490-RICR-00-00-2
490-RICR-00-00-2. Rules and Procedures for Water Supply Systems Management Planning (version Periodic Refile, 12/18/2001 to 01/02/2003)
STATE OF RHODE ISLAND
AND PROVIDENCE PLANTATIONS
RI WATER RESOURCES BOARD
Rules and Procedures for
WATER SUPPLY SYSTEM MANAGEMENT PLANNING
OCTOBER 1998
AUTHORITY: These regulations are adopted in accordance with Chapter 42-35 pursuant to
Chapter 46-15.3 of the Rhode Island General Laws (1997).
1
TABLE OF CONTENTS
SECTION 1.00 PURPOSE AND GOALS
3
SECTION 2.00 LEGISLATIVE AUTHORITY
3
SECTION 3.00 LIBERALAPPLICATION
4
SECTION 4.00 SEVERABILITY
4
SECTION 5.00 CONFORMITY WITH OTHER LEGISLATION
4
SECTION 6.00 DEFINITIONS
4
SECTION 7.00 APPLICABILITY - PREPARATION OF PLANS
9
SECTION 8.00 PLAN CONTENTS
9
8.01
Goals Statement
10
8.02 Water Supply System Description
10
8.03 Requirements of the Water Quality Protection Component
13
8.04 Supply Management
15
8.04(1) Anticipated Future Demands
15
8.04(2) Available Water
16
8.04(3) Alternative Supply
20
8.04(4) Supply Augmentation Studies
20
8.05 Demand Management
21
8.06 System Management
23
8.07 Emergency Management
25
8.08 Implementation Schedule, Responsible Entities and Projected Costs
27
8.09 Financial Management
27
8.10 Coordination
29
8.12 Rhode Island Geographic Information System Compatibility
29
SECTION 9.00 DATA COLLECTION REQUIREMENTS
30
9.01 Reporting Requirements
30
SECTION 10.00 PLAN SUBMITTAL
31
10.01 Time Schedule for Plan Submittal
31
10.02 Plan Amendments
31
10.03 Filing of Plans
32
10.04 Requests For Time Extensions
32
SECTION 11.00 REVIEW OF PLANS
33
2
11.01 Review Process
33
11.02 Public Comment
33
SECTION 12.00 DETERMINATION OF PLAN COMPLIANCE
34
12.01 Determination of Compliance
34
12.02 Determination of Non-Compliance
34
12.03 First Notice of Deficiencies
35
SECTION 13.00 EVALUATION OF PLAN IMPLEMENTATION
35
13.01 General Policy
35
SECTION 14.00 APPEAL PROCEDURE
36
14.01 Filing of Appeal
36
14.02 Contents of Appeal
36
14.03 Conduct of Hearing
36
14.04 Burden of Proof and Standard for Review
36
SECTION 15.00 ENFORCEMENT
36
3
SECTION 1.00 PURPOSE AND GOALS
1.01
The purpose of these regulations is to implement the provisions of Chapter 46 - 15.3 of
Rhode Island General Laws (RIGL), as amended, to ensure: (1) Water Supply Systems
Management Plans (WSSMP), including emergency management and contingency plans, are
prepared, maintained, and carried out by each entity engaged in or authorized to engage in the
supply, treatment, transmission or distribution of drinking water; (2) that the WSSMPs are
consistent with policy set forth in State Guide Plan Elements; (3) that the plans and their execution
achieve effective conservation, development, utilization, and protection of this finite natural
resource in ways that meet the present and future needs of the state and its people; (4) that Water
Quality Protection Plans (WQPP) are incorporated as components of WSSMPs; (5) that the WQPP
component includes strategies for well-head and watershed protection required by statute and for
drinking water quality improvements; (6) that policies and procedures for collecting and
administrating the Water Quality Protection Fund are implemented consistent with the intent of
applicable Rhode Island General Laws, bonding agreements, and public interest.
1.02
The Board recognizes that compliance with these requirements may occur over time and
that preparation of the plans called for by these rules initiates a process whereby the objectives of
RIGL Chapter 46-15.3 are met. The Board expects water suppliers to comply with these rules as
expeditiously as possible. Where applicable, plans shall include schedules for the completion of
work required by these rules.
1.03
In accordance with policy, planning efforts shall ensure that existing sources of supply be
maintained as long as their use or reactivation is feasible. Feasibility includes, but is not limited
to, consideration of the quality of the source, the safe yield, the costs of operating and maintaining
the source, and other statutory and nonfinancial constraints.
1.04
The principal goals of these rules are to produce a management plan for each water supply
system that will: (1) meet all statutory requirements; (2) carry out applicable policies and
recommendations of the State Guide Plan: (3) assist water suppliers in the development, operation,
and maintenance of their systems; (4) gain and maintain the eligibility of water suppliers to obtain
financial assistance available for protection of water quality or for any other purpose related to
management of water supply systems; and (5) give local governments, state agencies, and the
public information needed to assess the current and future needs of water supply systems in
relation to community and state development so that they can assist water suppliers in meeting
these needs.
SECTION 2.00 LEGISLATIVE AUTHORITY
These rules and procedures are promulgated pursuant to the requirements and provisions of RIGL
Chapter 46-15.3, Water Supply System Management Planning Act, as amended.
SECTION 3.00 LIBERAL APPLICATION
The terms and provisions of these rules and procedures shall be liberally construed to allow the
4
Board to effectuate the purposes of state law, goals and policies consistent with the Water Supply
System Management Planning Act, RIGL Chapter 46-15.3 as amended.
SECTION 4.00 SEVERABILITY
If any provision of these rules and procedures or the application thereof to any person or
circumstances is held invalid by a court of competent jurisdiction, the remainder of the rules and
procedures shall not be affected thereby. The invalidity of any section or sections or of parts of
any section or sections shall not affect the validity of the remainder of these rules and procedures.
SECTION 5.00 CONFORMITY WITH OTHER LEGISLATION
The water supply systems management plans shall conform to all applicable provisions of state
and federal laws including the federal Safe Drinking Water Act (42 USC 300f et seq.); RIGL
Chapter 46-13, Public Drinking Water Supply; and Chapter 46-14, Contamination of Drinking
Water, as administered by the RI Department of Health.
SECTION 6.00 DEFINITIONS
For the purposes of these regulations, the following terms shall have the following meanings:
1) Abandoned water supply sources shall mean the sources that are no longer used or maintained,
such as permanently disconnected surface waters or wells.
2) Act shall mean the Water Supply Systems Management Act.
3) Active water supply sources shall mean RI Department of Health-approved sources of supply
connected to a water supply system and available for distribution; these sources may be surface
waters or wells, residential or other uses.
4) Aquifer shall mean a geological formation, groups of formations, or part of a formation capable
of yielding a significant amount of groundwater to wells, springs, or surface water.
5) Available water shall mean the maximum amount of water that can dependably be supplied,
taking into account limitations imposed by hydraulic or other considerations. In determining the
available water, estimates of the safe yield of surface reservoirs and/or well capacity of
groundwater sources shall be utilized as appropriate. Water committed by another water supplier
through interconnections may be included in the determination of available water. Once accounted
for in a water system's calculation of available water, the same volume of water may not be
accounted for in another supplier's calculation of available water. Temporarily inactive,
abandoned, and emergency water supply sources shall not be included unless approved by the
Board. System storage shall not be included in the calculation of available water.
6) Board shall mean the Rhode Island Water Resources Board as established by Title 46, RIGL
5
Chapters 15 and 15.1.
7) Commercial agriculture producers shall mean producers with gross income from sale of
agricultural commodities of $2500.00 or more during a calendar year.
8) Commission shall mean Public Utilities Commission.
9) Comprehensive Plans shall mean local comprehensive plans as required by RIGL Chapter 45-
22.2.
10) Conservation shall mean methods, procedures, and devices designed to promote efficient use
of water and to eliminate waste of water.
11) Consumption shall mean all water delivered by water suppliers for its intended use for
industrial, commercial, agricultural, residential or other uses.
12) Demand, average daily shall mean the total volume of water supplied to the system including
changes in storage over the representative period divided by the number of days in that
representative period. The most recent representative period of record shall be utilized and shall
not be affected by unusual demand conditions such as drought or a significant temporary increase
in demand.
13) Demand management shall mean any conscious effort to modify water use for efficient
utilization of available supply.
14) Demand, maximum daily shall mean the maximum one day rate of water supplied to the
system including changes in storage experienced over the most recent year not affected by unusual
demand conditions, such as drought or a significant temporary increase in demand.
15) Demand, peak hourly shall mean the maximum one-hour rate of water supplied to the system
including changes in storage experienced over the most recent year.
16) Distribution facilities shall mean the pipes and appurtenant facilities employed specifically to
deliver, to dispense, to render or to circulate potable water directly to the consumer.
17) Drought shall mean a condition of dryness due to lower than normal precipitation. For water
supply purposes drought is associated with safe yield especially for conditions where a system
cannot be replenished and failure is anticipated.
