250-RICR-150-10-4
250-RICR-150-10-4. Rules and Regulations for the Operation and Maintenance of Wastewater Treatment Facilities (version Technical Revision, 05/19/2008 to 05/19/2008)
250-RICR-150-10-4
TITLE 250 – DEPARTMENT OF ENVIRONMENTAL MANAGEMENT
CHAPTER 150 – WATER RESOURCES
SUBCHAPTER 10 - WASTEWATER & STORMWATER
PART 4 – Rules and Regulations for the Operation and Maintenance of Wastewater
Treatment Facilities
4.1
Purpose
It is the purpose of these Rules and Regulations to ensure that Wastewater Treatment
Facilities are at all times maintained in acceptable working order and operated at their
maximum level of efficiency to adequately transport and/or remove the maximum
amount of objectionable constituents in wastewater, and to serve the purposes of the
Federal Clean Water Act and applicable R.I. Gen. Laws. To achieve this purpose these
Rules and Regulations provide the provisions for Owners of a Wastewater Treatment
Facility to submit for approval and, once approved, adhere to an Operation and
Maintenance Plan. Accordingly these Rules and Regulations establish a procedure for
the evaluation and approval of Operation and Maintenance Plans by the Department of
Environmental Management.
4.2
Authority
These Rules and Regulations are adopted pursuant to R.I. Gen. Laws Chapters 46-12,
42-17.1, 42-17.6 and 42-35.
4.3
Application
The terms and provisions of these Rules and Regulations shall be liberally construed to
permit the Department to effectuate the purposes of state law, goals and policies.
4.4
Definitions
For the purposes of these Rules and Regulations only, the subsequent terms shall have
the following meanings:
A.
“Combined sewer overflow" means a structure within a combined sewage
collection system that allows a discharge during a wet-weather event into a
receiving water without going to a treatment works.
B.
“Department” means the Rhode Island Department of Environmental
Management.
C.
“Director” means the Director of the Department of Environmental Management
or his/her designee(s).
D.
“NPDES” means the National Pollution Discharge Elimination System, which may
include the delegated Rhode Island Pollution Discharge Elimination System.
E.
“Operation and maintenance plan” or “Plan” means either an electronic or paper
document submitted to the Director for evaluation and written approval. Each
document shall include, but not be limited to, a description of the specific
Wastewater Treatment Facility, procedures for operation and maintenance,
required staffing levels, design and other pertinent information as enumerated in
§ 4.5 of this Part.
F.
“Owner” means
1.
The permittee named on the NPDES permit issued for the Wastewater
Treatment Facility, or,
2.
A city or town or the State of Rhode Island, or district association, or other
public body (created by or pursuant to Rhode Island State Law) having
jurisdiction over a Wastewater Treatment Facility.
G.
“Sanitary sewer overflow” means an intentional or unintentional discharge of raw
or partially treated Wastewater from any point within a Wastewater Treatment
Facility’s collection system. For the purposes of these regulations a Sanitary
Sewer Overflow will not include a wet-weather-related discharge from any
Combined Sewer Overflow authorized within a NPDES permit.
H.
“Wastewater” means human waste from any receptacles intended to receive or
retain bodily waste products, and any organic or non-biological wastes from
residences, businesses, institutions and industries or any combination of the
above, as well as any water used as a means of conveyance of such wastes,
which is intended to enter a Wastewater Treatment Facility for collection,
conveyance, treatment and discharge in accordance with a NPDES permit.
I.
“Wastewater treatment facility” means a group or assemblage of processes,
devices and structures for the conveyance, treatment or removal of objectionable
constituents of Wastewater. A Wastewater Treatment Facility shall include, but
not be limited to, all physically connected Wastewater collection system piping,
pumping, storage, physical, chemical and/or biological treatment, filtering and
disinfection systems. For the purposes of these Rules and Regulations, a
Wastewater Treatment Facility shall include privately owned wastewater
collection, pumping, storage and conveyance systems interconnected with and
emptying into a host Wastewater collection system. For the purposes of these
Rules and Regulations, a Wastewater Treatment Facility shall not be considered
to be:
1.
