Regl. 9049, art. 107-107
SUBMITTAL DOCUMENTS
Length: 1,373 wordsOfficial source
Cite as Reglamento Núm. 9049, Art. 107-107
[A]107.1 General. Submittal documents consisting of construction documents, statement of
special inspections, geotechnical report and other data shall be submitted in digital form with each
permit application. The construction documents shall be prepared by a registered design
professional where required by the statutes of Puerto Rico in which the project is to be constructed.
Where special conditions exist, the building official is authorized to require additional construction
documents to be prepared by a registered design professional.
Exception: The building official is authorized to waive the submission of construction
documents and other data not required to be prepared by a registered design professional if it
is found that the nature of the work applied for is such that review of construction documents
is not necessary to obtain compliance with this code, as established by the Joint Regulation.
[A]107.2 Construction documents. Construction documents shall be in accordance with Sections
107.2.1 through 107.2.8.
[A]107.2.1 Information on construction documents. Construction documents shall be
dimensioned and drawn on suitable material. Electronic media documents are permitted to be
submitted where approved by the building official. Construction documents shall be of
sufficient clarity to indicate the location, nature and extent of the work proposed and show in
detail that it will conform to the provisions of this code and relevant laws, ordinances, rules
and regulations, as determined by the building official, as established by the Joint Regulation.
[A]107.2.2 Fire protection system shop drawings. Shop drawings for the fire protection
system(s) shall be submitted to indicate conformance to this code and the construction
documents and shall be approved prior to the start of system installation. Shop drawings shall
contain all information as required by the referenced installation standards in Chapter 9.
[A]107.2.3 Means of egress. The construction documents shall show in sufficient detail the
location, construction, size and character of all portions of the means of egress including the
path of the exit discharge to the public way in compliance with the provisions of this code. In
other than occupancies in Groups R-2, R-3, and I-1, the construction documents shall designate
the number of occupants to be accommodated on every floor, and in all rooms and spaces.
[A]107.2.4 Exterior wall envelope. Construction documents for all buildings shall describe
the exterior wall envelope in sufficient detail to determine compliance with this code. The
construction documents shall provide details of the exterior wall envelope as required,
including flashing, intersections with dissimilar materials, corners, end details, control joints,
intersections at roof, eaves or parapets, means of drainage, water-resistive membrane and
details around openings. The construction documents shall include manufacturer's installation
instructions that provide supporting documentation that the proposed penetration and opening
37
details described in the construction documents maintain the weather resistance of the exterior
wall envelope. The supporting documentation shall fully describe the exterior wall system that
was tested, where applicable, as well as the test procedure used.
[A]107.2.5 Exterior balconies and elevated walking surfaces. Where balconies or other
elevated walking surfaces are exposed to water from direct or blowing rain, snow, or irrigation,
and the structural framing is protected by an impervious moisture barrier, the construction
documents shall include details for all elements of the impervious moisture barrier system. The
construction documents shall include manufacturer's installation instructions.
[A]107.2.6 Site plan. The construction documents submitted with the application for permit
shall be accompanied by a site plan showing to scale the size and location of new construction
and existing structures on the site, distances from lot lines, the established street grades and
the proposed finished grades and, as applicable, flood hazard areas, floodways, and design
flood elevations; and it shall be drawn in accordance with an accurate boundary line survey. In
the case of demolition, the site plan shall show construction to be demolished and the location
and size of existing structures and construction that are to remain on the site or plot as
established by the Joint Regulation.
[A]107.2.6.1 Design flood elevations. Where design flood elevations are not specified,
they shall be established in accordance with Section 1612.3.1.
[A]107.2.7 Structural information. The construction documents shall provide the
information specified in Section 1603.
[A]107.2.8 Relocatable buildings. Construction documents for relocatable buildings shall
comply with Section 3112.
[A]107.3 Examination of documents. The building official shall examine or cause to be examined
the accompanying submittal documents and shall ascertain by such examinations whether the
construction indicated and described is in accordance with the requirements of this code and other
pertinent laws or ordinances.
[A]107.3.1 Approval of construction documents. When the building official issues a permit,
the construction documents shall be approved, in writing or by digital stamp, as "Reviewed for
Code Compliance." One set of construction documents in digital format, so reviewed, shall be
retained by the building official and a copy returned to the applicant. A printed copy shall be
kept at the site of work and shall be open to inspection by the building official or a duly
authorized representative.
[A]107.3.2 Previous approvals. This code shall not require changes in the construction
documents, construction or designated occupancy of a structure for which a lawful permit has
been heretofore issued or otherwise lawfully authorized, and the construction of which has
been pursued in good faith with this Code, and the Joint Regulation.
38
[A]107.3.3 Phased approval. The building official is authorized to issue a permit for the
construction of foundations or any other part of a building or structure before the construction
documents for the whole building or structure have been submitted, provided that adequate
information and detailed statements have been filed complying with pertinent requirements of
this code. The holder of such permit for the foundation or other parts of a building or structure
shall proceed at the holder's own risk with the building operation and without assurance that a
permit for the entire structure will be granted.
[A]107.3.4 Design professional in responsible charge and Designated Inspector. Registered
Design Professionals and Designated Inspectors shall comply with all applicable laws in
Puerto Rico, including Act 135 of June 15, 1967 with amendments and Act 7 of July 19, 1985
with amendments in the certification process and the Joint Regulation. Where it is required
that documents be prepared by a registered design professional, the building official shall be
authorized to require the owner or the owner's authorized agent to engage and designate on
the building permit application a registered design professional who shall act as the registered
design professional in responsible charge. If the circumstances require, the owner or the
owner's authorized agent shall designate a substitute registered design professional in
responsible charge who shall perform the duties required of the original registered design
professional in responsible charge. The building official shall be notified in writing by the
owner or the owner's authorized agent if the registered design professional in responsible
charge is changed or is unable to continue to perform the duties and the owner and the new
registered design professionals shall comply with the requirements established in the Joint
Regulation. The registered design professional in responsible charge shall be responsible for
reviewing and coordinating submittal documents prepared by others, including phased and
deferred submittal items, for compatibility with the design of the building.
[A]107.3.4.1 Deferred submittals. Deferral of any submittal items shall have the prior
approval of the building official. The registered design professional in responsible charge
shall list the deferred submittals on the construction documents for review by the building
official. Documents for deferred submittal items shall be submitted to the registered design
professional in responsible charge who shall review them and forward them to the building
official with a notation indicating that the deferred submittal documents have been
reviewed and found to be in general conformance to the design of the building. The
deferred submittal items shall not be installed until the deferred submittal documents have
been approved by the building official.
[A]107.4 Amended construction documents. Work shall be installed in accordance with the
approved construction documents, and any changes made during construction that are not in
compliance with the approved construction documents shall be resubmitted for approval as an
amended set of construction documents.
[A]107.5 Retention of construction documents. A digital set of approved construction
documents shall be retained by the building official, as established by the Joint Regulation.
39