Regl. 9049, art. 107-106 dup3
CONSTRUCTION DOCUMENTS
Length: 1,361 wordsOfficial source
Cite as Reglamento Núm. 9049, Art. 107-106 dup3
[A]106.1 General. Submittal documents consisting of construction documents, special inspection
and structural observation programs, investigation and evaluation reports, and other data shall be
submitted in digital form with each application for a permit. The construction documents shall be
prepared by a registered design professional where required by the statutes of Puerto Rico. Where
special conditions exist, the code official is authorized to require additional construction
documents to be prepared by a registered design professional.
Exception: The code official is authorized to waive the submission of construction documents
and other data not required to be prepared by a registered design professional if it is found that
the nature of the work applied for is such that reviewing of construction documents is not
necessary to obtain compliance with this code, as established by the Joint Regulation.
[A]106.2 Construction documents. Construction documents shall be in accordance with Sections
106.2.1 through 106.2.6.
816
[A]106.2.1 Construction documents. Construction documents shall be dimensioned and
drawn on suitable material. Electronic media documents are permitted to be submitted where
approved by the code official. Construction documents shall be of sufficient clarity to indicate
the location, nature and extent of the work proposed and show in detail that it will conform to
the provisions of this code and relevant laws, ordinances, rules and regulations, as determined
by the code official, and as established by the Joint Regulation. The work areas shall be shown.
[A]106.2.2 Fire protection system(s) shop drawings. Shop drawings for the fire protection
system(s) shall be submitted to indicate compliance with this code and the construction
documents and shall be approved prior to the start of system installation. Shop drawings shall
contain information as required by the referenced installation standards in Chapter 9 of the
Puerto Rico Building Code.
[A]106.2.3 Means of egress. The construction documents for Alterations-Level 2,
Alterations-Level 3, additions and changes of occupancy shall show in sufficient detail the
location, construction, size and character of all portions of the means of egress in compliance
with the provisions of this code. The construction documents shall designate the number of
occupants to be accommodated in every work area of every floor and in all affected rooms and
spaces.
[A]106.2.4 Exterior wall envelope. Construction documents for work affecting the exterior
wall envelope shall describe the exterior wall envelope in sufficient detail to determine
compliance with this code. The construction documents shall provide details of the exterior
wall envelope as required, including windows, doors, flashing, intersections with dissimilar
materials, corners, end details, control joints, intersections at roof, eaves or parapets, means of
drainage, water-resistive membrane, and details around openings.
The construction documents shall include manufacturer's installation instructions that provide
supporting documentation that the proposed penetration and opening details described in the
construction documents maintain the wind and weather resistance of the exterior wall
envelope. The supporting documentation shall fully describe the exterior wall system that was
tested, where applicable, as well as the test procedure used.
[A]106.2.5 Exterior balconies and elevated walking surfaces. Where the scope of work
involves balconies or other elevated walking surfaces exposed to water from direct or blowing
rain, snow or irrigation, and the structural framing is protected by an impervious moisture
barrier, the construction documents shall include details for all elements of the impervious
moisture barrier system. The construction documents shall include manufacturer's installation
instructions.
[A]106.2.6 Site plan. The construction documents submitted with the application for permit
shall be accompanied by a site plan showing to scale the size and location of new construction
and existing structures on the site, distances from lot lines, the established street grades, and
the proposed finished grades; and it shall be drawn in accordance with an accurate boundary
line survey. In the case of demolition, the site plan shall show construction to be demolished
817
and the location and size of existing structures and construction that are to remain on the site
or plot, as established by the Joint Regulation.
[A]106.3 Examination of documents. The code official shall examine or cause to be examined
the submittal documents and shall ascertain by such examinations whether the construction or
occupancy indicated and described is in accordance with the requirements of this code and other
pertinent laws or ordinances.
[A]106.3.1 Approval of construction documents. Where the code official issues a permit, the
construction documents shall be approved in writing or by digital stamp as "Reviewed for
Code Compliance." One set of construction documents in digital format, so reviewed, shall be
retained by the code official and a copy shall be returned to the applicant. A printed copy shall
be kept at the site of work, and shall be open to inspection by the code official or a duly
authorized representative.
[A]106.3.2 Previous approval. This code shall not require changes in the construction
documents, construction or designated occupancy of a structure for which a lawful permit has
been issued and the construction of which has been pursued in good faith with this Code, and
the Joint Regulation
[A]106.3.3 Phased approval. The code official is authorized to issue a permit for the
construction of foundations or any other part of a building before the construction documents
for the whole building or structure have been submitted, provided that adequate information
and detailed statements have been filed complying with pertinent requirements of this code.
The holder of such permit for the foundation or other parts of a building shall proceed at the
holder's own risk with the building operation and without assurance that a permit for the entire
structure will be granted.
[A]106.3.4 Deferred submittals. Deferral of any submittal items shall have the prior approval
of the code official. The registered design professional in responsible charge shall list the
deferred submittals on the construction documents for review by the code official
Submittal documents for deferred submittal items shall be submitted to the registered design
professional in responsible charge who shall review them and forward them to the code official
with a notation indicating that the deferred submittal documents have been reviewed and that
they have been found to be in general conformance to the design of the building. The deferred
submittal items shall not be installed until their deferred submittal documents have been
approved by the code official.
[A]106.4 Amended construction documents. Work shall be installed in accordance with the
reviewed construction documents, and any changes made during construction that are not in
compliance with the approved construction documents shall be resubmitted for approval as an
amended set of construction documents.
[A]106.5 Retention of construction documents. A digital set of approved construction
documents shall be retained by the code official, as established by the Joint Regulation.
818
[A]106.6 Design professional in responsible charge and Designated Inspector. Registered
Design Professionals and Designated Inspectors shall comply with all applicable laws in Puerto
Rico, including Act 135 of June 15, 1967 with amendments and Act 7 of July 19, 1985 with
amendments in the certification process and the Joint Regulation. Where it is required that
documents be prepared by a registered design professional, the code official shall be authorized to
require the owner or the owner's authorized agent to engage and designate on the building permit
application a registered design professional who shall act as the registered design professional in
responsible charge. If the circumstances require, the owner or the owner's authorized agent shall
designate a substitute registered design professional in responsible charge who shall perform the
duties required of the original registered design professional in responsible charge. The code
official shall be notified in writing by the owner or the owner's authorized agent if the registered
design professional in responsible charge is changed or is unable to continue to perform the duties
and the owner and the new registered design professionals shall comply with the requirements
established in the Joint Regulation. The registered design professional in responsible charge shall
be responsible for reviewing and coordinating submittal documents prepared by others, including
phased and deferred submittal items, for compatibility with the design of the building. Where
structural observation is required, the inspection program shall name the individual or firms who
are to perform structural observation and describe the stages of construction at which structural
observation is to occur.