8) Eligible expenditure shall mean the acquisition of a fee simple interest or of a conservation
restriction, as that term is defined in RIGL Title 34, Chapter 39-Paragraph 2 (a) or other interest in
watershed lands including, but not limited to, costs and expenses relating to the improvement of
such lands or interests therein, maintenance of the lands or roads or interests therein, and taxes
thereon, and the costs of preparation of Water Quality Protection Plan (WQPP) components and
updates, and related property surveys and appraisals, or the funding of the construction of physical
improvements that directly protect water supply. Watershed lands eligible for protection may be
located in or out of state. No funds shall be used to extend service lines or expand system
6
capacity.
19) Emergency water supply sources shall mean not regular sources of supply but supplies held
in reserve for use in emergencies. The use of emergency water supply sources must be approved
by the RI Department of Health; these may be surface waters or wells.
20) Fund shall mean the Water Quality Protection Fund according to RIGL 46-15.3-5 and 46-15.3-
9.
21) Groundwater recharge shall mean the process of addition of water to the zone of saturation,
that is, the zone beneath the water table.
22) Institutional water supplier shall mean any public water system as defined in the rules and
regulations pertaining to public drinking water under RIGL 46-13, which does not sell water but
supplies more than 50 million gallons per year of drinking water and is governmental or quasi-
governmental in nature.
23) Major user shall mean any public or private organization or entity using more than 3 million
gallons of water per year (a water system may use a lower threshold).
24) Master meter shall mean a meter that measures water from a source of supply or from other
water suppliers.
25) Metered supply shall mean the quantity of water measured at the points of entry into the
transmission and distribution system.
26) Non-account water shall mean the difference between the metered supply and the metered
consumption for a specific period including an allowance for fire fighting.
27) Raw water shall mean water in its natural state prior to any treatment.
28) Recharge area shall mean the land surface from which water is added to the zone of
saturation. The recharge area for a particular well or aquifer, for instance, is that land surface from
which water moves to the well or aquifer or may move to the well or aquifer under certain
hydraulic conditions.
29) Safe Drinking Water Act (SDWA) shall mean the federal legislation of 1974, amended in
1986, and reauthorized in 1996, to establish standards for drinking water safety.
30) Safe yield (surface water) shall mean a sustainable withdrawal that can be continuously
supplied from a surface water supply source without adverse effects throughout a critical dry
period with a 1% chance of occurrence, or one that is equivalent to the drought of record,
whichever is more severe.
31) Safe yield (aquifer or well) shall mean the rate at which groundwater can be withdrawn
without producing unacceptable or undesirable effects such as drawdowns or changes in water
quality.
7
32) Saturated thickness shall mean the thickness of an aquifer measured from the water table to
an essentially impermeable boundary; such boundary is typically taken to be the top of the bedrock
surface.
33) Service area shall mean the geographic boundary within which service connections to
customers of a water supply system are committed by charter of the water commission, board, or
authority.
34) Source shall mean the raw water upon which a public water supply system depends, and
refers to both groundwater and surface water.
35) Specific capacity shall mean the discharge of a well per unit of drawdown.
36) Susceptibility determination shall mean an analysis of the potential for a water supplier to
draw water contaminated by inventoried sources at concentrations that would pose concern. Such
a determination, therefore, would likely take into account hydrologic and hydrogeologic factors,
inherent characteristics of the contaminants (e.g., toxicity, environmental fate and transport); and
characteristics of the potential source of the contaminant (location, likelihood of release,
effectiveness of mitigation measures). In small source water protection areas, where differences in
distances between sources and intake are small, and hydrologic and hydrogeologic factors are
relatively constant, susceptibility of a water supply is related to the likelihood of a significant
release and the inherent characteristics of the source (e.g., toxicity, fate and transport, etc.).
37) Total reservoir storage capacity shall mean the reservoir volume at the normal full pool
level or spillway elevation.
38) Transmission facilities shall mean the pipes, pumping stations, and storage facilities required
to carry high volumes of potable water from a water source to distribution facilities, or throughout
an area for the purpose of supplying water to the general population, or wholesale customs.
39) Transmissivity shall mean a measure of the ability of an aquifer to transmit a fluid. It can be
quantified as the hydraulic conductivity multiplied by the saturated thickness.
40) Useable reservoir storage capacity shall mean the difference between the total reservoir
storage capacity and the volume at the minimum reservoir storage level as determined by the intake
pipe elevation or the water elevation below which water cannot be treated to meet water quality
standards.
41) User category shall mean metered single-family residential, multi-residential, commercial,
industrial, or wholesale purchaser (for example, another water supplier), metered water system
usage, water used for fire fighting purposes and non-account water
Multi-residential shall include apartments, condominiums, nursing homes, college dormitories,
correctional facilities and any other commercial or institutional entity, which provides non-
transitory housing and are not metered separately.
8
Commercial shall include non-governmental institutions and entities identified by the following
Standard Industrial Classification (SIC) two-digit major group codes:
Agriculture, etc. - Major Groups 01 - 09
Construction - Major Group 15 - 17
Transportation, communications, electric, gas, etc - Major Groups 40 - 48
Wholesale Trade - Major Groups 50, 51
Retail Trade - Major Group 52 - 59
Finance, Insurance, etc. - Major Groups 60 - 67
Services - Major Groups 70 - 89
Industrial shall include entities identified by the following SIC two-digit major group codes:
Mining - Major Group 14
Manufacturing - Major Groups 20, 22 - 39
Transportation, communication, electric, gas, etc. - Major Group 49
Metered governmental shall include an estimate of water used for fire fighting purposes
and
those entities identified by the following SIC two-digit major group codes:
Public Administration - Major Groups 91 - 97
Non-account water may include unmetered water usage, leaks, theft, etc.
42) Watershed shall mean those land areas, which because of their topography, subsurface
characteristics, and drainage patterns, act as collectors of raw water, which replenish or recharge
surface and ground water supply sources.
43) Water supplier shall mean any municipality, municipal department, agency, district, authority,
or other entity engaged in or authorized to engage in the supply, treatment, transmission or
distribution of drinking water on a wholesale or retail sales basis.
44) Water supply emergency shall include, but not be limited to, one or a combination of the
following situations:
(1) Mechanical failure or similar type of emergency including loss of power, loss of
pumping capacity, loss of storage capability or major breaks or leaks which result in an inability
to meet average daily or maximum daily demand for water.
(2) Water quality emergencies due to contamination of the water supply, the distribution
system or storage tanks which result in an inability to meet average daily and maximum daily
demand with remaining public water supplies.
(3) Seasonal water shortages or inadequacy of source, distribution system or storage
capacity to meet water supply needs.
45) Water supply sources temporarily inactive are seasonal sources of supply or sources
temporarily not in use due to mechanical or quality problems or lack of demand. These sources
may be surface waters or wells and, depending upon the reason for the "temporarily inactive"
status, have RI Department of Health approval or must be approved by the RI Department of
Health prior to use.
46) Water system shall mean any combination of interconnected sources and facilities used for
9
supplying potable water. Water systems are owned and operated by water suppliers.
47) Wellhead Protection Area (WPA) shall mean the surface and subsurface area surrounding a
public drinking water well through which contaminants are reasonably likely to move toward and
reach the wellhead. Commonly called "well field" or "recharge area".
SECTION 7.00 APPLICABILITY - PREPARATION OF PLANS
All water suppliers and institutional water suppliers which obtain, transport, purchase, or sell
more than 50,000,000 gallons of water per year shall be required to prepare, maintain, and carry
out a Water Supply Systems Management Plan (WSSMP) as described by these procedures. A
supplier that bills 50 million gallons or less of public drinking water per calendar year shall be
exempt from the implementation of the Act under the Board's application of "de minimis no carat
lex". In order to continue to qualify for said de minimis exemption the supplier must report
annually in January of each year the total amount of water produced or total amount of water billed
for the preceding calendar year. Any supplier exceeding the 50 million-gallon threshold for the
prior calendar year shall be subject to this Act, these rules, and the imposition of water quality
charges starting March 1st following the calendar year in which billings exceeded the 50 million-
gallon threshold. Once a de minimis supplier becomes subject to imposition of the charge under
these rules, even though such supplier may subsequently fall below the 50 million gallon per year
threshold, said supplier shall continue to be subject to the Act. Institutional water systems, which
exceed the 50 million-gallon threshold, shall be subject to this act. Pumping records on a calendar
year basis shall be utilized as the indicator for this eligibility.
SECTION 8.00 PLAN CONTENTS
Water Supply System Management Plans shall address each of the topics listed in this section, to
the extent that each is relevant to the water supplier, the water source(s), the water system(s), and
the area served or eligible to be served. The plan shall include an Executive Summary highlighting
the elements of the plan.
8.01 Goals Statement
(a) Stated goals shall promote the effective and efficient conservation, development, utilization,
and protection of the states' surface and ground water resources.
(b) Goal statements shall be consistent with the comprehensive plan of the municipality or
municipalities in which the service area is, or is planned to be, located and with State Guide Plan
Element 721, "Water Supply Policies for Rhode Island."
8.02 Water Supply System Description
(a) Organization and Legal Structure: The organization and legal structure of the water supply
system shall be described. The plan shall state the owner of the water supply system; the name of
10
the chief executive officer, director or agency head, and board of directors shall be included. A
chart of the organizational structure showing all aspects of water system management and
operation shall be provided. Major responsibilities for each management position shown on the
organizational chart shall be described. The water supply system’s legal basis shall be described.
(b) System Overview: The description of the water system shall include a system overview, which
generally describes all system components, the functions and relationships of each and any recent
improvements thereto. A schematic drawing of water supply sources and infrastructure
components including all transmission lines, treatment and storage facilities, pump stations, and
system interconnections shall be provided.
(c) Supply Sources: All water supply sources shall be listed and mapped and a description of each
provided. This shall include all surface and groundwater supplies owned or operated by the water
supplier or available through contractual agreements. The operating status of each water supply
source shall be noted as abandoned, active, emergency, or temporarily inactive, as defined herein.
A general discussion of the reason for the temporarily inactive or abandoned status of any water
source shall be provided. The description of abandoned sources shall rely upon existing
information, no additional information or field verification of information shall be required.
(1) Surface Water Sources: The location of each source, of intake structures, of
impoundment and watershed, and water supplier-owned lands shall be mapped at an appropriate
scale for each surface water supply. The description of each surface impoundment shall include
the surface area of the impoundment, size and elevation of intakes, stage storage curve or table,
total and useable storage capacity, and the acreage of the watershed. Also, include any existing or
proposed, minimum downstream discharge rates imposed by a permitting agency or other lawfully
imposed requirement shall be described. For systems with multiple impoundments, the function of
each reservoir shall be noted as distribution or storage with a description of the relation of all
components of the system.
(2) Groundwater Sources: The location of wells, principal aquifers, recharge areas, and
water supplier-owned lands shall be shown for each groundwater source. The description of each
groundwater source shall include the type and location of the well, its depth and diameter; the type
of pump, age, remaining useful life, and its rated capacity and head, screen length and depth of
screen from the surface, slot size, and casing material. The existing monitoring program shall also
be described including sampling locations, the location of monitoring wells, the type of data
collected (include qualitative and/or quantitative parameters measured), and frequency of
monitoring.
(d) Infrastructure Components: All infrastructure components, including treatment and storage
facilities, transmission lines, and pumping stations shall be listed and mapped and a description of
each provided. Pressure zones shall be depicted on the map of infrastructure components.
Transmission facilities shall not include distribution facilities.
(1) Treatment Facilities: The name and location of water treatment facilities, the source(s)
that are treated, and the treatment available shall be described. The design flow and emergency
provisions such as, standby generators, chemical feed equipment and bypasses shall also be
described for each facility. Techniques for disposal of filter back wash and treatment tank sludge
11
including the disposal site or discharge location shall be described.
(2) Storage Facilities: The name, location and total useable volume of each storage facility
(including clearwells) shall be described. The age and condition of the facility and date of last
inspection shall be described. The description of all new storage facilities shall include the
material it is constructed of, the interior paint coating or lining, and whether cathodic protection is
provided. This information should also be included for existing facilities, if available.
(3) Pump Stations: The name, location, capacity, and number of pump stations and related
capacities shall be described. If applicable, a description of any hydropneumatic storage tank(s)
associated with each pumping facility should also be provided. Emergency power provisions that
are available at each facility shall be included.
(4) Transmission Facilities: The description of the transmission system shall include the
type of pipe, length, diameter, age and condition as available through routine operation and
maintenance. The description should also include a leakage and repair history, where available.
Age should be provided as the actual year the pipe was installed, if known , or to the nearest 10-
year increment.
(e) Interconnections: All available interconnections with other water supply systems including
connections for emergency purposes, whether for sale or purchase of water, shall be listed and
mapped and a description of each provided. The operational parameters of the interconnections
shall be explained indicating the quantity and frequency of water delivered. The capacity and
condition of the transmission main and any pumping facilities shall be described. Legal, technical
and financial requirements for interconnection use shall be specified and any source, hydraulic or
contractual limitations to use described. A summary of any contracts for purchase or sale of water
shall be included.
(f) Service Area: The present service area and any planned extensions thereto shall be described
and mapped. The description shall include:
(1) The geographic extent of the defined boundary including the areas served by the water
supply and any areas within the service area not currently served but eligible to be served;
(2) The present and historic number of water services;
(3) The present population served and the population not currently served but eligible to be
served; and
(4) Population distribution patterns, economic status of users and other population
demographics as available from applicable local comprehensive plans and/or the RI Department
of Administration , Statewide Planning Program.
(g) Meters: The extent of source and distribution metering and programs for meter reading, testing,
calibration and repair/replacement shall be described. The description shall include the location,
size, ownership, and age of master meters and meters at system interconnections. The location of
master meters shall be included on the map of treatment and transmission facilities described in
Section 8.02(d). The description shall also include the extent of distribution metering expressed
12
as a percentage of total service connections. Major users and the age of their meters shall also be
provided. Current programs for reading, testing, calibration, repair, and replacement of major
users' meters shall be described. System specific characteristics, which affect the longevity of
meters, should be described.
(h) System Production Data: Current, and as available, historic system production data shall be
provided. If the system has changed substantially over time, for example, an additional well added
or taken out of service permanently, a description of the changes and when they occurred shall be
included. The volume of water withdrawn from each source and for the total system and the
volume of water bought from or sold to another water supplier, expressed in gallons, shall be
reported on at least a monthly and annual basis for the current year and on an annual basis for the
historic data.
(i) Water Use Data: Current and historic water use data shall be provided. If water use has
changed significantly over time, a description of the changes and when they occurred shall be
included. The water use data shall include at least the following:
(1) System-wide and per capita water use expressed as; (i) average daily demand on an
annual and monthly basis, (ii) maximum daily demand; and (iii) other pertinent data, such as peak
hour demand, if available. For historic data, the reporting of data on an annual basis shall be
sufficient. The peaking factor (maximum daily demand divided by average daily demand on an
annual basis) shall also be provided;
(2) Water use analyzed by user category and sub-category (by SIC code) presented as total
water use expressed in millions of gallons per year, and as average daily demand on a monthly and
annual basis;
(3) A list of major users and their water use on an annual basis;
(4) Reasonable estimation and evaluation of water used for firefighting purposes, non-
account water including but not limited to water supply system use, other unmetered public uses,
metering inaccuracies and identified major leaks on an annual basis and as percentage of water
produced;
(5) Water conservation programs currently practiced by the water supplier shall be
outlined and the impact of water saving device installation upon per capita or user category
described; all assumptions and the methodology utilized in estimating impacts shall be provided.
(j) Significant water supply system deficiencies and needed improvements shall be summarized
based upon a review of the information compiled above.
SECTION 8.03 Requirements of the Water Quality Protection Component
(a) If a water quality protection component meeting the criteria of previous applicable rules has
not been completed, every water supplier that sells more than 50 million gallons per year shall
prior to disbursement of bond proceeds to such supplier, complete a water quality protection
13
component which at a minimum includes:
(1) Delineation of Source Water Protection Areas: A determination of the boundaries of
the watersheds of reservoirs serving the supplier or of the aquifers serving the supplier or of the
aquifers serving public wells.
(i) Groundwater Systems: For water suppliers relying on ground water, the
delineation of source water protection areas will be in accordance with accepted methods
under the state's approved Wellhead Protection Program. In cases where a protection area
contiguous to the well or wellfield would alone be inadequate to provide for the protection
and benefit of the public water suppliers need to delineate recharge areas that are not
adjacent to or surrounding the well.
(ii) Surface Water Systems: For water suppliers relying on surface water, the
delineation of the source water protection area must include the entire watershed area
upstream of the intake structure. The delineation of the source water protection area for
these public water supplies would be the topographic boundary. Where water is diverted
into this area from another watershed(s), the watershed area(s) upstream of each diversion
structure would also need to be delineated in a similar manner.
(iii) Groundwater/Surface Water Interface: Water suppliers should consider the
impacts of groundwater on surface water when delineating source water protection areas
for water suppliers based mostly on surface water contribution areas and zones of
groundwater contribution to public surface water supplies. Water suppliers should also
consider the impacts of surface water on public water wells when delineating certain
systems based mostly on ground water. These source water protection areas may include
surface water contribution areas in addition to the zones of groundwater contribution to the
supply.
(2) Inventory of significant potential sources of contaminants of concern in each source
water protection area.
(i) Contaminants of Concern: The contaminants of concern must include those raw
water contaminants regulated under the Safe Drinking Water Act, contaminants with a
maximum contaminant level (MCL), contaminants regulated under the Surface Water
Treatment Rule (SWTR), and the microorganism Cryptosporidium. In addition, inventories
will also include those contaminants that are not federally regulated under the Safe
Drinking Water Act but which the Department of Health has determined may present a
threat to public health.
