250-RICR-140-05-7
250-RICR-140-05-7. Solid Waste Regulation No. 7 Facilities That Process Construction and Demolition Debris (version Periodic Refile, 12/31/2001 to 03/15/2018)
STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS
DEPARTMENT OF ENVIRONMENTAL MANAGEMENT
OFFICE OF WASTE MANAGEMENT
SOLID WASTE REGULATION NO. 7
FACILITIES THAT PROCESS
CONSTRUCTION AND DEMOLITION DEBRIS
EFFECTIVE DATE- JANUARY 1997
AMENDED APRIL 2001
TABLE OF CONTENTS
7.1.00 GENERAL INFORMATION & REQUIRED PLANS
1
7.1.01 General Information
1
7.1.02 Radius Plan
2
7.1.03 Site Plan
2
7.1.04 Construction and Engineering Plans
3
7.1.05 Operating Plan
3
7.1.06 Closure Plan
4
7.2.00 FACILITIES THAT PROCESS CONSTRUCTION AND DEMOLITION DEBRIS -
OPERATING STANDARDS
5
7.2.01 General
5
7.2.02 Storage
5
7.2.03 Wastewater and Leachate
6
7.2.04 Groundwater Monitoring Wells
6
7.2.05 Buffer
6
7.2.06 Fire Protection
6
7.2.07 Equipment Failure and Shutdown Provisions
7
7.2.08 Closure Fund Agreement or Closure Bond
7
7.3.00 CONSTRUCTION AND DEMOLITION DEBRIS: REUSE, SAMPLING AND
TESTING REQUIREMENTS
8
7.3.01 General Information
8
7.3.02 Screenings: Reuse, Sampling and Testing Requirements
9
7.3.03 Wood Chips: Reuse, Sampling and Testing Requirements
10
7.4.00 APPLICABILITY
11
Rule 7.00-Appendix
12
1
SOLID WASTE REGULATION NO. 7
FACILITIES THAT PROCESS CONSTRUCTION AND DEMOLITION DEBRIS
7.1.00
GENERAL INFORMATION & REQUIRED PLANS
7.1.01
General Information:
(a)
Pursuant to R.I. Gen. Laws §23-18.9-8, any person who desires to construct,
develop, establish, manage, own, operate, or maintain a construction and
demolition debris processing facility, as defined in Rule 1.00 must obtain a solid
waste management facility license from the Department in accordance with the
requirements set forth in Rules 1.00 and 7.00 of these Rules and Regulations.
(b)
Processing facilities that accept 50 tons per day or less of construction and
demolition debris, as construction and demolition debris is defined by R.I. Gen.
Laws §23-18.9-7(7) and these regulations, are exempt from the requirement of
obtaining a solid waste management facility license; however they are not exempt
from complying with all other applicable requirements, which shall include
submittal and approval of all applicable required information prior to operation, for
the construction and operation of a construction and demolition debris processing
facility, and are subject to the Rules and Regulations for such facilities. A
"License Exemption Form" (Rule 7.00 Appendix "A") shall also be completed and
filed with the Department to register qualifying facilities.
(c)
Facilities that which receive any of the following types of materials do not qualify
for the exemption set forth in subsection (b) above and must apply for a solid
waste management facility license. These materials include solid waste that is not
construction and demolition debris (even if resulting from the construction,
remodeling, repair and demolition of structures and roads and land clearing),
including but not limited to, asbestos, garbage, corrugated container board,
electrical fixtures containing hazardous liquids such as fluorescent lights,
fluorescent light ballasts or transformers, carpeting, furniture, appliances, tires,
drums, containers greater than ten gallons in size, any containers having more than
one inch of residue remaining on the bottom, and fuel tanks. Specifically excluded
from the definition of construction and demolition debris is solid waste (including
what otherwise would be construction and demolition debris) resulting from any
processing technique, other than that employed at a Department-approved
construction and demolition debris processing facility, that renders individual
waste components unrecognizable, such as pulverizing or shredding.
