POST-ACCEPTANCE PERFORMANCE PERIOD VERIFICATION
Length: 271 wordsOfficial source
Cite as Reglamento Núm. 8682, Art. 8.05 dup2
ACTIVITIES
In order to be able to responsibly monitor and verify the Energy and Water Conservation Measures
proposed in the IGA Report, SOEP and the Government Unit shall, in coordination with the ESCO,
that must:
1. Describe variables affecting post-acceptance performance period energy or water use.
Include variables such as weather, operating hours, set point changes, etc. Describe how
each variable will be quantified, i.e., measurements, monitoring, assumptions,
manufacturer data, maintenance logs, engineering resources, etc.
2. Define key system performance factors characterizing the post-acceptance performance
period conditions. Include factors such as comfort conditions, lighting intensities,
temperature set points, etc.
3. Describe the intent of post-acceptance performance period verification activities.
4. Provide detailed schedule of post-acceptance performance period verification activities and
inspections.
5. Define requirements for the Government Unit witnessing of measurements if different than
whole project data requirements.
6. Provide details of post-acceptance performance period data to be collected, including, but
not limited to: Parameters to be monitored; Details of equipment to be monitored (location,
type, model, quantity, etc.); Sampling plan, including details of usage groups and sample
32 I Page
Energy Savings Performance Contract Program Amended Regulation
sizes, Duration, frequency, interval, and seasonal or other requirements of measurements;
Monitoring equipment to be used; Installation requirements for monitoring equipment;
Calibration requirements/procedures; Expected accuracy of measurements/monitoring
equipment; Quality control procedures to be used; Form of data to be collected (.xls, .CVS,
etc.), among others.
7. Detail data analysis to be performed.
8. Define O&M and repair reporting requirements. Detail verification activities and reporting
responsibilities of the Government and contractor on operations and maintenance items.
Define reporting schedule.