Section 180
Section 180.
Emergency Assents
1. Catastrophic Storms Assent
A. The Executive Director may grant an
Emergency Assent when catastrophic storms,
flooding, and/or erosion has occurred at a site
under Council jurisdiction, and where, if im-
mediate action is not taken, the existing conditions
may cause one or more of the following:
1)
Immediate threat to public health and safety;
2)
Immediate
and
significant
adverse
environmental impacts;
These Emergency Assents may permit only such
action at the site that will correct conditions (1) and
(2) above in a manner consistent with the policies
of the Program.
2. Imminent Peril Assent
A. The Chairman, Vice Chairman, or in their
absence the Executive Director, may grant an
Emergency Assent in circumstances where they
determine that there is imminent peril and where, if
immediate action is not taken, the existing
conditions may cause one or more of the following:
(1) Bodily harm or a threat to public health;
(2) Significant adverse environmental impacts;
or
(3) Significant economic loss to the State.
B. The reasons for these findings shall be stated
on the record.
3. Post Hurricane and Storm Permitting
Procedures
A. It shall be the policy of the Council to
establish emergency procedures for the issuance
of assents in the event of the following:
(1) A hurricane, severe storm or other disaster
has caused severe and widespread damage in
portions of CRMC jurisdiction; and
(2) The Governor has submitted a formal
request to the President to declare areas within
CRMC jurisdiction a major disaster area; and
(3) The Executive Director of the CRMC
determines the probable number of applications
for CRMC assents resulting directly from the
disaster will cause significant delays in the
orderly processing of assents and, thereby
impose an undue hardship on disaster victims
and other applicants; and
(4) The CRMC shall provide adequate public
notice of its decisions to impose emergency
procedures.
B. The Council encourages other state agencies
and each coastal community to adopt emergency
permitting procedures equivalent to those of the
CRMC
in
order
to
speed appropriate
reconstruction and minimize adverse economic and
environmental impacts.
C. The Council shall impose a temporary
moratorium to remain in effect for a maximum of
30 days from the disaster declaration. The purpose
of the moratorium shall be to provide the Council
and affected coastal communities with adequate
time to assess damages, determine changes in
natural features that may change vulnerability to
damage, and identify mitigation opportunities. The
temporary moratorium shall apply to the following:
(1) Applications for new alterations and
activities requiring Council Assent, which do not
result from the disaster.
(2) Reconstruction of all residential and
associated residential structures, commercial and
recreational structures in both A-zone and
V-zone that were destroyed by 50% or more by
storm induced flood, wave and wind damage.
D. During
the
moratorium,
priority
consideration will be given to necessary and/or
emergency
alterations,
reconstruction,
or
replacement of essential public facilities, such as
roads, bridges, and public utilities. The Council
recognizes that a major hurricane or other storm
events
may
severely
damage
or
destroy
infrastructure and utilities such as roads, bridges,
water and sewer lines located in high hazard areas.
When such damage occurs, it shall be the policy of
the Council to require the review of alteration
reconstruction options which may lessen or
mitigate the probability of future recurrent damage.
Rhode Island Coastal Resources Management Council
Original Edition
Page 2
Section 180
E. During the moratorium the Executive
Director of the Council shall solicit the
recommendations of the Rhode Island Department
of Environmental Management and the local
municipalities for the purchase of open space or
other mitigative responses in high damage areas
and make a policy decision about repermitting
according to best available options for hurricane
mitigation.
F.
Procedures and priorities for addressing post
storm reconstruction applications after the
moratorium are as follows:
1)
Priority will be given to consideration of
applications for reconstruction of structures
which were physically damaged or destroyed 50
percent or more by storm-induced flooding, wave
or wind damage.
2)
Applicants for repair or reconstruction in A,
B, or C flood zones, as delineated in the FEMA
maps, may follow the procedures in Section
300.14 Maintenance.
3)
Final priority will be given to any application
for new alterations and activities unrelated to the
disaster.
4)
If the Executive Director determines that a
large number of post-storm applications will be
received, and that the normal processing will
result in an undue burden or hardship to storm
victims, and the Executive Director determines
there is no over-riding programmatic policy of
goal to be served by holding a group of
applications, then the Executive Director may, in
specific instances, waive the requirements of a
new Assent for structures physically destroyed
50 percent or more by storm-induced flood, wave
and wind damage, and allow for Emergency
Permits to be issued.