(d)
No license or registration shall be issued or be renewed if the facility has any
existing violations of these rules and regulation during the time of application or
request for renewal. The Department is authorized to deny, suspend, or revoke a
2
license or registration, or deny a license renewal or registration renewal where it
finds there has been a failure to comply with regulations established by the
Department, or where the applicant, licensee, or registrant is not in compliance
with any approved operating plan or engineering plans adopted pursuant to these
Rules and Regulations. The Department may also issue a Notice of Violation with
administrative penalties. Licenses and registrations issued pursuant to this section
are non-transferrable.
(e)
Granting of a license, license renewal, registration, or permission for an equipment
addition shall in no way effect the applicant's responsibility to meet all federal and
state laws, local zoning and other local codes or ordinances.
(f)
Construction and demolition debris processing facilities and other processing
facilities that accept 50 tons per day or less of construction and demolition debris
must demonstrate, through records maintained at the facility, and provided to the
Department (upon request), that seventy-five percent (75%) of all material
received by the facility are processed and removed from the site within six (6)
weeks of receipt on a continuous basis, and that in no case stores material on site
for over three (3) months.
(g)
All solid waste management facilities that process or separate construction and
demolition debris and generate screenings and/or wood chips must comply with
Rule 7.3.00.
7.1.02
Radius Plan: A radius plan including all the information listed below shall be submitted
for approval with each application for a registration, license or renewal. The radius plan
must be drawn to a minimum scale of one inch to two hundred feet (1" = 200') adjusted
to fit on a standard 24 x 36 inch sheet and include all areas within one-quarter (1/4) mile
radius out from all property lines of the site. The required information includes:
(a) Zoning of the area as required in Rule 1.5.05 above
(b) All buildings and dwellings
(c) All water supplies (wells, etc.)
(d) All surface water courses
(e) All roads
(f)
Legal boundaries of site certified by a Registered Land Surveyor in the State
of Rhode Island
(g) North arrow
(h) Extent of 100 year floodplain (where applicable)
(i)
Locus Plan
7.1.03
Site Plan: A site plan including all of the information listed below for all areas within
the site shall be submitted for approval with each application for a registration, license
or renewal. The site plan must be drawn to a minimum scale of one inch to fifty feet
3
(1"=50') and adjusted to fit on a standard size (24" x 36") sheet. The required
information includes:
(a) Existing and proposed contours at two (2) foot contour intervals or less
(b) Buildings
(c) Roads
(d) Utilities
(e) Surface water courses (if any)
(f)
Wells (if any)
(g) Site drainage facilities
(h) Groundwater monitoring wells, if required by Rule 7.2.04
(i)
Unloading, processing and storage areas
(j)
Legal Boundaries of site certified by a Registered Land Surveyor in the State
of Rhode Island
(k) Fences and gates
(l)
Weighing facilities
(m) Locations of buffer zones
(n) On-site traffic patterns
(o) Landscaping
(p) North arrow
(q) Any and all freshwater wetlands as defined by Department Rules and
Regulations
(r)
Legend
7.1.04
Construction and Engineering Plans: A preliminary set of construction and engineering
plans and specifications relating to all buildings and equipment of the facility must be
submitted for approval to the Department with each application for a license or renewal.
This set shall be sufficient in detail to allow for a comprehensive review. A complete
set of final plans approved by the Department shall be a condition of the license prior to
construction or operation.
