835-RICR-20-00-1
835-RICR-20-00-1. Use of the Wastewater Facilities (version Amendment, 03/31/2004 to 12/13/2004)
TABLE OF CONTENTS
ARTICLE 1-PURPOSE..................................................................................................1
ARTICLE 2-DEFINITIONS..........................................................................................2
ARTICLE 3-MUNICIPAL SEWER CONNECTION PERMITS..........................17
3.1
Municipal Permit Applications ............................................................17
3.2
Application Review................................................................................17
3.3
Amendments by the Commission........................................................17
3.4
Municipal Applications to Amend Permit..........................................17
ARTICLE 4-BUILDING SEWER CONNECTION PERMITS.............................18
4.1
Mandatory Connections ........................................................................18
4.2
Direct Connections .................................................................................18
4.3
Indirect Connection................................................................................18
4.4
Municipal User Lists ..............................................................................18
4.5
Building Sewer Connection Permits Required...................................19
4.6
Transfer of Permits Not Allowed.........................................................19
4.7
Building Sewer Connection Permit Application................................19
4.8
Expedited Permit Process......................................................................20
4.9
Permit Conditions...................................................................................20
4.10 Building Sewer Connection Plans........................................................20
4.11 Flow Monitoring/Impact Analysis......................................................21
4.12 Discharge from Swimming Pools.........................................................21
4.13 Stormwater Connections .......................................................................22
4.14 Grease Removal Systems.......................................................................22
4.15 Connection Costs ....................................................................................24
4.16 Building Sewers ......................................................................................24
4.17 Existing Building Sewers.......................................................................24
4.18 Building Sewer Construction................................................................24
4.19 Building Sewer Elevation ......................................................................24
4.20 Disconnection..........................................................................................25
4.21 Clean Outs ...............................................................................................25
4.22 Safety Requirements...............................................................................25
4.23 Interference with Traffic Flow ..............................................................25
4.24 Notice to the Commission .....................................................................26
4.25 Sewer Alterations (Permits) ..................................................................26
ARTICLE 5-DISCHARGE REQUIREMENTS, LIMITATIONS.........................27
5.1
Authority..................................................................................................27
5.2
General Discharge Limitations .............................................................27
5.31 Specific Discharge Limitations .............................................................27
5.32 Specific Facility Limitations ..................................................................31
5.4
General Discharge Prohibitions............................................................32
5.5
Specific Discharge Prohibitions............................................................32
5.6
Federal Categorical Pretreatment Standards......................................33
5.7
Dilution Prohibition ...............................................................................34
5.8
Remedies..................................................................................................34
ARTICLE 6-INTERFERENCE WITH COMMISSION PROPERTY ..................35
ARTICLE 7-INSPECTION POWERS.......................................................................36
7.1
General Powers.......................................................................................36
7.2 User Documentation ..............................................................................36
ARTICLE 8-WASTEWATER DISCHARGE PERMIT SYSTEM ........................38
8.1
Wastewater Discharge Permits Required ...........................................38
8.2
Compliance Required.............................................................................38
8.3
Expedited Permit Process......................................................................38
8.4
Wastewater Discharge Permit Application ........................................38
8.5
Permit Conditions...................................................................................40
8.6
General Pretreatment Requirements ...................................................42
8.7
Installation of Zero Discharge Pretreatment Systems.......................43
8.8
Compliance Certification.......................................................................44
8.9
Spill and Slug Prevention Control and Countermeasures
Plan ...........................................................................................................44
8.10 Duration of Permits/Reissuance of Permits.......................................47
8.11 Modification of Permits .........................................................................47
8.12 Transfer of Permits .................................................................................47
8.13 Wastewater Discharge Permit Revocation..........................................48
8.14 Suspension of Permit..............................................................................49
