216-RICR-50-05-7
216-RICR-50-05-7. Clean Water Infrastructure Plans (version Periodic Refile, 01/02/2002 to 08/21/2018)
RULES AND REGULATIONS FOR
CLEAN WATER INFRASTRUCTURE PLANS
[R46-15.6-INFRA]
STATE OF RHODE ISLAND AND PROVIDENCE PLANTATION
Department of Health
October 1994
AS AMENDED
January 1995
January 2002 (re-filing in accordance with
the provisions of section 42-35-4.1 of the
Rhode Island General Laws, as amended)
i
INTRODUCTION
The waters of this state are a critical renewable resource which must be protected to insure the continued
availability of safe and potable drinking water for present and future needs. It is a paramount policy of the
state to protect the purity of present and future drinking water supplies by protecting the infrastructure of
potable water, including sources, treatment plants and distribution systems. The decay of water supply
infrastructure due to deterioration or functional obsolescence can threaten the quality of water supplies
and therefore can endanger public health. Therefore, it is necessary to take timely and continuing steps to
repair and replace the infrastructure used to treat and deliver drinking water from public water suppliers.
By planning and funding for future infrastructure replacement, unexpected large capital expenditures
causing sudden increases in water rates can hopefully be avoided. The intent of this Infrastructure
Replacement Plan is to provide a planning and funding mechanism to insure that infrastructure
replacement programs are carried out by each municipality, district, agency, authority, or other entity
engaged in the supply, treatment, transmission, and/or distribution of drinking water. Goals of the plan
include the justification of a facility replacement program, the provision of a dedicated and sufficient
funding mechanism, the prioritization of infrastructure replacement, and the prevention of the erosion of
drinking water infrastructure.
These rules and regulations are promulgated pursuant to the requirements and provisions of RIGL Chapter
46-15.6 Clean Water Infrastructure of the General Laws of Rhode Island, as amended.
The terms and provisions of the rules and regulations shall be liberally construed to allow the Department
of Health to effectuate the purposes of the state law, goals and policies consistent with the Clean Water
Infrastructure Act, Chapter 46-15.6 of the General Laws of Rhode Island, as amended.
ii
TABLE OF CONTENTS
PAGE
SECTION 1
DEFINITIONS
1
SECTION 2
APPLICABILITY--PREPARATION OF PLANS
2
SECTION 3
CONFORMITY WITH OTHER LEGISLATION
2
SECTION 4
CONTENTS OF PLANS
3
SECTION 5
REVIEW OF PLANS
4
SECTION 6
FINANCING OF IMPROVEMENTS
5
SECTION 7
SEVERABILITY
6
APPENDIX 1 TYPICAL LIFE EXPECTANCY
7
1
SECTION 1.0 DEFINITIONS
Wherever used in these rules and regulations the following terms shall be construed as
follows:
1.1
Audit--the annual formal examination of the water supplier's financial statements including all
investments, interest, expenditures, and operating costs.
1.2
Commission--the Public Utilities Commission (PUC) of the State of Rhode Island.
1.3
Comprehensive Plan--the Comprehensive Plan adopted and approved in accordance with
RIGL Chapter 45-22.2, the RI Comprehensive Planning and Land Use Regulation Act. A
document prepared by each local municipality which contains the planning and implementation
program for land use, housing, economic development, natural and cultural resources, services
and facilities, open space and recreation, and circulation.
1.4
Department--the Department of Health (DOH), Division of Drinking Water Quality.
1.5
Distribution facilities--the pipes and appurtenant facilities employed specifically to deliver, to
dispense, to render or to circulate potable water directly to the consumer.
1.6
Drinking Water--potable water served to the public.
1.7
Economic life--the expected financial lifespan of a component of a public water system which
is used to depreciate the capital expense of the component.
1.8
Eligible expenditures--those costs and expenses necessary to fund, manage, and implement
the infrastructure replacement plan, only. This may include associated accounting fees,
consulting fees, replacement construction, etc.
1.9
Infrastructure--the permanent underlying framework of the public water system, including but
not limited to, supplies, transmission, storage, distribution, pumping, and treatment facilities.
1.10
Life expectancy--the expected physical lifespan of a component of a public water system.
