Cite as Reglamento Núm. 8682, Art. 7.09 dup2

OPERATING PARAMETERS OF INSTALLED EQUIPMENT The ESPC will include a Schedule that will specify the performance testing procedures that will be used for start-up and for the commission of the installed equipment and total system. The schedule will also provide for the Government Unit to be notified of, and present, during all commissioning procedures. This schedule will contain a provision for the documentation of the Government Unit's attendance at the various tests, and their approval that the tests followed the specified procedures, and met or exceeded the expected results. The operating parameters will contain any specified parameters for the operation of the installed equipment such as temperature setbacks, equipment run times, load controlling specifications and other conditions for the operation of the equipment.