220-RICR-60-15-1
220-RICR-60-15-1. Regulations for Public Library Construction Reimbursement (version Adoption, 08/06/2018 to 01/04/2022)
1.1 Authority
A. Pursuant to R.I. Gen. Laws
§ 29-6-6, the Office of Library and Information Services may award
state grant-in-aid to reimburse the construction or improvement of
public library facilities in a city or town.
B. Pursuant to R.I. Gen. Laws
§§ 29-3.1-7(8) and 29-3.1-4.1(b)(7), the Chief of Library Services
is charged to develop standards and regulations for public library
development and the Library Board of Rhode Island is charged to
approve such standards and regulations.
1.2 Purpose
The purpose of this Part is
to set regulations for Public Library Construction Reimbursement, to
govern the award of state grant-in-aid for library construction that
is undertaken to improve library facilities and meet community needs
for services as outlined in the library’s strategic plan.
1.3 Definitions
A. The following terms shall
have the following meaning:
1. "Adjusted equalized
weighted assessed valuation" means the full and fair market
value of real estate, tangible personal property and motor vehicle
wealth of all cities and towns as of the third preceding calendar
year as prescribed by R.I.
Gen. Laws 16-7-21 .
2. "Maintenance and
repair" means the building maintenance and repair that must be
undertaken periodically due to wear and tear of the facility and/or
the fixed life of building features such as HVAC systems, roofs,
carpets, wall coverings, and other fixed assets within the building.
3. "Professional
librarian" means a librarian that holds a master's degree in
library and information science from a graduate school accredited by
the American Library Association.
4. "State fiscal year"
means the period from July 1 through June 30.
1.4 Eligibility Requirements
A. The library must be legally
established as a free public library according to R.I. Gen. Laws
Chapter 29-4.
B. The library and its
municipality must be eligible for state aid to libraries in
accordance with R.I. Gen. Laws § 29-6-3 and meet all requirements
therein.
C. The library must have a
regular source of operating income and shall furnish proof that the
governing body providing operating funds has agreed to provide
appropriations so that the new or improved facility can be properly
operated, and services to be provided will be adequately funded such
that the library continues to meet the Minimum Standards and
Regulations for Rhode Island Public Libraries (Part 2 of this
Subchapter).
D. The library must
demonstrate that 100% (one hundred percent) of the funds required to
complete the project in its entirety are secured and available at the
time a reimbursement agreement is entered into with the library. The
library must provide for the total funds needed to complete the
project, including the state share and interest costs, until
reimbursement of the state share begins in the state fiscal year
following the completion, audit, and acceptance of the project by the
Office of Library and Information Services.
E. The library must clearly
demonstrate the need for the project, relating its plan for
construction to the current and future needs of the community and the
need for library services in the area. The statement of need must
include documentation that current public library facilities in the
municipality are inadequate for the provision of services to the
library's defined service area and that the library's plans for
construction will adequately address these needs for both the short
and long-term life of the facility.
1.5 Project Requirements
A. A professional librarian
with experience of library construction projects must serve as an
independent consultant, assisting the library director, library board
and/or building committee and the architect throughout the planning
and construction of the building.
B. There must be a written
building program prepared by the consultant, or the library director
with the guidance of the consultant, prior to the designing of the
building by the architect. The building program must be in keeping
with the library's long-range plan and informed by a long-term
community needs assessment.
C. The library must assure
that the project in its entirety is in compliance with applicable
state and federal laws including, but not limited to:
1. Award of Municipal
Contracts, R.I. Gen. Laws Chapter 45-55;
2. Minority Business
Enterprises R.I. Gen. Laws Chapter 37-14.1;
3. Equal Employment
Opportunity R.I. Gen. Laws Chapter 28-5.1;
4. The Green Buildings Act,
R.I. Gen. Laws Chapter 37-24;
5. Historical Preservation
R.I. Gen. Laws Chapter 42-45; and
6. The Americans With
Disabilities Act of 1990, Pub. L. No. 101-336, 104 Stat. 328 (1990).
D. Facilities built or
remodeled under a construction agreement with the Office of Library
and Information Services must continue to be used as free public
library facilities and continue to meet eligibility requirements for
state aid to libraries. The library will not dispose of or encumber
its title or other interests in the site and facilities during the
period of state reimbursement without consultation with and the
express written permission of the Office of Library and Information
Services
E. The library will follow
such procedures, submit such reports, maintain such records, and
afford access thereto, as the Office of Library and Information
Services sets forth in its regulations.
1.6 Construction Reimbursement
Funding and Priorities
A. Priority will be assigned
to projects based on ability to pay, with communities in the lowest
quartile of "adjusted equalized weighted assessed valuation"
ranked highest.
B. Priority will be given to
those communities that have not previously completed a library
construction project involving state reimbursement funding.
C. Any city, town or public
library receiving construction reimbursement funding shall not be
eligible to apply for additional construction funding for the same
facility until the year following the fiscal year in which the state
completes payment for a previous project.
D. Agreements for
reimbursement of construction projects will be entered on a priority
basis, with the estimated total amount required for library
construction reimbursement payments in any given fiscal year not to
exceed five million dollars for all projects.
E. State reimbursement may be
made available for up to fifty percent of the total allowable project
costs according to R.I. Gen Laws § 29-6-6, within the following
parameters for maximum reimbursement amounts and/or total state
share:
1. Construction costs are
eligible for fifty percent reimbursement of expenditures up to the
amount of three hundred dollars ($300) per square foot for new
construction or two hundred and fifty dollars ($250) per square foot
for renovation and remodeling. If the actual construction costs
exceed one or both of these amounts per square foot, the state share
shall be based on the not-to-be-exceeded amounts. Cost per square
foot is determined by the cost of contracts for new construction
and/or contracts for expansion, remodeling and alteration of existing
buildings.
2. Architect's fees will be
reimbursed up to an amount equal to 10% of the total cost of
contracts for construction; any amount in excess of 10% of the total
construction costs is not reimbursable.
3. Site costs, including
demolition, sitework, the acquisition of a site or building, site
improvement and parking lots, are reimbursable up to the lesser
amount of one million dollars or 10% (ten percent) of the total
project cost less the site costs.
4. Furniture, fixtures and
equipment are reimbursable up to the amount of 10% (ten per cent) of
the total project cost.
5. The total amount of
reimbursement for any project shall not exceed ten million dollars.
F. The reimbursement amount
will be determined by the Office of Library and Information Services.
Should total requests for funding exceed the maximum amount
available, the Office of Library and Information Services will
determine the grant amount based on project priority and
demonstration of need.
1.7 Application Procedures
A. During the early planning
phase of a construction project, the library shall submit a letter of
intent to the Office of Library and Information Services outlining
the timeline and approximate cost of the project.
B. The library shall submit a
preliminary project budget to the Office of Library and Information
Services based on the building program as soon as it is available.
C. Upon completion of
preliminary estimates and preliminary architectural plans and
drawings, the library shall submit a construction reimbursement
application to the Office of Library and Information Services. The
Office of Library and Information Services will review the
application, schematic plans and site, and provide a review of the
project's potential eligibility for reimbursement to the library.
D. The Office of Library and
Information Services will review the final construction plans and
documents with the library and architect and provide a final
assessment of the project’s eligibility for construction
reimbursement. The Office of Library and Information Services may
approve, reject or recommend changes to the project.
E. The Office of Library and
Information Services will participate in the development of the loan
or mortgage agreement, assuring the lender of its participation in
the project and reviewing and approving the terms of the loan(s) for
the state share of the project. Neither the State of Rhode Island
nor the Office of Library and Information Services shall be named as
a guarantor in any financing agreement.
F. Upon final approval of the
project, the Office of Library and Information Services will enter
into a reimbursement agreement with the library.
1.8 Allowable and Non-Allowable
Costs
A. Allowable costs include the
following
1. Construction of new
buildings to be used specifically as public library facilities.
2. Expansion, remodeling, and
alteration, as distinguished from maintenance and repair, of existing
buildings to be used for public library purposes.
3. Construction, expansion,
remodeling and alteration of the portion of a multipurpose building
in which a library is to be housed. Costs relating to those portions
of the shared mechanical, meeting room and multipurpose areas which
are included in the square footage of the library will also be
eligible.
4. Expenses incurred within
three fiscal years preceding the fiscal year in which the project was
approved that are related to:
a. Acquiring land for a new
building or expansion of an existing library building.
b. Acquiring a building to be
converted to a library and expanded, if necessary.
c. Such expenses must
constitute the transaction cost of acquiring the building, or a
transfer of public funds.
5. Site grading, improvement
of land, and landscaping for public library use areas.
6. Parking lots, when part of
a larger construction project.
7. Independent library
building consultant.
8. Architectural, engineering
and related inspection expenses.
9. Furnishings and equipment.
10. Fire suppression systems,
when part of a larger project.
11. Expenses related to
meeting a high-performance green building standard such as but not
limited to the Leadership in Energy and Environmental Design (LEED)
standard.
B. Non-allowable costs include
the following:
1. Library materials.
2. General operating and
office supplies.
3. Fundraising costs.
4. Non-public library use
costs for a library or multipurpose building.
5. Salaries of in-house
administration or library staff.
6. Feasibility studies.
7. Lease of facilities,
service, equipment, or maintenance contracts.
8. Moving expenses.
9. Landscaping for non-public
library use areas.
10. Parking lots which are not
part of a larger construction project.
11. Legal fees (except those
associated with borrowing the state’s share of the project costs).
1.9 Bidding and Contractor
Requirements
A. After a reimbursement
agreement has been signed with the Office of Library and Information
Services, the library will secure the services of a contractor
utilizing open cooperative bids in accordance with state regulations
for the award of contracts by municipalities (R.I. Gen Laws Chapter
45-55).
B. After the opening of the
bids, the library shall provide the Office of Library and Information
Services with a tabulation of bids received.
C. The library shall award the
contract to the responsive and responsible bidder whose bid is either
the lowest bid price, or lowest evaluated or responsive bid price
(R.I. Gen. Laws § 45-55-5).
D. The actual construction
work will be performed by the lump sum (fixed price) contract method.
Use of this method does not preclude the use of a construction
manager if this is otherwise allowed by the governing body.
E. The successful bidder must
comply with all state laws applicable to state funded projects and
construction, including, but not limited to, Minority Business
Enterprises (R.I. Gen. Laws § 37-14.1) and Equal Employment
Opportunity (R.I. Gen. Laws § 28-5.1). Compliance with state laws
must be documented and transmitted to the Office of Library and
Information Services prior to the library's award of contract to the
successful bidder. A contractor's failure to meet these requirements
constitutes non‑compliance.
F. The project
contractor/subcontractor(s) shall comply with all applicable federal
laws, including but not limited to the Davis Bacon Act as
supplemented by the U.S. Department of Labor regulations and the
Copeland Anti-Kickback Act.
G. After signing the contract
with the successful bidder, the library will submit a copy of the
construction contract to the Office of Library and Information
Services.
H. The library or its designee
will provide the Office of Library and Information Services with the
official record of all construction project meetings in a timely
manner. The library or its designee will also provide the Office of
Library and Information Services with all approved payment requests
and copies of approved amendments to the contract (change orders).
1.10 Display of Signs
A. The site of the
construction project shall display a sign of standard size or in
accordance with local ordinances including the statement that state
funds administered by the Rhode Island Office of Library and
Information Services are being used for such construction.
B. The completed building
shall include a plaque indicating the date of completion and sources
of funds, including the statement that project funding includes state
funds administered by the Rhode Island Office of Library and
Information Services.
1.11 Completion of Project
A. The library shall complete
its construction project within two years of signing a construction
agreement with the Office of Library and Information Services, and in
accordance with the application and approved drawings and
specifications.
B. Upon completion of the
project, the library shall submit a Certificate of Substantial
Completion to the Office of Library and Information Services.
C. The Office of Library and
Information Services or its designee shall initiate a final audit of
the project within four (4) weeks of receiving the Certificate of
Substantial Completion and conclude its review within four (4) weeks,
subject to the provision of complete documentation as requested by
the Office of Library and Information Services.
D. The audit shall be
conducted in accordance with the funding principles established by
the Office of Library and Information Services. The library shall
provide the Office of Library and Information Services, through its
authorized representative, access to and the right to examine all
records, books, papers, or documents related to the grant.
1.12 Reimbursement and Grant
Conclusion
A. Reimbursement payments will
begin in the state fiscal year that follows the fiscal year in which
the project was completed, audited and accepted. Reimbursement will
be paid to the municipality if a municipal bond or loan is used for
funding, or to the library in all other instances.
B. Reimbursement payments will
be made over the course of twenty (20) years. The State of Rhode
Island may accelerate payments, pay down the principal of any loan,
or pay the balance of any loan in a lump sum payment at its sole
discretion.
C. Any library or municipality
that refinances any loan covering the state share must receive
approval from the Office of Library and Information Services prior to
entering any agreement that modifies the terms of the original loan.
Any modified loan agreement must be submitted to the Office of
Library and Information Services.
D. The library shall retain
all financial and construction records for three years following the
final reimbursement payment or until notified by the Office of
Library and Information Services that records are no longer needed
for program administration or review.