration.
Investment Grade Audit (IGA) Refers to the study by the Qualified ESCO selected for a
particular ESPC Project which includes detailed descriptions of the improvements recommended
for the project, the estimated costs of the improvements and the utility, operations and maintenance
cost savings projected to result from the recommended improvements.
Measurement and Verification (M&V) Refers to the report, submitted once every three months
during the contract period by the ESCO and validated by SOEP and the Contract Administrator
regarding the cost savings achieved as a result of the efficiency measures implemented as part of
the ESPC. The M&V services provide the Government Unit with assurance that all measures
implemented and equipment installed as part of the ESPC are performing as required.
3 I Page
Energy Savings Performance Contract Program Amended Regulation
Notice of Interest (NOI)- Refers to the notice sent by a Government Unit to all Qualified ESCOs
prior to the issuance of an RFP, requesting Qualified ESCOs to confirm whether they are interested
in participating in a certain RFP. The NOI has the purpose of ensuring that ESCOs electing to
participate in an RFP are aware of the nature and technical requirements of the Project and possess
the skills and knowledge required to provide an adequate response to the RFP.
Operations and Management (O&M) - ESCOs must provide adequate justification for O&M
cost savings by providing a detailed description of how savings are generated and detail cost
savings calculations.
Payment and Performance Bond - Refers to the guarantee provided by the ESCO in order to
ensure the timely and adequate completion of all construction and installation services in
accordance to the terms of the ESPC.
Professional Engineer - Refers to a person duly certified to provide engineering services in
Puerto Rico as a professional engineer (PE).
Procurement Process - Refers to the competitive process set forth in this Regulation through
which a Government Unit selects an ESCO for the provision of Conservation Measures through
the execution of an ESPC.
Project Site(s) - Refers to the buildings and installations owned, operated or leased by a
Government Unit for which an ESCO shall provide ESPC services.
Public Building - Refers to any structure, building or facility, including its electrical and/or
mechanical equipment, and infrastructure, owned, operated or leased by a Government Unit.
Qualified ESCO Registry - Refers to the registry kept and maintained by SOEP identifying all
ESCOs which have been qualified through a qualification process as set forth in this Regulation
and which are eligible for providing ESPC services to Government Units.
Savings in public utility services costs - Refers to any reduction in the cost of public utility
services for a prolonged period of time due to efficiency and conservation measures that have been
implemented or by reason of services rendered by a Qualified ESCO.
Savings in operational and maintenance costs - Refers to measurable reductions in operational
and maintenance costs which directly result from the implementation of Conservation Measures.
These savings will be calculated in comparison with the operational and maintenance costs
established as the baseline for calculation.
Savings Guarantee - Refers to the guarantee made by an ESCO that the savings resulting from
the Conservation Measures implemented will meet or exceed the cost, including financing costs,
associated with implemented such measures.
Surety Bond - Refers to the guarantee provided by the ESCO in order to ensure Savings
Guarantees set forth in the ESPC.
4 I Page
Energy Savings Performance Contract Program Amended Regulation
State Office of Energy Policy (SOEP) Refers to the government agency created by Act 57-
2014 with the purpose of promoting energy conservation throughout Government Units and
overseeing the implementation of energy efficiency measures through the use of ESPCs.
Term of the Contract- Refers to the term of the ESPC, which shall not exceed fifteen (15) years.
The term allowed in the contract shall reflect the useful life of the conservation measure but shall
never exceed fifteen (15) years.
Water Conservation Measures - Any improvement, modification, equipment and changes in
maintenance practices or training programs designed to reduce water consumption or operating
costs related to its conservation. Measures should match or exceed compliance with applicable
state building codes.
CHAPTER TWO: ENERGY SAVINGS PERFORMANCE CONTRACTS OVERVIEW