7.1.05
Operating Plan: An operating plan shall be submitted for approval by all construction
and demolition debris processing facilities and other processing facilities that accept 50
tons per day or less of construction and demolition debris. Said plan shall include, at a
minimum, information on all of the areas listed below. The duration of the operating
plan shall equal that of the license, where applicable, and shall be updated with each
application for renewal or earlier if necessary. Any changes or additions to the facility's
operation subsequent to the approval of the operating plan, including new equipment
additions, shall be submitted to the Department for approval prior to the time that
changes will be implemented. The following information, at a minimum, shall be
included in the plan:
(a) Description of the overall operation and function of all processing equipment
to be used
4
(b) Operating hours
(c) Operating and design capabilities
(d) Types of materials to be accepted, processed, stored, recycled and/or disposed
of at a licensed facility
(e) Personnel and duties
(f)
Dust Control Program
(g) Odor Control Program
(h) Litter Control Program
(i)
Vector Control Program
(j)
Groundwater Monitoring Program if required by Rule 7.2.04
(k) Final disposal quantities and arrangements for non-recyclables and processing
residue
(l)
Communications equipment available
(m) Provisions for limited access
(n) Description of program for providing records containing the date, time,
weight of construction and demolition debris to be processed and registration
of each vehicle unloading or loading materials at the facility
(o) Weighing facilities or other volume accounting method
(p) Fire control and prevention provisions approved by the local fire chief
including a contingency plan for fires in storage areas and/or unprocessed
stockpile areas
(q) Methods describing how non-processible waste, hazardous waste and waste
not authorized by the Department will be identified, handled and removed
from the facility
(r)
Methods describing how adulterated wood waste [treated wood, painted
wood, coated wood and any other wood that is not clean] will be identified
and separated from the waste stream being processed, such that it will not be
recycled and re-used with unadulterated wood waste
(s)
Identification of how "recyclable materials" and "recyclables" which cannot
be marketed will be disposed of
(t)
Sampling and Testing plan for processed material containing that information
required by Rule 7.3.00 of these Regulations
(u) Identification of proposed markets and the names and address of destinations
for "recyclable materials" and "recyclables"
(v) Identification of provisions or methods of solid waste and leachate
containment
(w) Routine maintenance and house cleaning schedules
(x) Erosion/Sedimentation Control Plan
7.1.06
Closure Plan: The applicant shall submit for approval a closure plan that which includes
information on the following:
(a) Fences, gates and any other security measures to prevent unauthorized access
to the site during closure and post-closure activities.
5
(b) Legal boundaries
(c) Measures taken to remove all remaining refuse and residue
(d) Planned or estimated year or time period of proposed closure
(e) Methods of restricting access and preventing additional waste disposal
(f)
Methods of protecting ground and surface water
(g) Intended future use of the facility
(h) A Closure Fund or Closure Bond shall be established to ensure proper closure
of the facility. The Closure Fund shall establish and maintain the amount
necessary for a third party closure and shall include all costs necessary for
adequate closure. Periodic review and adjustments of the fund must be done
as required. The terms and conditions of the Closure Fund shall be set forth in
a Closure Fund Agreement as required by Rule 7.2.08.
(i) Measures taken to stabilize all disturbed soils.
7.2.00
FACILITIES THAT PROCESS CONSTRUCTION AND DEMOLITION DEBRIS -
OPERATING STANDARDS
7.2.01
General: All construction and demolition debris processing facilities and processing
facilities that accept 50 tons per day or less of construction and demolition debris shall
meet the requirements set forth in this rule in addition to the General Operating
Standards set forth in Rule 1.00 and other applicable requirements set forth in these
Rules and Regulations.
7.2.02
Storage:
(a)
The storage of unprocessed and/or processed construction and demolition debris
stockpiles is limited in size to the financial assurance to be posted for closure costs
as required in Rules 7.1.06 and 7.2.08. For example if the closure cost estimate is
based on the disposal of a 1000 ton stockpile of unprocessed construction and
demolition debris, the facility must limit its unprocessed stockpile to 1000 tons.
(b)
The facility must be able to demonstrate through records maintained at the facility,
and provided to the department (upon request), that seventy-five percent (75%) of
all material received by the facility is processed and removed from the site within
six (6) weeks of receipt on a continuous basis, and in no case shall the facility store
material on site for over three (3) months.
(c)
Storage of unprocessed and/or processed construction and demolition debris must
be in designated areas, and stockpiles must not exceed twenty (20) feet in height
and fifty (50) feet in width. A minimum separation of fifty (50) feet must also be
maintained between stockpiles, and between stockpiles and buildings or other
structures. In addition, unprocessed and/or processed construction and demolition
debris must not be compacted, or covered with soil or other materials. Processing
6
of materials utilizing compaction equipment may be allowed only with prior
Department approval.
7.2.03
Wastewater and Leachate: All water used in processing the construction and demolition
debris, and cleaning of the facility, as well as leachate from any refuse collected in
storage pits or transfer areas, shall be disposed of in a manner that will not pollute any
source of private or public water supply, or any of the waters or groundwaters of the
State and shall be disposed of in accordance with all state and federal laws and
regulations.