(ii) Significant Potential Sources: The inventory needs to include a clear
description of the sources of contamination (or categories of sources) by location either
specific or by area. A significant potential source of contamination includes any facility or
activity that stores, uses, or produces, as a product or by-product, the contaminants to the
environment at levels that could contribute significantly to the concentration of these
contaminants in the source waters of the public water supply.
14
(iii) For known or potential sources of contamination that are isolated to a limited
number of locations, identify the names and address of these sources of contamination. For
known or potential sources of contamination that cover large areas and multiple land
owners, identify the geographic area where they are located. Identified sources of
contamination shall be mapped on the water supply source map(s). Water supply source
maps shall also identify current zoning and land use.
If copper sulfate or other algicide is applied to water supply reservoirs, their
tributaries, frequency, and amount of applications shall be described.
3) Determination of Source Water Susceptibility.
(i) A susceptibility determination can be conducted by the water supplier or by the
Rhode Island Department of Health. Plan updates shall require a susceptibility
determination of all new sources of contamination to the water source.
(ii) A susceptibility determination shall describe how the results of the analysis
identify sources of contamination of the public water supply, how significant the threat is,
and the relative threat of contamination between sources within the source water protection
area. The analysis will be the means for the water system to make the inventory useful for
decision-making regarding source water protection.
(4) Description of present and past efforts to protect water quality, both regulatory and
non-regulatory. Included in this description shall be public education initiatives, land acquisitions,
acquisition of buffer zones, diversion and/or treatment of storm water or spills, and desirable land
use control regulations.
(5) Identification of protection strategies determined to be most appropriate for protecting
surface or groundwater quality within the source water protection area(s), which at a minimum
shall include a strategy for public education that fosters water quality protection.
(6) An implementation approach for each protection strategy identified above including,
but not limited to, a discussion of problems that may be encountered and how they will be
resolved. A priority list of actions for implementing measures over a 5 year implementation
schedule which includes a description of ongoing efforts to implement measures.
(7) Efforts to coordinate implementation of recommendations with municipal officials or
boards governing land use activities within the water supply sources, watershed, or recharge area
shall be documented.
(8) An approved Wellhead Protection Plan, as required by the federal Safe Drinking Water
Act and RIDEM's Rules and Regulations for Groundwater Quality which meet the minimum
requirements of these regulations may be referenced.
(9) Those items listed as 2(ii), 2(iii) and 3(ii) are required in the water quality protection
component of the initial water supply system management plan but are optional in any update
15
requirements. However, all plan updates shall require a complete susceptibility determination of
all new sources of contamination to the water source.
8.04 Supply Management
Description of supply management measures necessary to insure present and future availability of
drinking water in adequate quantity and quality to meet existing and projected demands for the 5
and 20 year planning periods shall include but not be limited to the following:
8.04.1 Anticipated Future Demand
Anticipated future demand for the 5-year and 20-year planning periods shall be described,
including but not limited to:
(a) Estimates of changes in population and economic development within existing and planned
future extensions to service areas;
(1) Population changes shall be based upon an analysis of existing and potential land uses
consistent with relevant Comprehensive Community Plans and population projections provided by
the RI Statewide Planning Program. If water supplier's population growth projections differ by
more than 10% from estimates developed by the relevant municipality(ies), the water supplier
shall provide explanation for the differences;
(2) The assessment shall include estimates of future wholesale customers and any system
expansions resulting from the agreed upon merger of water supply systems;
(b) Any legal obligations to provide water including a description of the intended users, the
amounts required and the duration of the contract;
(c) To the extent possible, projected future water use or demand by user category including total
water use expressed as millions of gallons per year, average daily demand on an annual basis,
maximum daily demand, and assessment of the impact of proposed conservation measures on
future demand;
(d) Projected future water use by major users on an annual basis;
(e) Reasonable estimation and evaluation of water used for fire fighting purposes and non-account
water including water supply system use; other unmetered public uses, metering inaccuracies and
major leaks, expressed as millions of gallons per day; and
(f) Consideration should be given to the potential for matching the end uses of water to the quality
necessary for that purpose. Any plan to utilize non-potable water must also describe a cross-
connection control program.
8.04.2 Available Water
16
An analysis of the ability to provide an adequate supply of potable water to existing and projected
customers for the 5-year and 20-year planning periods and as necessary, identification of timing
and quantity of additional supplies and facilities required to meet anticipated needs, shall be
provided as specified below.
(a) General policies:
(1) The safe yield of surface water sources shall be determined using a mass balance
analysis based on a critical dry period with a 1% probability of occurrence or drought of record,
whichever is worse.
(2) Water suppliers who, for operational purposes, utilize a safe yield definition based
upon a critical dry period with a probability of occurrence greater than 1%, must state the reasons
for utilizing such an approach and document proposed or implemented measures to safely manage
the higher level of risk. In no case will a safe yield analysis based upon a critical dry period with
a probability of occurrence greater than 5% be considered acceptable.
(3) Safe yield analyses previously performed that substantially meet the requirements of
this section may be submitted in lieu of the study required herein and shall be reviewed on a case-
by-case basis.
(4) Water suppliers operating under a safe yield based upon a critical dry period with a
probability of occurrence greater than 1% shall undertake demand, supply, system and emergency
management measures to effectively reduce the system’s level of risk.
(5) Water suppliers, whose average daily demand for the most recent year exceeds the
available water, shall immediately initiate demand, supply, and system management measures as
appropriate.
(b) Determination of safe yield for surface water supplies shall be based on the general mass
balance equation such that:
SI - SO = S where;
SI = summation of all different forms of inflow to the reservoir.
SO = summation of all different forms of outflow from the reservoir.
S = net change of storage within the reservoir.
The methodology for determining the safe yield of surface water supplies shall include but
not be limited to the following:
(1) Gauged stream data collected from within the watershed shall be used for determining
stream flow into a reservoir. Where such data are not available gauge data from another
watershed (external) which closely approximates the watershed of interest may be used. Factors to
17
consider when selecting the external gauging station shall include location, percent stratified drift,
vegetation, slope, flow regulation, upstream land uses and drainage area size.
(2) Runoff information must be related to stream gauging records.
(3) Direct precipitation and evaporation related to surface area of the reservoir shall be
included in the mass balance analysis. Rainfall and evaporation data shall be based on an interval
no greater than one month and may be combined for a net impact to the reservoir.
(4) Diversions of water into or out of the watershed must be included in the analysis, as
well as the operating characteristics of the diversion, flow capacity of the diversion and the runoff
to the point of diversion. Existing as well as proposed diversions will be analyzed.
(5) Consumptive losses to the watershed shall be evaluated.
(6) The physical characteristics of the reservoir shall be described. At minimum, this will
include the total reservoir storage capacity and useable reservoir storage capacity. It will also
describe whether flashboards are used and any other pertinent information necessary to describe
the physical characteristics of the reservoir. Top and bottom elevation of the reservoir shall be
provided using the mean sea level as a datum.
(7) Reservoirs with less than 150 million gallons of storage per square mile of watershed
area shall evaluate yield based on short and long duration droughts (respectively, less than and
greater than 1 year) and use the worst case for analysis. In no case shall the analysis be based on a
critical dry period with less than a 1% occurrence.
(8) The operating characteristics (rules) of the reservoirs shall be described.
(9) Releases shall be described as required by federal and state law.
(10) The amount of leakage through the dam shall be estimated.
(11) The determination of safe yield shall factor in sediment deposition.
(12) When determining safe yield, outflow (water demand for domestic, industrial,
commercial, and agricultural use) shall be based on monthly draft rates. Uniform withdrawal rates
may be used, where appropriate, and if previously approved by the RI Water Resources Board or
its successor.
(13) The critical drawdown period shall be measured from full, or near full, reservoir
levels to the bottom of the useable storage or lowest elevation reached for 1 year or less-cycle
reservoirs.
(14) Numerical methods are preferred for safe yield determinations. Graphical methods,
consistent with item 12 of this section, may be used.
(c) Describe the methodology for determining maximum potential yield, maximum well capacity,
18
and well efficiency of existing groundwater supplies. Based upon available information water
suppliers should present a summarized description of each well as required below. Background
documentation should not be included. However, references should be cited. No additional
fieldwork will be required to provide "missing" aquifer test information.
(1) Identify the aquifer in which the well(s) or well field is located and any pertinent
hydrologic/geologic information affecting the supply of water.
(i) For the approved wellhead protection area, provide a scaled map, with north
arrow, denoting locations of observation and/or monitoring wells, ponds, streams,
wetlands, other wells, and all other information that may be pertinent to the hydrogeologic
setting of the well. A USGS topographic map may be used for this purpose. Where details
become difficult to read, a larger scaled map, such as a driller's report, may be used.
(2) Provide a description of each production and observation well including but not
limited to the following, as applicable:
(i) Description of geologic material drilled through;
(ii) Depth to bedrock;
(iii) Estimate of saturated thickness of the aquifer at the well location. If this is not
available then provide the depth from the water table to the bottom of the well;
(iv) Maximum drawdown level;
(v) Date and results of most recent aquifer test or well redevelopment, to include:
(A) Name of individual or entity that conducted the pump test;
(B) Pumping rates for test;
(C) Duration of pump test;
(D) Static water level;
(E) Final pumping water level;
(F) Specific capacity;
(G) Transmissivity; and
(H) Description of any difficulties with the aquifer test.