8.15 Reinstatement of Permit ........................................................................49
ARTICLE 9-WASTEWATER MONITORING AND REPORTING ..................50
9.1
Records and Monitoring........................................................................50
9.2
Inspection and Sampling.......................................................................51
9.3
Monitoring and Analysis of Process Wastewater..............................52
9.4
Baseline Monitoring Report ..................................................................53
9.5
Compliance Schedule Progress Report ...............................................55
9.6
Report on Compliance with Categorical Pretreatment
Standard Deadline..................................................................................55
9.7
Periodic Compliance Reports ...............................................................56
9.8
Notification/Reporting Requirements................................................56
9.9
Hazardous Waste Notification .............................................................60
9.10 Signatories and Certification.................................................................60
ARTICLE 10-ENFORCEMENT .................................................................................61
10.1 Administrative Enforcement Remedies ..............................................61
10.2 Calculation of Administrative Penalty................................................65
10.3 Administrative Hearings.......................................................................67
10.4 Equal Access to Justice Application.....................................................69
10.5 Petitions for Declaratory Rulings .........................................................70
10.6 Judicial Remedies ...................................................................................70
10.7 Costs .........................................................................................................71
10.8 Annual Publication of Users in Significant Noncompliance ...........72
10.9 Denial of Access......................................................................................72
10.10 Inspection of Connections......................................................................72
10.11 Affirmative Defenses to Discharge Violations....................................74
ARTICLE 11-INTERPRETATION OF REQUIREMENTS...................................76
11.1 Construction............................................................................................76
11.2 Captions ...................................................................................................76
11.3 Severability ..............................................................................................76
ARTICLE 12-AMENDMENT TO RULES AND REGULATIONS.....................77
ARTICLE 13-RESERVED ...........................................................................................78
ARTICLE 14-SEPTAGE DISCHARGE PERMIT SYSTEM .................................79
14.1 Septage Permitting System....................................................................79
14.2 Septage Sources.......................................................................................79
14.3 Septage Load Tickets..............................................................................79
14.4 Septage Disposal.....................................................................................80
14.5 Septage Prohibitions...............................................................................81
14.6 Septage Records......................................................................................81
14.7 Compliance Required.............................................................................81
printed 11/94
ARTICLE 1-PURPOSE
In order to insure the proper collection, treatment and disposal of wastewater
and sewage sludge and adequate treatment of industrial wastewater within the
Narragansett Bay Water Quality Management District (District); to encourage the
recovery and recycling of wastes and the proper operation and maintenance of
interceptors and the treatment facilities within said District; to comply with the
requirements of the United States Environmental Protection Agency and the
Rhode Island Department of Environmental Management and to provide for the
keeping of records of the Narragansett Bay Water Quality Management District
Commission Wastewater Facilities (Facilities) the following Rules and
Regulations governing the use of wastewater facilities within the Narragansett
Bay Water Quality Management District Commission (Commission) are adopted
by the Commission as provided by Title 46, Chapter 25, as amended, of the
General Laws of 1980 of the State of Rhode Island creating and organizing said
Commission. In the event of future wastewater facility acquisitions and/or
annexations to the Commission, these Rules and Regulations shall become
incorporated by reference and binding thereon, and all previous Rules and
Regulations of said facility/facilities shall be abolished. Upon acquisition
and/or annexation, any and all site specific facility limitations necessary and/or
appropriate to remain in full force and effect shall be incorporated by reference
and retained by way of appendices to the Commission’s current Rules and
Regulations. All such modifications shall be subject to the necessary public
notice and hearing requirements for major modifications as mandated by 40 CFR
403.18, prior to incorporation.
printed 11/94
1
ARTICLE 2-DEFINITIONS
ACT or THE ACT shall refer to the Narragansett Bay Water Quality
Management District Commission Act, Title 46, Chapter 25 & 25.1, et seq., as
amended.
APPURTENANCE shall mean auxiliary structures attached to a sewer which
shall include, but not be limited to, pump stations, slots, regulators, outfalls,
force mains, manholes, catch basins, tide gates, monitoring devices and metering
chambers.
AUTHORIZED EMPLOYEES or AGENTS OF THE COMMISSION shall mean
a person who by reason of his or her general position, contract or job description
with the Commission has specific duties and responsibilities to perform on
behalf of the Commission.