7.2.04
Groundwater Monitoring Wells: Facilities that process construction and demolition
debris may be required by the Department to install monitoring wells at locations
approved by the Department. A hydrogeological report and water quality monitoring
plan may be required based on the following factors:
(a) Size, type and location of storage stockpiles;
(b) Length of time unprocessed materials will be stored;
(c) Groundwater classification and proximity to groundwater drinking wells
(public and private);
(d) Proximity to and classification of surface water bodies, flowing water bodies
and freshwater wetlands; or
(e) Other factors determined by the Department that may be necessary to protect
the health, welfare and safety of the public and the environment.
7.2.05
Buffer: A buffer zone, or approved equally protective alternative measure(s) must be
identified and maintained between all processed and unprocessed construction and
demolition debris stockpiles, processing activities and the property line of the facility.
Said buffer zone must be of sufficient distance to address dust, odors, litter, or any other
concern or condition identified by the Department. Alternative measures may include,
but are not limited to enclosing operations and/or storage within the confines of a
protective structure, fencing, screening, vegetation or approved equal.
7.2.06
Fire Protection: A facility shall not pose a hazard to the health and safety of persons or
property from fires. No facility that processes construction and demolition debris shall
be issued a license, registration, or renewal unless it has submitted a fire protection plan
that has been approved by the local fire chief, or his or her designee, of the district in
which the facility is located. In addition, the following requirements must be met:
(a) All facilities that process construction and demolition debris shall submit site
locator plans, site sketches, and operating plans to the Department and to the
local fire chief for their review and approval so as to provide emergency
service whenever called.
(b) There shall be within 1000 feet of the facility and storage stockpiles, either an
adequate supply of water under pressure or the equivalent of cover material
7
for use exclusively in fighting fires or other equivalent method that which
meets the approval of the Department and the local fire chief. Cover material
for the purposes of extinguishing a fire shall be required in the event that the
construction and demolition debris is stored outside of the confines of a
protective structure.
(c) All facility equipment including but not limited to, dozers, front end loaders
and compactors shall be supplied with fire extinguishers.
(d) The above required elements must be included in the facility's fire
contingency plan.
(e) The local fire chief or his or her designee is authorized to conduct random,
unannounced inspections of facilities licensed or registered under this
regulation to insure continued compliance with the approved fire protection
plan. If any facility, notified by the local fire chief at the time of inspection, is
found to be in non-compliance with the approved plan said facility shall
immediately cease operation until such time as they correct any deficiency
and the local fire chief or his or her designee finds the facility is in
compliance with the approved fire protection plan.
(f)
If the Department is notified in writing by the local fire chief that any facility
is found to be in violation of the fire protection plan under this regulation on
three separate inspections, within any three year time period, said facility shall
have their license or registration to operate under this regulation revoked.
7.2.07
Equipment Failure and Shutdown Provisions: All facilities shall have an alternate
method of disposal, approved in writing by the Department, with another solid waste
management facility for use in the event of equipment failure or forced shutdown. In the
event of equipment failure or forced shutdown, storage of unprocessed materials must
not exceed the Department approved storage quantity as specified in Section 7.2.02.
7.2.08
Closure Fund Agreement or Closure Bond:
(a) Every facility shall establish a closure fund agreement with the Department.
The facility shall establish and maintain a joint depository account in the
name(s) of the facility and the Department at a federally insured financial
institution establishing a closure fund as required by 7.1.06(h), and 7.1.06(i).
(b) A facility shall be permitted to withdraw funds from the account described in
paragraph (a) of this section only with the prior written approval of the
Department and only for the purposes of closure as described in the closure
plan described in and submitted as a requirement of Rule 7.1.06.
(c) As a precondition to acceptance of any materials at the facility or within six
(6) months of the effective date of these regulations relative to any existing
facility, the facility must have on deposit in the Closure Fund an amount
sufficient to fully finance closure of the facility at capacity.
8
(d) Each facility must submit to the Department on a quarterly basis a statement
generated from the financial institution representing the amount held in the
Closure Fund.
(e) In the event that the amount in the Closure Fund exceeds the amount for
which normal federal insurance is provided, it shall be the responsibility of
the facility to acquire full insurance for the total amount of the closure fund
and/or to establish any additional accounts necessary subject to the provisions
of this section.
(f)
No facility shall have the right to withdraw, pledge, mortgage, assign,
transfer, encumber or otherwise alienate funds from the Closure Fund without
the prior written approval of the Department.