1.11
Maintenance--a planned program of inspection, adjustment, exercise, lubrication, etc. which
allows the maximum continuous service of the equipment in the system at the lowest possible
cost to the utility as required in the Department of Environmental Management's Water
Supply Management Planning Section 8.07(c). Routine maintenance expenditures are not
eligible for funding from the Infrastructure Replacement Plan.
1.12
Rate fee--the charge per unit for public water based upon a ratio, scale, or standard relative to
the cost of supplying potable drinking water.
1.13
Rehabilitation--rehabilitation which restores existing facilities or components to a condition
which extends the physical and economic life of the component. Rehabilitation is an eligible
expenditure under the Infrastructure Replacement Plan.
1.14
Repair--expenditures to return into service a component of the infrastructure that has failed is
not an eligible expenditure under the Infrastructure Replacement Plan.
2
1.15
Replacement--new construction to substitute for existing facilities or components which can
not be rehabilitated or repaired cost effectively is an eligible expenditure under the
Infrastructure Replacement Plan.
1.16
Special account--an account established by physically opening an account designated as the
"Infrastructure Replacement Fund" that is acceptable under this Act. This account shall be
self-contained in that deposits and withdrawals are recorded by the financial institution through
a fiduciary relationship with the utility. This special account shall be a restricted receipt
account dedicated solely for funding of eligible expenditures from the infrastructure
replacement program and be administered by the general manager of the water supplier or his
designee. All receipts, income, and interest earned on these funds shall be accrued within this
special account.
1.17
Surcharge--a fee charged in addition to normal system rate fees which is used to fund
extraordinary or special conditions of the water system.
1.18
Transmission facilities--shall mean the pipes, pumping stations, and storage facilities required
to carry raw and/or potable water from a water source to or throughout an area served or to
be served by a water supply system for the specific purpose of supplying water to support a
general population.
1.19
Water supplier--any municipality, municipal department, agency, district, authority, or other
entity engaged in or authorized to engage in the supply, treatment, transmission, or distribution
of drinking water on a wholesale or retail sales basis.
1.20
Water supply sources--are Department of Health approved sources of supply connected to a
water supply system and available for distribution. These sources may be surface waters or
groundwater wells.
1.21
Water supply management plan--a plan prepared by applicable public water suppliers which
plans and implements effective and efficient conservation, development, utilization, and
protection of water supply resources consistent with the present and future needs of the State
and its people as defined in RIGL 46-15.4.
SECTION 2.0 APPLICABILITY - PREPARATION OF PLANS
2.1
All water suppliers which supply, obtain, transport, distribute, purchase, and/or sell on a
wholesale or retail basis, more than fifty million (50,000,000) gallons of water per year shall be
required to prepare, maintain, and carry out a clean water infrastructure replacement plan as
described in these regulations.
SECTION 3.0 CONFORMITY WITH OTHER LEGISLATION
3.1
The clean water infrastructure replacement plans shall be in conformity with all applicable
provisions of state and federal laws including the federal Safe Drinking Water Act (42 USC
Section 300f et seq.); Chapter 46-13 of the General Laws of Rhode Island, Public Drinking
Water Supply. Infrastructure replacement plans must be consistent with the Comprehensive
3
Plan for the community or communities associated with the water system. Infrastructure
replacement plans shall also be consistent with the Water Supply Management plans required
under Chapter 46-15.4.
SECTION 4.0 CONTENTS OF PLANS
4.1
Clean water infrastructure replacement plans shall be prepared in the format, and shall
address each of the topics listed in this section, to the extent that each is relevant to the water
supplier, the water source, the water system, and the transmission/distribution/storage system.
Systems which currently have an infrastructure replacement plan may review the existing
plan and utilize existing information to the extent that it is consistent with the intent of the
infrastructure replacement plan outlined below. The initial plan may include a schedule for the
completion of the evaluation of major components or items which require detailed
investigation. The schedule must demonstrate an expeditious, responsible, and reasonable
time period for compliance.