AUTHORIZED REPRESENTATIVE OF USER:
A. If the user is a corporation, authorized representative shall mean:
1)
the president, a vice-president, secretary, or treasurer of the
corporation in charge of a principal business function, or any
other person who performs similar policy or decision-making
functions for the corporation, or
2)
the manager of one or more manufacturing, production or
operation facilities employing more than 250 persons or having
gross annual sales or expenditures exceeding $25 million (in
second-quarter 1980 dollars), if authority to sign documents has
been assigned or delegated to the manager in accordance with
corporate procedures.
B. If the user is a partnership, association, or sole proprietorship an
authorized representative shall mean a general partner or the
proprietor.
C. If the user is representing Federal, state or local governments, or an agent
thereof, an authorized representative shall mean a director or
highest
official appointed or designated to oversee the operation and
performance
of the activities of the government facility.
D. The individuals described in paragraphs 1-3 above may designate
another authorized representative if said authorization is submitted to
the Commission in writing and specifies the individual or position
printed 11/94
2
responsible for the overall operation of the facility from which the
discharge
originates
or
having
overall
responsibility
for
environmental matters of the company.
printed 11/94
3
BATCH DISCHARGE shall mean a discharge that does not flow on a
continuous basis or the discharge of all or part of the contents of a tank that
occurs intermittently or over a short period of time. A holding tank or
equalization tank which receives concentrated batch discharges which are then
discharged or "bled" into the sewer system over an extended period of time shall
be considered a batch discharge.
BIOCHEMICAL OXYGEN DEMAND (BOD) shall mean the quantity of oxygen
utilized in the biochemical oxidation of organic matter under standard laboratory
procedure for five (5) consecutive days at 20 degrees centigrade expressed in
terms of weight and concentration (milligrams per liter (mg/l)).
BIOLOGICALS shall mean preparations made from living organisms and their
products, including vaccines, cultures, etc., intended for use in diagnosing,
immunizing or treating humans or animals or in research pertaining thereto.
BLOOD PRODUCTS shall mean any products derived from human blood,
including, but not limited to, whole blood, blood plasma, platelets, red or white
blood corpuscles, and other derived licensed products, such as interferon, etc.
BOARD OF COMMISSIONERS shall mean the Narragansett Bay Water
Quality Management District Commission sitting as a governing body at a duly
authorized meeting with a quorum being present.
BODY FLUIDS shall mean liquids emanating or derived from humans including
blood, blood products, cerebrospinal, pleural, peritoneal and pericardial fluids,
and amniotic fluids, and semen and vaginal secretions but excluding feces, urine,
nasal secretions, sputum, sweat, tears, saliva, and breast milk, unless any such
excluded substance contains visible blood or is isolation waste.
BUILDING DRAIN shall mean that part of the lowest horizontal piping within
a building that carries water, wastewater or stormwater to a building sewer.
BUILDING SEWER shall mean the extension from the building drain to the
public sewer, or other place of disposal. Also referred to as “house connection”.
BYPASS shall mean the intentional diversion of waste streams from any portion
of a user's treatment facility.
printed 11/94
4
CATEGORICAL
PRETREATMENT
STANDARD
OR
CATEGORICAL
STANDARD shall refer to any regulation containing pollutant discharge limits
promulgated by the U.S. E.P.A. in accordance with Section 307 (b) and (c) of the
Federal Water Pollution Control Act which applies to a specific category of users
and which appears in 40 CFR Chapter 1, Subchapter N, parts 405-471,
incorporated herein by reference.
CHEMICAL OXYGEN DEMAND (COD) A measure of the amount of oxygen
required to oxidize organic and oxidizable inorganic compounds in water.
CLEAN WATER ACT shall refer to the Federal Water Pollution Control Act, also
known as the Clean Water Act, as amended, 334 USC 1251 et seq.
COLOR shall refer to the optical density at the visual wave length of maximum
absorption, relative to distilled water, one hundred percent (100%) transmittance
is equivalent to zero (0.0) optical density.
COMBINED SEWER shall mean a sewer intended to receive and convey both
wastewater and surface runoff from storms.
COMMISSION for the purposes of these Rules and Regulations shall be
construed to mean the Narragansett Bay Water Quality Management District
Commission in its capacity as a public corporation or acting though its
authorized employees and agents. (See BOARD OF COMMISSIONERS
definition.)
COMPOSITE SAMPLE shall refer to the sample collection technique resulting
from the combination of individual wastewater grab samples taken at selected
intervals based on either an increment of flow or time.
CONCENTRATED DISCHARGE shall mean either a batch or continuous
discharge with a mass load exceeding one hundred percent (100%) of the daily
maximum allowable mass load, as calculated for each individual user for any
parameter regulated under Article 5 of these Rules and Regulations. The
concentrated discharge mass load shall be calculated as follows:
V x C2
Percentage (%) =
------------
x 100
Q x C1
Where:
V =
total volume of the concentrated discharge(s) in gallons.
C2= concentration of the concentrated discharge in mg/l for any
parameter regulated under Article 5.
printed 11/94
5
Q =
average daily flow of regulated process water in gallons as
determined by the Commission for the individual user.
C1 = daily maximum allowable concentration in mg/l for any
parameter regulated under Article 5.
CONTACT COOLING WATER shall mean any water used for cooling purposes
which comes into direct contact with the object being cooled such as any raw
material, intermediate product, waste product or finished product.
DILUTION shall mean the addition of water or wastewater to another
wastewater stream in order to change the concentration of certain pollutants or
pollution causing agents.
DISCHARGE shall mean the introduction of water, wastewater and/or
pollutants into the Commission's facilities from any source.
DISTRICT OR NARRAGANSETT BAY WATER QUALITY MANAGEMENT
DISTRICT shall be defined by Title 46, Chapter 25, as amended, of the Rhode
Island General Laws.
DIRECT CONNECTION shall mean the connection of a building sewer directly
to a sewer owned by the Commission.
EASEMENT shall mean the acquired legal right to use land owned by others for
a specific purpose.
ENVIRONMENTAL PROTECTION AGENCY (EPA) shall refer to the U.S.
Environmental Protection Agency or, where appropriate, the term may also be
used as a designation for the Regional Water Management Division Director or
other duly authorized official of said agency.
EXECUTIVE DIRECTOR shall mean the Executive Director of the Narragansett
Bay Water Quality Management District Commission or his or her designee.
EXISTING SOURCE shall include, but not be limited to, any source of
discharge, the construction or operation of which commenced prior to the
publication of proposed categorical pretreatment standards under section 307(b)
and (c) (33 U.S.C. 1317) of the Federal Water Pollution Control Act, which will be
applicable to such source if the standard is thereafter promulgated in accordance
with section 307 of the Federal Water Pollution Control Act.
FACILITY OR FACILITIES (See WASTEWATER FACILITIES definition)
printed 11/94
6
GARBAGE shall include, but not be limited to, the wastes resulting from the
handling, preparation, cooking and serving of food, and from the handling,
storage, and sale of produce.
GARBAGE DISPOSAL UNIT or GARBAGE GRINDER shall mean a
mechanical device used for grinding, shredding or macerating garbage to a small
particle size before discharge to the sewer.
GRAB SAMPLE shall mean a sample which is taken from a waste stream on a
one-time basis with no regard to the flow in the waste stream and without
consideration of time.
GREASE shall mean volatile and non-volatile residual fats, oils, fatty acids,
soaps, waxes, mineral oils and other materials of similar composition.
GREASE REMOVAL DEVICE shall mean a device for removal of grease
and/or oil from a wastewater discharge.
INDIRECT CONNECTION shall mean a building sewer connection that is not a
direct connection; and whose wastewater discharge shall, notwithstanding the
passage in its normal course through other sewers or conduits, ultimately
discharge in whole or in part through Commission sewers.
INDUSTRIAL WASTES shall refer to wastewater from industrial processes,
trade or business as distinct from domestic or sanitary wastes.
INFECTIOUS WASTES shall refer to wastewater contaminated by or
containing any agent or organism, such as a virus or a bacteria, capable of being
communicated by invasion and multiplication in body tissues and capable of
causing disease or adverse health impacts in humans.