(g) In the event that the amount in the Closure Fund is not sufficient to finance
complete closure, the facility is responsible for the full cost to complete
closure.
(h) As an option to the use of a closure fund depository account as described in
Rule 7.2.08(a) -7.2.08(g), the facility shall establish and maintain a closure
bond in the amount necessary to properly close the facility when it is at full
capacity. This closure bond shall be established as a pre-condition for
licensure or registration as an approved facility.
7.3.00
CONSTRUCTION AND DEMOLITION DEBRIS: REUSE, SAMPLING AND
TESTING REQUIREMENTS
7.3.01
General Information:
(a) All facilities that process or separate construction and demolition debris and
generate screenings and/or wood chips for reuse must sample and test these
materials in accordance with Rules 7.3.02 and 7.3.03.
(b) Any costs associated with the testing of these materials by the facility or by
the Department to verify the results of the facility's tests shall be borne by the
facility. Each facility must establish a fund with the Department to cover the
costs of these tests. The amount required in this fund must be indicated in the
facility operating plan and must be based on the number of tests required for
the quantity of materials processed or separated at the facility. At all times,
the fund established pursuant to this section must equal or be greater than the
cost of two (2) rounds of sampling.
9
7.3.02
Screenings: Reuse, Sampling and Testing Requirements:
(a) The Department may approve the use of screenings for use as an alternative
daily cover on landfills in the State if it can be demonstrated that the
screenings meet the criteria in a landfill's approved operating plan, and are
capable of meeting the following minimum performance criteria for daily
cover material:
(1)
to control and not sustain fires;
(2)
to control and not contribute to odors (this may require the separation of
plaster and wall-board from daily cover material);
(3)
to control and not contribute to the propagation of vectors;
(4)
to control and not contribute to blowing litter and dust;
(5)
the screenings pass through a two inch screen;
(6)
the amount of fines (material passing through a number 200 sieve) in the
screenings is less than 25 percent by weight (dry basis);
(7)
screenings may be mixed with other suitable materials, to meet the
requirements set forth above.
(8)
analytical testing for all screenings proposed for use as a daily cover
shall include, at a minimum, appropriate toxicity Characteristic
Leaching Procedure (TCLP) parameters as set forth in Part 261 of Title
40 of the Code of Federal Regulations (40 CFR 261) as is or as amended
at a frequency approved in the operating plan.
(b) Screenings separated from construction and demolition debris may also be
reused for other specific uses if prior written approval is received from the
Department. Such beneficial uses shall be evaluated on a case by case basis
and shall be limited to non-agricultural and non-residential applications.
(c) All projects utilizing screenings from construction and demolition debris must
have a sampling and testing plan and schedule approved by the Department.
(d) The sampling and testing plan shall include, but not be limited to, addressing
the following constituents of concern:
(1)
Metals: Arsenic, Cadmium, Chromium, Copper, Lead, Mercury and
Nickel.
(2)
Organic Compounds: PCB's, Endrin, Toxaphene, 2,4,5-T, 2,4,5-TP
(Silvex).
(3)
Asbestos - Must not exceed the requirements of the Rules and
Regulations for Asbestos Control which states: "Regulated Asbestos
Containing Materials: are friable asbestos materials containing more
than 1% asbestos, including non-friable asbestos that may release
asbestos fibers when handled or demolished.".
10
(e) No screenings shall be utilized within 200 feet of any body of surface water or
freshwater wetland or within 500 feet of any body of surface water or
freshwater wetland within the watershed of a public drinking water supply
without specific approval of the Department.
(f)
No screenings shall be utilized within 200 feet of any private drinking water
supply well or within 500 feet of any public drinking water supply well.
(g) The plan shall also identify testing procedures and protocols, testing
frequency, and maximum contaminant limits based upon the proposed end
uses.