(vi) Date and results of quarterly specific capacity determination, to include:
(A) Type and rated capacity of existing production well pump;
(B) Duration of pump operation;
(C) Static water level; and
(D) Pumping water level.
(vii) Well efficiency expressed as the ratio of the most recent measured specific
capacity to the maximum specific capacity determined from the most recent aquifer test or
redevelopment.
(3) Report the maximum potential yield for each well based on the results of the most
19
recent tests described in section 8.04.2 (c)(2) of the regulations.
(4) State the current pumping rates of the existing wells, in addition to the maximum well
capacity of each well based on such limitations as the pump’s relationship to other wells,
interference from other wells, contamination, excessive drawdown, any restrictions on pumping
rate due to operational considerations, regulatory requirements or other factors, etc. For each
production well provide a brief redevelopment history, if applicable.
(d) A determination of available water shall identify any limitations to utilization of the safe yield
for surface waters or maximum well capacity of wells, including any constraints such as hydraulic
considerations, treatment limitations, or interference effects that must be considered in the estimate
of available water. For purposes of this analysis, available water shall be the sum of the
operational safe yield of surface water supplies, maximum well capacity, 90% of untapped
groundwater capacity, and water purchased from other suppliers.
(1) For both existing and future conditions, compare available water with average and
maximum daily demand. Improved efficiencies or "water savings" resulting from proposed
supply, demand, and system management measures shall be factored into each analysis, as
appropriate. If average daily demand exceeds available water, identify additional supply, demand
and/or system management measures to be undertaken and if necessary, the timing and quantity of
additional supplies and facilities. The analyses shall include the following:
(A) Existing Conditions: Compare existing available water with existing average
daily and maximum daily demand for the most recent year.
(B) Future Conditions: Compare future available water with projected average
daily and maximum daily demands for the 5 and 20 year planning periods.
8.04.3 Alternative Supply
Identification of available alternative water supply sources including retention of water
sources for standby or future use that are in compliance with or can meet drinking water quality
standards; reactivation of any water sources not in use; potential system interconnections for
ongoing, standby, or emergency use; supply augmentation; and shared or joint-use facilities or
sources. Factors to be considered include but are not limited to the following:
(1) General description of treatment necessary to utilize alternative water supply source(s)
based upon final and currently proposed requirements of RIGL Chapter 46-13 as administered by
the RI Department of Health;
(2) Ability of existing treatment facilities to improve raw water quality to applicable
drinking water quality standards;
(3) Capacity of pumping and distribution systems;
(4) Necessary measures to maintain or improve the quality of water supply sources; and
20
(5) For reactivation of temporarily inactive water sources, identify necessary remediation
measures.
8.04.4 Supply Augmentation Studies
Supply augmentation studies shall assess recommended alternative water supply sources
with a discussion of the reasons for selecting each option to be implemented. Included in the
evaluation should be an analysis of the ability to meet future demand. Where applicable,
information such as necessary construction, lands needed, lands to be sold or for which a change in
use is proposed, water rights needed, water quality, identification of existing and potential
competing uses of the resource, relationship to local, regional and state land use plans, costs and
financing, timing, and life-expectancy of facilities should be addressed.
(1) Water suppliers operating at a safe yield based upon a critical dry period with a
probability of occurrence of 5% that are unable to document to the Boards' satisfaction that they
are able to safely operate at this level of risk, shall be required to immediately initiate supply
augmentation studies.
(2) Supply augmentation studies shall be initiated immediately if all appropriate supply,
demand, and system management measures have been implemented and the average daily demand
for the most recent year equals or exceeds available water, as defined in Section 8.04.2.
Augmentation studies shall also be initiated immediately, if individually, the safe yield of the
reservoir system or 90% of the current well capacity is exceeded.
(3) If the analysis of the ability to provide an adequate supply of potable water for the 5-
year and 20-year period, as required under Section 8.04.2 (d), herein indicates the need for
additional sources of supply or facilities, water suppliers shall initiate supply augmentation
studies.
8.05 Demand Management
The plan shall describe measures to reduce the demand for, and to effectuate efficient use of, the
state’s water resources. The plan shall include a program to retrofit existing water uses not in
conformance with the RI State Building Code, Plumbing Code Regulations SBC-3 (1990) for
water-saving plumbing equipment.
(a) Residential Retrofit Program (RRP): The Residential Retrofit Program plan shall describe the
steps necessary to establish and administer the retrofit program (e.g. hire consultants/staff) and a
schedule for implementation. The Residential Retrofit Program shall provide for the distribution of
retrofit kits, as described below. The Board shall consider plans utilizing water-saving plumbing
equipment which achieves higher performance standards and/or results in greater water savings.
An example would be an incentive program to accelerate replacement of older toilets with water
conserving models. The Board shall review and approve of alternative RRP plans on a case by
case basis. The minimum Residential Retrofit program shall include but not be limited to the
following:
21
(1) Annual Notification of Program Objectives and Achievements: No later than one year
after approval of the RRP plan by the Board and on an annual basis thereafter, water suppliers
shall publicize the objectives and accomplishments of the retrofit program and the availability of
water efficiency devices and installation services at cost, or at no direct cost.
(2) Retrofit Kits: Water suppliers shall offer kits containing water saving plumbing
devices; installation of said devices will be at cost or at no direct cost to all residential users. A
minimum of 1 retrofit kit which at a minimum contains 2 low-flow faucet aerators, 1 low-flow
showerhead, 1 toilet displacement device, 1 package of leak detection tablets, installation
instructions, leak detection pamphlet, reorder card for obtaining additional equipment, and a
survey form to evaluate the potential for long term water conservation, shall be made available to
all residential dwelling units.
(i) Water suppliers are encouraged to investigate making other water-saving
plumbing
equipment, such as replacement toilets using 1.6 gallons per flushing cycle, available at
cost.
(ii) Minimum standards for water-saving plumbing equipment: Where applicable,
the water saving plumbing equipment shall conform to or exceed the RI State Building
Code, Plumbing Code Regulations.
(iii) Water suppliers may act as a central purchaser and supplier of water-saving
plumbing equipment and may enter into cooperative agreements with other water suppliers
or other agencies to facilitate bulk purchases of water-saving equipment required to
implement approved retrofit plans.
(3) Implementation Schedule: Residential Retrofit Programs shall be phased in over a 10-
year period. A minimum of 10% of all residential dwelling units annually shall be targeted for kit
distribution and installation as outlined in Section 8.05 (a) (4). An implementation period of less
than 10 years shall be required for any water suppliers projected to need new or additional
supplies within the 10-year period. In these cases, the time period for implementation shall be
determined by the Board on a case by case basis.
(4) Retrofit Kit Distribution: The actual number of water-saving plumbing devices
installed is greatly influenced by the water supplier's level of effort in distributing the equipment,
educating the public on its use and related benefits, and assisting in installation, if necessary. The
distribution method selected by the water supplier shall assure a high level of water saving
plumbing equipment installation.
(i) A minimum of 10% of the residential dwelling units annually shall be targeted
for distribution and installation of water conservation devices.
(ii) Acceptable kit distribution methods include the following:
(A) Mailing or direct delivery of retrofit kit request cards to each
residential
class user;
22
(B) Direct distribution of kits to residential dwelling units (door-to-door
delivery or direct mailing of kits);
(C) Messages included on customer bills providing a toll free phone
number
to call to order retrofit kit(s); or
(D) Other method as previously approved of by the Water Resources
Board.
(iii) Within 30 - 60 days of distribution of retrofit kits, customers shall be reminded
of the importance of water conservation and to install the water saving plumbing devices.
Water suppliers may opt to publish reminders in local newspapers, to distribute
installation reminder cards, telemarketing or other approaches, as appropriate.
(iv) Distribution of kits to residential users in apartments and multi-family housing
units serviced by single meters: Distribution of kits shall be to the owner or manager of the
apartment or multi-family housing unit. Multi-family kit request cards shall be developed
and distributed. Water suppliers shall not be required to offer installation assistance to
multi-family housing units.
(v) For water suppliers needing new or additional supplies within 5 years before
additional sources of supply are pursued, water suppliers shall directly distribute retrofit
kits at cost or at no direct cost to all residential dwelling units and shall explain the need
for and cost effectiveness of full compliance with water conservation requirements.
(5) Public Education and Information: Efforts should be tied to key events in the
Residential Retrofit Program and shall include a media campaign as specified in Section 8.05 (a)
(1). Additionally, water suppliers are encouraged to offer water conservation presentations at
local schools and to civic and other organizations. Water suppliers are encouraged to coordinate
education and information efforts with other water suppliers or agencies.
