Regl. 8682, art. 2.03
BASIC ESPC PROCESS
Length: 126 wordsOfficial source
Cite as Reglamento Núm. 8682, Art. 2.03
An ESPC allows a Government Unit to finance and install proven energy-efficient technologies
and upgrade energy infrastructure at no up-front cost. The Government Unit, through a competitive
process and with SOEP's assistance, selects an ESCO to complete an energy audit of the facilities
and propose a project through which the financed debt service can be paid for from the utility
savings. Once an ESPC is negotiated, the ESCO designs, installs and commissions Conservation
Measures selected by the Government Unit from the suggested list of conservation measures
prepared by the ESCO. The ESCO can be contracted to provide maintenance of the system,
oversight, operations training or a combination of the aforementioned to ensure savings persist.
Energy savings are measured and verified and the ESCO guarantees the savings.