4.2
All principal components of the water system such as sources, reservoirs, dams, spillways,
intakes, treatment plants, pump stations, storage facilities, pumping and well equipment, shall
be listed and evaluated. Relatively small and numerous components of the system such as
water mains, distribution piping, valves, hydrants, and interconnections may be evaluated as a
group. This evaluation shall consider the following:
a. A brief description of the system with a schematic of the process flow will be included in
the plan. This description of the system may be taken directly from the Water Supply
Management Plan where relevant and is not intended as a duplicate effort but to facilitate
the evaluation of individual components. Age and condition of the existing component and
the necessity for replacement of the component within a twenty (20) year time frame
shall be evaluated. Specific components may be in need of immediate replacement while
others may extend well beyond the twenty year time frame. Replacement should be
evaluated and prioritized over a minimum of five (5) year intervals. The level of detail in
the analysis of the component should reflect the priority of the component to the proper
operation of the system as well as the age and known condition of the component. A
detailed schedule for the initial five year interval must be included. No infrastructure
replacement construction is required to take place within any time interval if demonstrated
to not be necessary.
b. Life expectancy of the component shall be determined. Life expectancy shall be
determined by design criteria, specific site conditions, maintenance records,
manufacturer's documentation, engineering evaluation, physical inspection, invasive and/
or non-destructive integrity testing, or a combination of all of the above. Records of
inspection and maintenance may be reviewed when determining the life expectancy of the
component. The attached Guideline, Appendix 1, is intended to serve as a general rule of
thumb for component life expectancy and actual life expectancy within an individual
system may be demonstrated to be significantly more or less than the Guideline value.
c. Consideration shall be given to the public water system's ability to meet current and future
requirements of the Safe Drinking Water Act. Treatment requirements should be
analyzed to the extent possible to insure that infrastructure replacement and/or
rehabilitation will comply with mandated requirements consistent with the Safe Drinking
4
Water Act.
d. A financial forecast shall be based on the analysis of the condition and life expectancy of
the existing facilities, prioritized needed repairs and replacements and amortize
proportionally such improvement requirements on an annual basis over the next twenty
years consistent with their respective life expectancy. The forecast shall include
contingency costs, range of construction costs, and/or confidence limits of the financial
forecast.
e. Infrastructure replacement shall meet the needs of the water suppliers, however priority
of anticipated replacement and grouping of replacement projects by time of replacement,
similarity of projects, and importance of the component to the system shall be considered
when establishing the schedule. Priority should be given to components which have a
known need for replacement and less detailed analysis given to relatively new
infrastructure items.
4.3
When planning infrastructure replacement, the water supplier shall consider sizing facilities to
meet the approved local comprehensive plans for existing or proposed service areas. The
existing or proposed service area shall be defined consistent with that described in the
supplier's most recent Water Supply Management Plan. Funding for proposed expansion shall
come from the capital improvement program utilizing new capital rather than from
replacement funding. It is intended that the infrastructure replacement plan evolve from the
Water Supply Management Plan and expand the concepts of capital improvement planning
initiated in the Water Supply Management Plan. The infrastructure replacement plan shall be
consistent with sound waterworks practice.
4.4
The infrastructure replacement plan must recognize and maintain existing fiscal controls and
accounting standards in accordance with Generally Accepted Government Accounting
Principles sufficient to ensure fiscal responsibility for the evaluation and implementation of the
infrastructure replacement. These fiscal controls and accounting standards must be
established where none currently exist. The financial requirements of the plan shall conform
to those outlined in Section 6.0 of these regulations.
4.5
Funds from the watershed protection fund may be used for the preparation of clean water
infrastructure replacement plans up to fifty (50) percent of the cost of the plan.
Disbursements from the fund shall be in accordance with Chapter 46-15.3-11 of the Public
Drinking Water Resources Board Operating Fund. The remaining costs are eligible for
funding through the Safe Drinking Water Revolving Loan Fund. The plan shall incorporate
the proposed rate structure impacts, schedule of proposed rate changes, and schedule for full
funding consistent with the funding requirements for scheduled infrastructure replacement.
SECTION 5.0 REVIEW OF PLANS
5.1
Water suppliers subject to the requirements of this chapter shall file six copies of the clean
water infrastructure plan with the Division of Drinking Water Quality of the Department of
Health (the Department). Plans must be submitted no later than one year subsequent to the
date the system's water supply management plan is due in accordance with RIGL Section 46-
15.4-4.
5
5.2
The Department shall coordinate review of the plan with the Department of Environmental
Management's Division of Water Supply Management, the Department of Administration's
Division of Planning, the Water Resources Board, and the Public Utilities Commission. The
PUC shall only review Plans for those systems which are regulated by the PUC. Each
Department shall have 120 days to review the plan and submit comments to the Department
of Health. Upon consideration of the comments, the Department shall determine if the plan
complies with the requirements of these regulations within two hundred forty days (240) of the
initial submission. A thirty day public comment period is inclusive in this two hundred forty
day (240) review period.
5.3
Water suppliers shall review and update their infrastructure replacement plans at a minimum
frequency of every five years. Major modifications or revisions to the infrastructure
replacement plan shall be submitted for review more frequently as necessary.
5.4
Water suppliers shall implement the infrastructure replacement plan according to the approved
plan. On-site review of facility components may be conducted by the Department when
appropriate and/or applicable. The responsible official of the water supply system shall be
required to verify that construction expenditures are consistent with the plan.
SECTION 6.0 FINANCING INFRASTRUCTURE IMPROVEMENTS
6.1
Each water supplier subject to the requirements of this chapter shall establish a separate
special account designated as the Infrastructure Replacement Fund to be held as a restricted
receipt account and to be administered by the water supplier solely to implement and carry out
the replacement or rehabilitation of infrastructure in accordance with the approved plan. The
dedicated account should be invested in accordance with the standards established for the
agency, municipality, or water supplier.
6.2
The costs of programs to implement infrastructure replacement shall be paid by the users of
the water system at a rate directly proportional to the users' consumption of water. Charges
shall be limited to those necessary and reasonable for implementation of the plan. These
charges shall be based upon the annual funding requirements of the facility improvements
necessitated over each successive twenty year period.
6.3
Interest earned on this account shall be credited to this account only. Accumulated funds in
excess of that estimated to be necessary to implement the plan shall revert to the rate payers
of the system on a biannual basis. Funds will be allowed to accumulate with the intent to build
sufficient capital to finance the estimated costs of major projects. It is understood that annual
investments may be necessary over many years to fund major projects. Funds accumulated
that are in excess of that estimated to implement the plan will cause the water supplier to
reduce the future charges for infrastructure replacement.
6.4
Water suppliers may alternatively fund the infrastructure replacement program through partial
or complete external funding at the option of the water supply system. Debt service and debt
service issuance costs for any and all funding shall be an eligible expense as part of the
program's funding requirements.
6.5
The Public Utilities Commission, as to water suppliers within its jurisdiction, shall permit an
increase for just and reasonable infrastructure replacement in the portion of the water
6
suppliers' rate structure to comply with this chapter and shall allow the water supplier to add
this required funding to its rate base in accordance with this chapter. Proposed increases in
rates by regulated water utilities to finance infrastructure improvements shall be filed and
reviewed in conformance with Chapter 39 of the RI General Laws.
6.6
The applicable section of the water supplier's annual audit shall be submitted to the
Department to verify compliance with the funding intentions of the infrastructure replacement
plan. The dedicated fund for infrastructure replacement will be a separate line item in the
audit. Financial and summary status reports shall be submitted for each on-going project
which outlines funds spent on the project, funds remaining, percentage of completion, and a
brief description of work completed and work remaining. Project expenditures must be
consistent with the plan and be eligible expenditures under the plan. Audits shall be submitted
within 180 days from the end of the water suppliers fiscal year. Extensions will be allowed for
reasonable cause.
SECTION 7.0 SEVERABILITY
7.1
If any provision of these rules and regulations or the application thereof to any person or
circumstance is held invalid by a court of competent jurisdiction, the remainder of the rules
and regulations shall not be affected thereby. The invalidity of any section or sections or parts
of any section or sections shall not affect the validity of the remainder of these rules and
regulations.
7
APPENDIX 1
TYPICAL LIFE EXPECTANCY
EQUIPMENT
YEARS
Source of supply plant
Structures and improvements
35-40
Collecting/impounding reservoirs
50-75
Intake structures
35-45
Wells and springs
25-35
Galleries and tunnels
25-50
Supply mains
50-75
Pumping plant
Structures
35-40
Pumping equipment
10-15
Other pumping plant
20
Water treatment plant
Structures
35-40
Water treatment equipment
15-20
Transmission/Distribution
Structures
35-40
Reservoirs and tanks
30-60
Mains
50-75
Services
30-50
Meters
15
Hydrants
40-60
General plant
Structures
35-40
Furniture/equipment
15-20
Transportation equipment
7
Stores equipment
10
Tools, shop equipment
7-10
Laboratory equipment
10-15
Power operated equipment
10
Communication equipment
10