(b) Major Users Technical Assistance Program (MUTAP): Water suppliers shall provide
technical assistance to major users as defined herein, in the performance of water audits and in the
formulation and implementation of sanitary device retrofit programs. Major users for which
technical assistance may be provided include multiple unit housing areas or developments,
commercial, industrial, institutional, government and agricultural and other outdoor water users.
(1) The MUTAP plan should include the following:
(i) A list of the major users, annual water uses, and types of use;
(ii) A description of the steps necessary for the major user to establish the technical
assistance program (e.g. hire consultants and/or staff, training).
(iii) A prioritized schedule for conducting water audits and formulating sanitary
device
23
retrofit programs. Priority should be given to major users with the greatest potential for
water savings.
(2) Water suppliers may enter into cooperative agreements with the owners or management
of such users for the preparation of specifications, bulk purchase, and installation of sanitary
device retrofit equipment for the purpose of implementing the retrofit programs.
(3) Water suppliers shall request of major users a general description for implementation
of demand management practices that will achieve a high level of efficiency.
(4) Implementation Schedule: The MUTAP plan shall include a schedule for
implementation of the proposed technical assistance program.
(c) Appropriate fees, rates, and charges to reduce demand shall be utilized, consistent with Section
8.09 herein.
8.06 System Management
System management measures necessary to insure that the physical components of the water system
are properly operated and maintained shall be described. A stated goal of system management
shall be to minimize non-account water and to strive to achieve and maintain less than 15% non-
account water as set forth in Water Supply Policies for Rhode Island, State Guide Plan Element
721, September 1997. Water suppliers are encouraged to establish a long-term goal of reducing
non-account water to 10% of the total metered supply. System improvements and maintenance
activities necessary to maintain compliance with RIGL Chapter 46-13 as administered by the RI
Department of Health must also be considered. System management measures to be described
shall include but not be limited to the following:
(a) Meter Installation, Maintenance, and Replacement (MIMR) Plan.
(1) 100% of water delivered, including water sold wholesale to other water suppliers
shall be metered to include public buildings. Excluded from this metering requirement is water
used for fire fighting purposes and system maintenance purposes, including flushing and active
bleeders. Water suppliers shall set forth a plan by which all water delivered shall be metered.
(2) All water suppliers shall effect and carry out a program for installation of remote
reading or automatic reading systems. These programs shall be in place and operational no later
than July 1, 2001.
(3) All water suppliers shall develop and carry out programs for recording metered usage
and billing thereafter, at an interval less than 1 year, as determined appropriate, not later than July
1, 2001. Water suppliers not meeting this deadline must demonstrate that the continuation of
annual meter reading and billing is consistent with the purposes of RIGL 46-15.3 et. seq, Water
Supply System Management Act, and specific statutory provisions for the implementation of
demand management measures that achieve a high level of water use efficiency through use of fees,
24
rates, and charges to influence use (RIGL 46-15.3 5(c)(1)(d) and the provision of timely and
accurate information on costs to users (RIGL 46-15.3-22 ).
(4) For major users, a schedule of maintenance and replacement of meters shall be
developed so as to maintain applicable meter standards. A schedule for testing and calibration
shall be developed.
(5) Master meters shall be tested at least once a year and calibrated as necessary to the
printed recommendations of the meter manufacturer and to good engineering practice.
(i) Ranges of meter accuracy should be in general conformance with the latest
revisions of the American Water Works Association (AWWA) standards (c700 Series) as
summarized in "Water Meters - Selection, Installation, Testing, and Maintenance" (AWWA
M6) and/or specific Rhode Island State Plumbing Code requirements.
(ii) When an AWWA standard for a meter is not available, the user must
demonstrate to the satisfaction of the Board that the meter is capable of measuring not less
than 95% and not more than 105% of the water that passes through the meter. All meter
tests shall be documented and maintained by the water supplier.
(b) Leak Detection and Repair (LDR) Plan:
(1) General Policy: Water supply management plans shall at a minimum set forth a
comprehensive plan and schedule for the detection and repair of leaks so as to maintain non-
account water at or below 15% of total metered supply. Comprehensive leak detection surveys
shall be conducted on a periodic basis according to specific needs, however surveys shall be
conducted immediately if non-account water exceeds 15%. Leaks should be repaired
expeditiously.
(2) The Leak Detection and Repair Plan shall set forth a plan and schedule for the detection
and repair of leaks and shall include but not be limited to a description of the types of leak
detection methods used and the sensitivity of the method used.
(3) If a comprehensive sonic leak detection and repair program has been completed since
the last plan submission, discuss the number of leaks found, the number fixed, the amount of water
saved, and the existing leakage rate in gallons per day per mile.
(4) If leak detection and repair objectives have been achieved, discuss the planned
continuing maintenance program to retain and achieve the lowest leakage rate feasible.
(c) Preventive Maintenance (PM) Plan shall be prepared and implemented. The PM Plan shall
include:
(1) A schedule for periodic inspection, maintenance, and/or testing of critical components
of the supply, treatment, storage, and distribution facilities, including emergency and standby
equipment and facilities (e.g. pumping station(s), valves, hydrants, water main flushing, cleaning,
lining, and upon start up, testing connections to emergency water supply sources) in general
25
conformance with recommended practices established in applicable American Water Works
Association standards.
(2) Accurate record keeping of inspections and routine maintenance;
(3) Evaluation of records and when necessary, the scheduling and performance of
corrective measures; and
(4) Maintenance of spare parts inventory and names and locations of manufacturers and
distributors of critical components.
8.07 Emergency Management
The emergency management component shall assess system risks and response capabilities, and
shall describe a practicable contingency plan for water supply emergencies. The plan shall at a
minimum:
(a) Identify known and potential natural and human-caused risks to the water system and assess the
extent and severity of each water supply emergency situation on each component of the water
supply system. Identification of system risks shall include but not be limited to hurricanes and
major storms, droughts which exceed the water supply systems' design drought, seasonal water
shortages, interruptions in the transmission or distribution system, obvious and immediate
contamination risks to water sources or transmission or distribution systems and limitations in
water sales agreements. The plan need not address emergencies experienced by water suppliers
on a routine basis, such as pipe breaks, inoperable valves and emergency power sources.
(b) Identify critical components of the water supply system that may be partially or totally
incapacitated during emergency situations. This analysis shall serve as the basis for the
development of programs of physical improvements and emergency management plans.
(c) Estimate the water system’s remaining capabilities to meet demand for each water supply
emergency situation. Describe the system storage capacities; supply redundancy, and other
available contingency measures.
(d) Identify demands on the system and evaluate the level of service to be sustained during
different emergency conditions. Major users and priority users should be identified. Assignment
of priority should be based upon the potential risk to health, safety and welfare posed by the
curtailment or suspension of service. The plans should identify the steps deemed appropriate and
feasible to reduce the demand for water for the duration of the water supply emergency, including
the enactment of bans or restrictions on certain water uses and/or new connections, as appropriate.
(e) Identify personnel responsible for actions and any training needs.
(f) Describe notification procedures and the means of implementation, if applicable, to be
followed in various emergency situations. The plan shall include notification of personnel, state
and local officials, media and the public, including public notification of priority users, advance
26
notification of users for which service may be curtailed or suspended if rationing is required and
for implementation of rationing and use bans.
(g) Inventory emergency or stand-by equipment, critical spare parts, and supplies; identify
additional equipment, parts, or supply needs, and the procedures for obtaining additional
equipment or loaning available equipment or services. Where appropriate, stand-by power to all
electrically operated facilities must be of sufficient capacity to provide 100% of the system's
average daily demand during an electrical outage. Interagency agreements specifying availability
and use of loaned equipment or services shall be documented in writing. This inventory shall
include but not be limited to availability and need for standby power for pumping station(s),
treatment plant(s) and extraordinary treatment processes.
(h) Identify sources of emergency water supply including but not limited to interconnections and
independent industrial and commercial water supplies within the service area. Identification of
legal, technical and financial requirements for their use, a schedule for activation, periodic testing,
available yield, and quality of the sources shall be included. Agreements with other water
suppliers or with independent industrial or commercial entities for use of emergency water
supplies shall be documented in writing.
(i) As appropriate and feasible, the plan may also address the necessary steps to treat
contaminated sources of supply.
(j) Specify water supply emergency responses which become progressively more stringent
depending upon the seriousness of the water supply emergency. Critical indicators of the
seriousness of the emergency, the extent of facility damage and seasonally varying triggers, such as
designated reservoir levels shall be identified. For groundwater supplies, consideration should be
given to seasonally varying trigger levels involving drawdown of the wells and/or static water
levels. These critical indicators shall act to trigger a mandatory management review and the
initiation of an appropriate response.
(k) Outline the steps to be taken for recovery from an emergency, including reverse triggers, as
appropriate, and describe when the steps will be activated.
(l) Outline and provide cost estimates for immediate actions or expenditures necessary to
eliminate critical vulnerabilities of the existing water supply system. Evaluate the availability of
resources to eliminate vulnerabilities and for overall implementation of the emergency
management plan. Pricing of specific emergency response procedures need not be included.
(m) Describe the relationship of the emergency management plan with other applicable local or
state plans.
8.08 Implementation Schedule, Responsible Entities, and Projected Costs
(a) Water supply system management plans shall designate the person(s) or organization
responsible for taking each action, others who must participate, and the time period in which the
action is to be taken.
27
(b) The capital, operating, and maintenance costs, if any, of each action shall be estimated.
Facilities and/or programs or studies scheduled for construction or implementation within 5 years
of the date of plan preparation should be more thoroughly evaluated than those actions scheduled
for later implementation.
8.09 Financial Management
(a) General Guidelines of Water Supply System Management.
(1) All rates and charges made by water suppliers which decline as quantity used increases
are hereby declared not conducive to sound water supply management designed to properly
conserve, develop, utilize, and protect this finite natural resource.
(2) Each water agency will operate in a financially self-supporting manner. Each shall
maintain long term revenue levels sufficient to cover all fixed and variable capital and operating
costs of conservation, use, management, protection, development and other costs of water supply
and may be allowed a reasonable profit as may be appropriate for the water supplier's type of
ownership and as consistent with Public Utilities Commission regulations. Charges to the water
supplier for intergovernmental services shall be fair and reasonable.
(3) The anticipated source(s) of funds to implement the water supply system management
plan shall be identified including but not limited to funds generated through fees, rates and charges
against water users. Such charges shall be limited to those necessary and reasonable to undertake
the actions required by RIGL Chapter 46-15.3 as made operative by these procedures. These
charges shall be included in bills rendered as specified herein.
(b) Current Financial Management Practices: Water supply system management plans shall
describe the water supplier's current financial management practices and status including but not
limited to:
(1) In spreadsheet format, a summary of operating income and expenses for the past 3
years:
(i) Annual water rate revenue; general facility charge revenue; special assessment
revenue; reserve fund revenues and/or other earned or unearned revenue from operating
funds shall be listed under operating income.
(ii) Annual water system indebtedness, including debt service on bonds; operation
and maintenance expenses; facility replacement funds; appropriations for major
improvements; and/or other expenses shall be listed under operating expenses, as
appropriate.
(iii) Any grants, loans, income from bond sales and income earned while holding
these or other capital funds shall be listed under capital funds.
(2) Existing rate structures shall be described.
28
(3) Frequency of billing and collection procedures and policies shall be described.
(c) Future Revenue Sources: Water supply system management plans shall list and discuss
anticipated revenue sources to implement system improvements and programs. A plan allocating
funds to finance system improvements and programs scheduled for implementation within 5 years
of plan preparation should be prepared. The plan should describe basic revenue requirements to
fund system operation, maintenance and improvements and discuss the systems' ability to secure
the revenue needed. Any assumptions regarding inflation rate, interest rates, bonding limit, grant
eligibility, etc. should be clearly stated.
(d) Assessment of Rates: Necessary changes in the rate structure to generate revenues for future
improvements shall be included. In establishing fees, rates, and charges, water suppliers shall
consider the following factors:
(1) Recovery of all capital and operating costs, fixed and variable of production, treatment,
conservation, use, management, protection, obtaining, development, procuring, and/or transporting
water, and its sale at wholesale or retail.
(2) Marginal cost pricing.
(3) Emergency and drought period surcharges.
(4) Seasonal price structures.
(5) Difference in costs based upon different points of delivery.
(6) The effect of fees, rates, and charges on use of water and, where applicable, on
wastewater costs and charges.
(7) The effect of reducing non-account water to levels consistent with or below stated
goals.
(8) The costs of preparing, maintaining, and implementing water supply system
management programs.
(e) Billing:
(1) Regular schedule,
(i) Bills shall be rendered on a regular schedule for metered usage.
(2) Joint Billing,
(i) All water suppliers selling water at retail shall discuss cooperative initiatives
or joint billing efforts for water supply and wastewater treatment in cooperation with the
parties responsible for the latter within the same water supply service area.
29
(ii) The water supplier shall evaluate arrangements with municipalities and
wastewater treatment agencies for operation of a combined billing system, including
equitable sharing of costs.
8.10 Coordination
(a) Water supply system management plans shall be coordinated and consistent with applicable
local comprehensive plans and shall be integrated into the water supply plans of the municipality
or municipalities in which the service area is or is planned to be located. Conversely, the local
comprehensive plans shall be consistent with water supplier's water supply system management
plans. Water supply system management plans shall describe water supplier's efforts to
coordinate with municipalities with respect to coordination of planning efforts. Particular
attention should be focused on existing and future land uses, zoning requirements, growth
projections, responsibilities and capabilities to respond to water supply emergencies, planning for
capital improvement needs, and other areas of mutual interest.
(b) Water supply system management plans shall describe water supplier's efforts to coordinate
with other water suppliers with respect to interconnections, service area expansions, capabilities
to assist in the response to water supply emergencies, the potential for regionalization and other
areas of mutual interest, as appropriate.
(c) Water supply system management plans shall describe water suppliers’ efforts to coordinate
with operators of wastewater treatment facilities servicing all or part of the water supply service
area with respect to data collection and the undertaking of feasibility studies of joint billing.
(d) In the event of conflicts between policies and plans of agencies, municipalities, water
suppliers, the Board shall encourage coordination and negotiate for the public interest in water.
8.11 Rhode Island Geographic Information System Compatibility
(a) All geographic data prepared as part of this plan should be in a form that the Board is able to
transfer data directly into the Rhode Island Geographic Information System (RIGIS). All data shall
be mapped to meet USGS National Map Accuracy standards for 1:24000 scale mapping. The
geographic basis will be Rhode Island State Plane Coordinates (RISPC) on the North American
Datum (NAD 83) in units of feet.
Digital mapping products should be suitable for immediate entry into the RIGIS database without
further modification. The accepted RIGIS data transfer file format is ESRI Arc/Info¹ export in a
non-compressed form. Although not restricted to the use of ESRI (Arc/Info) software, all
deliverables must be directly importable into Arc/Info coverage’s with polygon topology suitable
for immediate use by both workstation (NT and UNIX) and PC Arc/Info software.
Data set documentation requirements as are contained in a Digital Database Standards for the
RIGIS, published by the Environmental Data Center of the University of Rhode Island, and as
30
amended and superseded by Metadata Standards and Specifications for the RIGIS, RI Department
of Administration, Division of Planning (October 1993). Data sets within RIGIS are shared and
offered under licensing policy to any other requester.
SECTION 9.00 DATA COLLECTION REQUIREMENTS
Water use data must be assembled as an element of projecting long-term future water demand and
availability of supplies in order to assess progress in achieving identified objectives, including the
effectiveness of water conservation programs.
9.01 Reporting Requirements:
An interim report shall be submitted no later than 30 months from the Board's approval date of the
Water Supply System Management Plan (WSSMP). Any 30-month reporting date, previously
required by DEM and required for the Water Supply System Management Plan (WSSMP), shall be
re-evaluated by the Board in consultation with each supplier. An amendment to a water supply
management plan may be submitted to the Board at any time.
The 30-month report shall include updated water system data as further specified below. For
suppliers with approved water supply system management plans or water supply management
plans, it should include the status of the water supplier's plan implementation and shall describe
progress in completing specific milestones and/or tasks outlined in the approved plan. The report
shall include but not be limited to the following information:
(a) Metered water production from each source on a monthly basis;
(b) Metered water purchased from other water supplier(s) by interconnection, on a monthly basis;
(c) Estimate of population served, and number of service connections;
(d) Total metered retail water sales on an annual basis and metered retail water sales by user
category on an annual basis;
(e) Metered wholesale water sales by interconnection on a monthly basis;
(f) Estimated volume of water used for fire fighting purposes on an annual basis;
(g) Estimated volume of non-account water on an annual basis.
31
SECTION 10:00 PLAN SUBMITTAL
10.01 Time Schedule for Plan Submittal
(a) Each water supplier required by these regulations to prepare and maintain a water supply
system management plan shall file such plan per a date determined by the Water Resources Board.
(b) Institutional water suppliers or water suppliers that obtain, transport, purchase, or sell an
amount of water exceeding 50 million gallons per year are required to submit a water supply
system management plan, under the rules set forth in these procedures. The Board allows 18
months from the end of the chronological year in which the 50 million gallons or more per year
volume occurred for the development of these plans.
(c) In order to determine when a water supplier meets the 50 million-gallon per year threshold
under WSSMP, the Board shall utilize the information from the Rhode Island Department of
Health, payment of state surcharges, and any other available information.
10.02 Plan Amendments
(a) Each water supplier shall review its plans at least once every 5 years from the date of Board
approval or whenever a significant component of the plan is no longer valid, and shall amend or
replace its plan as required so as to remain current. The Board may notify the water supplier in
writing of any section(s) of the plan requiring revisions and of the reasons such revisions are
necessary. Such revised plan shall be submitted to the Board in accordance with a negotiated
schedule not to exceed 1 year beyond the 5 year due date.
(b) Circumstances under which a plan may be deemed invalid requiring updating include but are
not limited to the following:
(1) The water supplier proposes to add or abandon a source of supply beyond those
addressed in an existing plan;
(2) The water supplier projects water demand to be significantly greater than the demand
projected in an existing plan;
(3) Existing or projected demand exceeds available water;
(4) A new contract for the sale or purchase of water is executed;
(5) Use of an existing or proposed source becomes infeasible;
(6) Significant changes in existing or potential sources of contamination to water supplies.
(c) If only minor alterations to an existing plan are considered necessary, the water supplier may
request a waiver of the plan amendment requirement from the Board. The request for waiver must
be accompanied by written evidence supporting this conclusion including a progress report on all
items.
32
(d) Plan amendments or request for waivers will include a report of progress in implementing
priority measures.
10.03 Filing of Plans
(a) Each water supplier, as defined herein, shall file at least 7 copies of all plans, and amendments
thereto to the Board. The Board will deliver a copy to the following:
(1) The Office of Drinking Water Quality of the Department of Health;
(2) The Statewide Planning Program of the Department of Administration;
(3) The Administrator of the Division of Public Utilities and Carriers, and
(4) The Department of Environmental Management.
(b) The water supplier shall place an additional copy of all plans, replacements, and amendments
at its main office as well as in the main library of each municipality in which it serves on a retail
basis. The locations of public review copies will be part of the legal notice requirements.
10.04 Requests For Time Extensions
(a) Water suppliers may request in writing that the Board extend the time in which to complete
and submit its water supply system management plan, replacements, revisions, or
amendments thereto, 30 month interim report or other filings required by the Water Supply
System Management Act, RIGL 46-15.3 et seq., not to exceed 1 year. Such requests for
time extensions must be received no later than three months prior to the required filing's
scheduled submittal date.
(b) Approval of such requests shall be granted only upon demonstration that an extension is
justified by extraordinary circumstances of the water supplier. An extension, if approved,
shall not waive any of the requirements of Section 12.02, of these regulations.
(c) No extensions of time shall be granted for the submittal of emergency management plans.
SECTION 11.00 REVIEW OF PLANS
11:01 Review Process
(a) The Board shall coordinate the review of water supply system management plans and any
replacements or amendments thereto, prepared by water suppliers subject to these rules.
(b) Upon receipt of a water supply system management plan, replacements, revisions, or
amendments thereto, by the Board, the Board shall "date stamp" the plan. The "date stamped" date
shall be used to determine the initiation of the 90-day and 180-day specified review periods.
33
(c) The Board shall accept comments on water supply system management plans and any
replacements, or amendments thereto from the Office of Drinking Water Quality of the Department
of Health, the Statewide Planning Program of the Department of Administration, the Department of
Environmental Management and the Division of Public Utilities and Carriers no later than 90 days
from the date stamped by the Board, pursuant to Section 11.02(c).
(d) Upon consideration of the written comments by all agencies designated herein and any public
comment (Section 11.02) provided to the Board, the Board shall determine whether the plan
complies with the requirements of these procedures. The Board shall approve plans found in
compliance with these procedures.
(e) The Board shall notify the water supplier of its determination in writing. Unless extended by
the issuance of a first notice of deficiencies, the determination shall be made within 180 days of
the date stamped by the Board, pursuant to Section 11.01(c).
(f) Failure of the Board to notify a water supplier of its determination within the said time limit
shall constitute approval of the submitted water supply system management plan. However, if
plans, replacements or amendments thereto are submitted prior to the scheduled submittal date, the
Board may opt to utilize the scheduled submittal date as the initial submission date for purposes of
initiating the 180 day specified review period.
(g) The time period for the review of water supply system management plans, replacements,
revisions, or amendments thereto submitted after the scheduled submittal date shall be as
determined by the Board.
(h) The time period for the review of water supply system management plans amended as a result
of an invalidation of a plan component shall be in accordance with a schedule as agreed to by the
Board.
11.02 Public Comment
(a) The Board shall provide a 30-day period within the 180-day review period to receive
comments from the general public on the water supply system management plan.
(b) The Board shall publish a notice of the public comment period in a Rhode Island newspaper
having daily statewide circulation and at the discretion of the Board, in a local newspaper having
the largest daily circulation within the water supplier's service area.
(c) The Board shall accept written comment during the comment period.
(d) The plan shall be adopted by the governing board of each water supplier following a public
hearing. Notice of such public hearing shall be published once by the supplier at least 20 days
before the date set for the public hearing in a newspaper of general circulation in the State of
Rhode Island. Such notice shall set forth the date, time, and place of such hearing; means of public
review of the plan, and a brief description of the matters to be considered at such hearing.
34
SECTION 12.00 DETERMINATIONS OF PLAN COMPLIANCE
12.01 Determination of Compliance
Upon consideration of the written comments by all agencies designated herein and any public
comment received by the Board, the Board shall determine whether the plan is in substantial
compliance with the objectives of the Water Supply System Management Act and the requirements
of these regulations. Substantial compliance shall be defined as having achieved the Water Supply
System Management Act's stated objectives, goals, and planning mandates or otherwise having
committed resources, as evidenced by a schedule for the timely implementation of such actions
necessary to achieve the Act's objectives, goals, and mandates, as further specified in Section
8.08. The Board shall issue a determination of compliance to water suppliers whose plans have
been found in compliance with these regulations.
12.02 Determination of Non-Compliance
(a) The Board shall issue a determination of non-compliance should the following occur:
(1) A municipality or water supplier subject to the Water Supply System Management Act
fails to submit a water supply system management plan, replacement, revisions, or amendments
thereto, or a 30 month interim report or other filings required by the Water Supply System
Management within specified time periods as provided herein;
(2) Any reviewing agency finds that substantive deficiencies prevent the water supply
system management plan, replacements, revisions, or amendments thereto from meeting the
requirements of the Water Supply System Management Act and the Board finds that these
deficiencies constitute substantial non-compliance with the Act and this rule.
(b) The Board shall notify suppliers and other reviewing agencies of its determination of non-
compliance in writing and shall specify areas of non-compliance.
(c) The date for re-submission of the revised or replacement plan shall be in accordance with a
schedule as agreed to by the Board and the water supplier, not to exceed 1 year from the date of
determination of non-compliance. Any subsequent revisions shall be re-submitted no later than 6
months from the date of any subsequent notification by the Board.
(d) Revised or replacement plans shall be filed with the Board, as specified in Section 10.03 of
these regulations, unless instructed otherwise by the Board. Said review agencies shall review
and may submit written comments to the Board.
12.03 First Notice of Deficiencies
A first Notice of Deficiencies shall be issued if the Board finds that the water supply system
management plan, replacement, revision or amendment thereto is deficient due to incorrect,
inconsistent, or missing data or information but otherwise is in substantial compliance with the
objectives of the Water Supply System Management Act.
35
(a) The water supplier shall have 120 days from the date of notification within which to correct the
deficiencies and resubmit the replacement plan or filing to the Board.
(b) The Board shall have 90 days from the date of the resubmission to determine whether the
replacement plan or filing is in compliance with the regulations.
(c) Failure by the Board to notify the water supplier of its determination in writing within 90 days
of the date of resubmission shall constitute acknowledgement of compliance.
(d) The existing plan shall retain in effect until such time as the 5-year update or amendments are
approved.
SECTION 13.00 EVALUATION OF PLAN IMPLEMENTATION
13.01 General Policy
The Board may issue a determination of non-compliance should the following occur:
(a) Failure of a water supplier to implement their Board-approved plan.
(b) Failure of a water supplier to submit a 30-month report as further specified in Section 9.01.
(c) The Board after reviewing progress made in implementing a plan, finds that plan
implementation is not sufficient to achieve the objectives of the Water Supply System Management
Act. In assessing progress made under an approved water supply system management plans, the
Board shall consider the financial and technical resources available to the water supplier, factors
that are and are not within the control of the water supplier, changes occurring since the plan was
adopted or most recently amended, and other matters relevant to the execution of a water supply
system management plan.
SECTION 14.00 APPEAL PROCEDURE
14.01 Filing of Appeal
All appeals shall be in writing and shall be filed with and received by the Board within 30 days of
the notification of non-compliance.
14.02 Contents of Appeal
Every appeal shall contain all information necessary and procedures required by the Board, and
the water supplier's name and address, and the name of the chief executive officer, director or head
of the agency.
36
14.03 Conduct of Hearing
The notice and conduct of the hearing by the Board shall comply in all respects with provisions of
the Administrative Procedures Act, RIGL Chapter 42-35.
14.04 Burden of Proof and Standard for Review
At the adjudicatory hearing, the water supplier shall have the burden of proof to demonstrate by
clear and convincing evidence that the water supply system management plan complies with the
requirements of these rules and procedures.
SECTION 15.00 ENFORCEMENT
The Board shall forward any determinations of non-compliance made pursuant to Section 12.02
and 13.01 of these regulations to the Division of Public Utilities and Carriers for consideration of
enforcement action as set forth in RIGL Section 39-4-3.