An Onsite Wastewater Treatment System, which does not discharge into
surface waters but discharge into subsurface waters; or,
2.
Any privately owned plumbing; or,
3.
Any privately owned low-pressure grinder pumps; or,
4.
Gravity sewer lines conveying an average flow of less than 30,000 gallons
per day, as calculated by the Department’s “Flow Estimation Policy for
Design of Sanitary Sewers.”
4.5
Operation and Maintenance Plan Requirements
A.
At all times, Wastewater Treatment Facilities shall be maintained in good working
order and operated as efficiently as possible. Proper operation and maintenance
may include but not be limited to effective performance based on facility design,
adequate funding, effective management, adequate operator staffing and training
and adequate laboratory and process controls including quality assurance
procedures as determined to be appropriate by the Director and backup or
auxiliary facilities or similar systems to assure compliance or effective
performance. Proper operation and maintenance must include emergency
procedures and reporting requirements in case of power outages, natural
disaster, labor shortage (whether the result of intentional work stoppages or
epidemic) equipment failure, acts of terrorism/vandalism or Sanitary Sewer
Overflow. Reporting requirements shall include verbal notification to the
Department and, if applicable, the Owner of the host Wastewater Treatment
Facility as soon as possible, but not exceeding twenty-four (24) hours of
discovery of the event; a written report must be submitted to the Department not
more than five (5) business days of the event’s ending.
B.
The Owner shall submit for review and approval by the Director an Operation and
Maintenance Plan prescribing standards and procedures by which the
Wastewater Treatment Facility will be staffed, operated and maintained during
normal and emergency conditions. Should development of the Plan include the
practice of engineering, the Plan must then be prepared and certified by a
Registered Professional Engineer registered in the State of Rhode Island.
C.
The Owner of a new Wastewater Treatment Facility, or the owner of an existing
Wastewater Treatment Facility that is being upgraded shall submit a draft
Operations and Maintenance Plan, or draft revisions to an existing approved
Plan, to the Director for review and approval at least sixty (60) days prior to
commencement of operation of the new or upgraded Wastewater Treatment
Facility.
D.
The Owner of an existing Wastewater Treatment Facility without an approved
Plan must submit for approval a Plan necessary to comply with the requirements
herein within one (1) calendar year of the promulgation of these Rules and
Regulations, or at some other pre-approved time as determined at the discretion
of the Director.
E.
The Owner of an existing Wastewater Treatment Facility with an approved Plan
must submit for approval all revisions necessary to comply with the requirements
herein within one (1) calendar year of the promulgation of these Rules and
Regulations, or at some other pre-approved time as determined at the discretion
of the Director.
F.
The Owner may request an extension in time to complete and submit the
required revisions or submission of a Plan, per §§ 4.5(D) and 4.5(E) of this Part,
but this extension cannot exceed one year in addition to the one year herein.
1.
A request for submission extension must be in writing and be received by
the Department no later than three (3) months prior to the required
submittal date. Any request received later than three months prior to the
required submittal date will be denied.
2.
The request for extension must include all applicable reasons that would
require additional time for the submission of a draft plan.
3.
It shall be at the Director’s discretion to approve or deny such a request
for extensions of submission.
G.
The Owner of any existing Wastewater Treatment Facility operating on the
effective date of these Rules and Regulations shall continue to operate the
Wastewater Treatment Facility in compliance with an existing approved Plan,
which shall remain in full force and effect unless suspended or revoked by the
Director in accordance with § 4.13 of this Part.
H.
The contents of the Plan shall include at a minimum the following:
1.
Descriptions and schematics of the entire Wastewater Treatment Facility
in either paper or electronic form, and an overall plan with appropriate
labels for major components (i.e. collection piping and pumping,
headworks, clarifiers, aeration tanks, disinfection, sludge handling, etc.),
outfall(s) and compliance sampling locations. This description and
schematic must include:
a.
Sewer-line maps of the collection system, which will include but not
be limited to the overall service area, as well as the locations of
incoming wastewater from neighboring communities, pipe diameter,
distances between centers of manholes, slope or direction of flow,
and the locations of all pump stations, siphons, etc., (noting design
capacities) and flow meters. Other required collection system
information may include, but not be limited to, the dimensions of
easements and property lines. The information stated herein (that
is, in § 4.5(H)(1)(a) of this Part will not be submitted to the
Department for review, but shall be available for review by the
Director at any time during the approval process.
b.
A summary of all design criteria, including capacity calculations, for
the Wastewater Treatment Facility.
2.
Descriptions of, and detailed operating procedures for, all treatment
processes and major and essential equipment, including sampling and
monitoring equipment.
3.
A preventative maintenance plan for the Wastewater Treatment Facility.
This must include information stored within an adequate data-
management system.
4.
A listing of supplies and essential spare parts necessary to be kept on site
for normal and emergency use throughout the Wastewater Treatment
Facility.
5.
A staffing plan, including but not limited to position descriptions,
managerial and staffing hierarchy organization chart, minimum
qualifications and training, whether the position is full- or part-time, and
required Grade of Licensure, as stated by any Rules and Regulations
promulgated by the Rhode Island Board of Certification of Operators of
Wastewater Treatment Facilities.
6.
A description of any provisions to ensure security of the Wastewater
Treatment Facility’s physical and electronic data-management systems.
7.
Emergency procedures and reporting requirements in case of power
outages, natural disaster, labor shortage (whether the result of intentional
work stoppages or epidemic) equipment failure, acts of
terrorism/vandalism or Sanitary Sewer Overflow. Reporting requirements
shall include verbal notification to the Department as soon as possible but
not exceeding twenty-four (24) hours of discovery of the event; a written
report must be submitted not more than five (5) business days of the
event’s ending.
8.
Procedures for records keeping for up to three years of the time of
recording.
9.
Seasonal operational requirements, where applicable.
10.
A schedule for self-monitoring of influent and effluent, treatment processes
and operations to be reported on forms (paper or electronic) required by
the Director.
11.
A copy of the Wastewater Treatment Facility’s National Pollution
Discharge Elimination System (NPDES) or Rhode Island Pollution
Discharge Elimination System (RIPDES) discharge permit.
12.
Laboratory and sample collection procedures.
13.
A description of operational funding mechanisms, to be updated at any
time said funding mechanism changes.
14.
A copy of the sewer use ordinance.
15.
Procedures for tracking information regarding legally responsible parties of
privately owned Wastewater Treatment Facilities that are physically
connected to, and so empty into, an Owner’s Wastewater Treatment
Facility. Such information must include, at a minimum, the retention of up-
to-date and accurate contact information, including names, addresses and
emergency communication information for all privately owned Wastewater
Treatment Facilities connected to an Owner’s Wastewater Treatment
Facility.
16.
Procedures for informing responsible parties of privately owned
Wastewater Treatment Facilities that are physically connected to, and so
empty into, an Owner’s Wastewater Treatment Facility that, at a minimum,
said parties are under the authority of these regulations.
17.
Procedures for monitoring that privately owned Wastewater Treatment
Facilities that are physically connected to, and so empty into, an Owner’s
Wastewater Treatment Facility, are operated and maintained in
accordance with § 4.5(A) of this Part. These procedures shall include a
plan for action by the Owner should it become known that a privately
owned Wastewater Treatment Facility has failed.
18.
Provisions that the Wastewater Treatment Facility will minimize Sanitary
Sewer Overflows by maintaining and planning for proper collection-system
capacity. This must include a description of methods for Wastewater
Treatment Facility capacity management with details on the selection and
enforcement of any and all legal authority necessary for an Owner to
ensure system capacity by regulating the volume of flow entering the
Wastewater Treatment Facility, including but not limited to residential and
commercial customers, neighboring communities and industrial users.
Such legal authority may include project approval requirements at the
local level, sewer-use ordinances, contracts, service agreements and/or
other legally binding documents.
19.
A schedule for implementation of § 4.5(H)(15-18) of this Part above.
4.6
Procedures for the Evaluation and Approval of a Plan
The Director shall evaluate each Plan submitted giving full consideration to the
Wastewater Treatment Facility design parameters, public health requirements and
sound engineering, administrative and maintenance practices.
A.
In reviewing a Plan, the Director may use as guidance the following documents:
“Guides for an Operation and Maintenance Manual for Municipal Wastewater
Treatment Facilities” and “Guides for an Operation and Maintenance Manual for
Municipal Wastewater Pumping Stations and/or Pipelines,” and/or the “NPDES
Compliance Inspection Manual,” by the U.S. Environmental Protection Agency
(EPA); a current edition of “Operation of Municipal Wastewater Treatment Plants”
by the Water Environment Federation; “Standard Methods for the Examination of
Water and Wastewater”; and other standards, guidance and policies accepted by
the Director.
B.
Upon review of the Plan, the Director may:
1.
Require that the Owner provide information as the Director deems
necessary for the review of the Plan; if additional information is required
the Owner must submit said information within thirty (30) days of
notification, unless a longer time is granted, or,
2.
Issue an Order of Approval. This Order of Approval, however, may if
needed include stipulations requiring any such terms, conditions,
management practices and operation and maintenance requirements
deemed necessary by the Director for the Plan to comply with the
requirements of these Rules and Regulations and applicable state and
federal laws, or,
3.
Deny the Plan for failure to satisfy the requirements of these Rules and
Regulations and applicable state or federal laws. Should such a denial be
issued by the Director, the Owner shall have the right to appeal the denial
in accordance with § 4.14 of this Part.
C.
Upon approval of the Plan, the Department will issue an Order of Approval and
forward to the owner one copy of the approved Plan along with the Order of
Approval. This approved copy must at all times be kept on site at the Wastewater
Treatment Facility and must be available for use by facility operators. A second
identical approved copy will remain on file with the Department.
D.
The Order of Approval issued for a Plan shall be effective on the date that the
approval is issued and shall remain in effect unless modified, suspended or
revoked in accordance with § 4.12 of this Part.
4.7
Operation in Accordance with Approved Plan
A.
After the effective date of the approved Plan, the Wastewater Treatment Facility
shall be operated and maintained at all times in conformance with § 4.5 of this
Part and all aspects of the Plan.
B.
After the effective date of the approved Plan, failure to operate and maintain the
Wastewater Treatment Facility in accordance with the approved Plan shall
constitute a violation of an order of the Director pursuant to R.I. Gen. Laws § 46-
12-3 of the Water Pollution Act. Each day that a Wastewater Treatment Facility is
not operated in conformance with an approved Plan shall constitute a separate
violation.
4.8
Staffing
All Wastewater Treatment Facilities regulated by the Rhode Island Board of Certification
of Operators of Wastewater Treatment Facilities must be operated and maintained by
properly certified personnel in accordance with the Rules and Regulations for
Wastewater Treatment Facility Operators.
4.9
Odors
All Wastewater Treatment Facilities must comply with the Department’s Air Pollution
Control Regulation 17, or other Rules and Regulations pertaining to odors. As such, a
Wastewater Treatment Facility shall, at all times, be operated and maintained so as not
to emit or cause to be emitted into the atmosphere any air contaminant or combination
of contaminants which creates an objectionable odor beyond the property line of said
facility.
4.10 Records of Operation
The Director may require any Wastewater Treatment Facility to:
A.
Establish and maintain records of operation and maintenance.
B.
Create and submit reports, including but not limited to monthly operating reports,
alarm calibration and testing reports, etc.
C.
Install, calibrate, use and maintain monitoring equipment or methods.
D.
Sample discharges in accordance with such methods at locations, at intervals,
and in a manner as the Director shall prescribe. Such sampling may be in
addition to that required by NPDES monitoring requirements.
E.
Provide other information relating to discharges into the state waters or into a
Wastewater Treatment Facility as the Director may reasonably require.
4.11 Inspection; Right of Entry
A.
For the purpose of enforcing these Rules and Regulations, it is necessary that
the Director be able to conduct inspections of, review records of operation and
obtain samples of any substance from a Wastewater Treatment Facility, and to
evaluate a proposed Plan and/or ensure that operation and maintenance is in
conformance with an approved Plan, as well as state and federal laws related to
wastewater treatment. Therefore in accordance with the Department of
Environmental Management’s Administrative Inspection Guidelines, the Director
may at all reasonable times enter any Wastewater Treatment Facility premises,
buildings, plants or equipment, or other places belonging to, or controlled by any
Owner, inspect the same or any part thereof, review and copy records of
operation, either physical or electronic, historical or real-time, and obtain samples
of any substances which the Director deems necessary.
B.
Any person obstructing, hindering, or in any way causing to be obstructed or
hindered, the Director in the performance of his/her duties or who shall refuse to
permit the Director entrance into any Wastewater Treatment Facility premises,
buildings, plant or equipment, or other places belonging to or controlled by any
such person, or who shall refuse to permit the Director to review and copy
records of operations or obtain samples of any substances, in the performance of
his/her duties as such, shall be subject to the civil and criminal penalties set forth
in R.I. Gen. Laws §§ 46-12-13 and 46-12-14.
4.12 Revision of an Approved Plan
A.
An approved Plan shall not be revised in any manner without the prior
submission of the proposed revision to the Director for review and approval. The
Director may also require at any time that an approved Plan be revised for
reasons which include, but are not limited to, a determination that there has been
a substantial change or alteration in the Wastewater Treatment Facility’s
capacity, treatment process, equipment or effluent or influent wastewater
characteristics.
B.
Revisions to an approved Plan will generally be approved by issuing a “modified
Order of Approval.” Minor revisions may be approved by the Director as Standard
Operating Procedures. Once the Director approves a Standard Operating
Procedure it shall be considered an addendum of the approved Plan, and as
such must be adhered to in accordance with § 4.5 of this Part.
4.13 Enforcement
A.
Any Owner that operates a Wastewater Treatment Facility without an approved
Plan, or a person or entity operating a Wastewater Treatment Facility in violation
of an approved Plan or otherwise operates a Wastewater Treatment Facility in
violation of these Rules and Regulations shall be subject to administrative
enforcement actions, and/or civil and/or criminal penalties pursuant to R.I. Gen.
Laws Chapters 46-12, 46-17.1 and 42-17.6.
B.
Operation of a Wastewater Treatment Facility without an approved Plan or
operation in violation of an approved Plan may constitute grounds for the Director
to suspend or revoke state grants for pollution prevention facilities.
C.
The Director may seek appropriate equitable remedies pursuant to R.I. Gen.
Laws Chapter 46-12, as amended for the operation of a Wastewater Treatment
Facility without an approved Plan or operation of a Wastewater Treatment
Facility in violation of an approved Plan.
D.
After adoption of a Plan, the plan shall be enforced through R.I. Gen. Laws § 46-
12-10.
4.14 Appeals
Any person or entity for which an enforcement action has been initiated against by DEM
may appeal to the Director for review of the decision on which the enforcement action is
based by filing an appeal with the Administrative Adjudication Division. The procedures
for appeal of Department decisions pursuant to the provisions of R.I. Gen. Laws
Chapter 42-35 are contained in the Administrative Rules of Practice and Procedure for
the Administrative Adjudication Division for Environmental Matters (“AAD Regulations”).
4.15 Severability
If any provision of the Rules and Regulations or the application thereof to any person or
circumstance is held invalid by a court of competent jurisdiction, the remainder of the
Rules and Regulations shall not be affected thereby.
4.16 Superseded Rules and Regulations
Upon adoption, these Rules and Regulations will supersede the “Rules and Regulations
Pertaining to the Operation and Maintenance of Wastewater Treatment Facilities” dated
December 12, 1979 and as amended December 31, 2001.