7.3.03
Wood Chips: Reuse, Sampling and Testing Requirements:
(a) Wood chips generated from the pulverizing or chipping of unadulterated
wood or land clearing debris, such as brush, tree limbs and stumps, may be
utilized for the following:
(1)
landscaping mulch
(2)
soil amendment
(3)
sewage sludge amendment for composting
(4)
erosion control material
(5)
fuel
(6)
other uses approved by the Department and described in the facility's
operating plan
(b) Wood chips generated from the pulverizing or chipping of segregated building
wastes and segregated demolition wastes or adulterated or treated wood are
restricted to the following uses:
(1)
fuel
(2)
Department approved erosion control projects at approved landfills
(3)
other projects with Department approval
(c) All projects utilizing wood chips, except for fuel usage, must have a sampling
and testing plan and schedule approved by the Department.
(d) The sampling and testing plan shall include, but not be limited to, addressing
the following constituents of concern:
(1)
Asbestos - Must not exceed the requirements of the Rules and
Regulations for Asbestos Control which states: "Regulated Asbestos
Containing Materials: are friable asbestos materials containing more
11
than 1% asbestos, including non-friable asbestos that may release
asbestos fibers when handled or demolished."
(2)
Ignitable Petroleum Distillates - Must not meet the definition of a
hazardous waste as defined in the Rules and Regulations for Hazardous
Waste Management.
(3)
Metals: Chromated Copper Arsenate (CCA), Arsenic, Chromium,
Copper, Lead, and Mercury.
(4)
Semi-volatiles: Creosote*, creosol, Pentachlorophenol.
*-
Arsenic, Chromium, and Copper are indicators of Chromated Copper
Arsenate and Creosol, an active ingredient of Creosote, is an indicator of
Creosote.
(e) The plan shall also identify testing procedures and protocols, testing
frequency, and maximum contaminant limits based upon the proposed end
uses.
(f)
Wood chips generated for use as a fuel for boilers and wood-fired power
plants must meet the requirements for those facilities. The facility operating
plan must indicate all wood fuel facilities to be utilized.
7.4.00
APPLICABILITY
(a) All new facilities that process construction and demolition debris must
comply with the provisions of the Rules and Regulations.
(b) Within ninety (90) days from the effective date of these regulations all
existing facilities that process construction and demolition debris that:
(1)
Accept greater than 50 tons/day of construction and demolition debris
must apply for a solid waste management facility license.
(2)
Accept 50 tons/day or less of construction and demolition debris must
submit a completed "License Exemption Form", with all required
information to demonstrate compliance with the Rules and Regulations.
12
Rule 7.00-Appendix "A"
Registration of Processing Facilities that Accept 50 Tons/Day or Less of
Construction and Demolition Debris
License Exemption Form
Pursuant to Rule 7.1.01(b) processing facilities that accept only 50 tons/day or less of
construction and demolition debris, as construction and demolition debris is defined by these
Rules and Regulations, are exempt from the requirement of obtaining a solid waste management
facility license, however, they are not exempt from complying with all other applicable
requirements, which shall include submission of all applicable required information for approval,
for the construction and operation of a construction and demolition debris processing facility,
and are subject to the Rules and Regulations for such facilities.
Facility Name:
Owner's Name(s):
Operator Name(s):
(if different/title)
Facility Address:
(street, city, zip code)
Assessor's Plat/Lot Number:
Mailing Address:
(if different)
(street, city, zip code)
Owner/Operator
Date
Owner/Operator
Date
An operating plan, per Rule 7.1.05, must accompany this form, to address compliance with Rules
7.2.00 (Operating Standards) and 7.3.00 (Reuse, Sampling and Testing Requirements). In
addition, all facilities are required to establish a closure fund or closure bond with the
Department as per Rule 7.2.08.
13
The foregoing "Solid Waste Regulation No. 7- Facilities that Process Construction and Demolition
Debris" of the “Rules and Regulations for Composting Facilities and Solid Waste Management
Facilities, January 1997 and as amended April 2001", after due notice, are hereby adopted as
amended and filed with the Secretary of State this day of , to become effective
twenty (20) days thereafter, in accordance with the provisions of Chapters 2-1, 2-22, 2-23, 5-51, 23-
18.8, 23-18.9, 23-19, 23-19.1, 23-23, 23-63, 37-15.1, 42-17.1, 42-17.6, 42-35, 44-27, and 46-12 of
the General Laws of Rhode Island of 1956, as amended.
_____________________
______________________________
Date
Jan H. Reitsma, Director
Department of Environmental Management
Public Notice on:
Public Workshops on:
Filing Date:
Effective Date: