Regl. 8682, art. 8.04
POST-INSTALLATION M&V ACTIVITIES
Length: 180 wordsOfficial source
Cite as Reglamento Núm. 8682, Art. 8.04
ESCO must describe the intent of post-installation verification activities, including what will be
verified, and must, in coordination with SOEP:
1. Describe variables affecting post-installation energy or water use. Include variables such
as weather, operating hours, set point changes, etc. Describe how each variable will be
31 I Page
Energy Savings Performance Contract Program Amended Regulation
quantified, i.e., measurements, monitoring, assumptions, manufacturer data, maintenance
logs, engineering resources, etc.
2. Define key system performance factors characterizing the post-installation conditions such
as lighting intensities, temperature set points, etc.
3. Define requirements for the Government Unit to witness the measurements obtained, if
different than the project data requirements.
4. Provide details of post-installation data to be collected, including: Parameters to be
monitored; Details of equipment to be monitored (location, type, model, quantity, etc.);
Sampling plan, including details of usage groups and sample sizes; Duration, frequency,
interval, and seasonal or other requirements of measurements; Monitoring equipment to be
used; Installation requirements for monitoring equipment; Calibration
requirements/procedures; Expected accuracy of measurements/monitoring equipment;
Quality control procedures to be used.
5. Detail data analysis to be performed.