INTERFERENCE shall mean a discharge which, alone or in conjunction with a
discharge or discharges from other sources, both: (1) inhibits or disrupts the
Commission's facilities, treatment processes or operations, or sludge processes,
use or disposal; and (2) therefore is a cause of a violation of any requirement of
the Commission's RIPDES permit (including an increase in the magnitude or
duration of a violation) or of the prevention of sewage sludge use or disposal in
compliance with any of the following statutory/regulatory provisions or permits
issued thereunder (or more stringent State or local regulations): Section 405 of the
Clean Water Act; the Solid Waste Disposal Act (SWDA), including Title II
commonly referred to as the Resource Conservation and Recovery Act (RCRA);
printed 11/94
7
and State regulations contained in any State sludge management plan prepared
pursuant to Subtitle D of SWDA; the Clean Air Act; the Toxic Substances Control
Act; and the Marine Protection, Research and Sanctuaries Act.
printed 11/94
8
ISOLATION WASTE shall mean biological waste and discarded materials
contaminated with blood, excretion, exudates, or secretions from humans who
are isolated to protect others from certain highly communicable diseases, or
isolated animals known to be infected with highly communicable diseases. and
specified by the Center for Disease Controls (CDC) as classification 4.
MAY is permissive.
MEDICAL WASTE means any solid waste which is generated in the diagnosis,
treatment (e.g., provision of medical services), or immunization of human beings
or animals, in research pertaining thereto, or in the production or testing of
biologicals.
MUNICIPALITY shall mean any city, town, state authority or sewer district that
discharges wastewater into the sewers owned by the Commission.
NATIONAL PRETREATMENT STANDARD shall mean any regulation
containing pollutant discharge limits promulgated by EPA in accordance with
section 307 (b) and (c) of the Federal Water Pollution Control Act, which applies
to a specific category of Industrial Users.
NEW SOURCE shall mean any source of a discharge, the construction or
operations of which commenced after the publication of proposed Categorical
Pretreatment Standards under Section 307 (c) of the Federal Water Pollution
Control Act which will be applicable to such source if the standards are
thereafter promulgated in accordance with section 307 (c), provided that:
A. No other source is located at that site; or
B. The
source
completely
replaces
the
process
or
production
equipment that causes the discharge of pollutants of an existing
source at that site; or
C. The new wastewater generating process of the source is substantially
independent of an existing source at that site; and the construction of the
source creates a new facility rather than modifying an existing source at
that site.
For purposes of this definition, construction or operation has commenced if the
owner or operator has:
A.
Begun, or caused to begin as part of a continuous on-site
construction program:
printed 11/94
9
1) Any placement, assembly, or installation of facilities or
equipment; or
2) Significant site preparation work including clearing, excavation,
or removal of existing structures or facilities which is necessary for
the placement, assembly or installation of new source facilities or
equipment; or
B.
Entered into a binding contractual obligation for the purchase of
facilities or equipment which are intended to be used in its
operation within a reasonable time. Options to purchase or
contracts which can be terminated or modified without substantial
loss, and contracts for feasibility, engineering, and design studies
do not constitute a contractual obligation under this definition.
NONCONTACT COOLING WATER shall mean water used for cooling which
does not come into direct contact with any raw material, intermediate product,
waste product or finished product.
OUTFALL shall mean the mouth of a sewer, drain or conduit where an effluent
is discharged into the receiving waters.
OWNER or OPERATOR shall mean any person who owns, leases, operates,
controls or supervises a source.
PASS THROUGH shall mean a discharge which exits the Commission's facilities
into waters of the United States in quantities or concentrations which, alone or in
conjunction with a discharge or discharges from other sources, causes a violation
of any requirement of the Commission's RIPDES permit, (including an increase
in the magnitude or duration of a violation).
PERSON shall mean any individual, partnership, copartnership, firm, company,
corporation, association, joint stock company, trust, estate, municipality, any
local, state or Federal agency or any other legal entity, or their legal
representatives, agents or assigns.
pH shall mean the logarithm (to the base 10) of the reciprocal of the hydrogen ion
concentration in moles per liter (m/l) of solution. Neutral waste waters are
numerically equal to 7, the number increases to show increasing basicity and
decreases to show acidity.
POLLUTANT shall mean any dredged spoil, solid waste, incinerator residue,
sewage, garbage, sewage sludge, munitions, medical wastes, chemical wastes,
printed 11/94
10
industrial wastes, biological materials, radioactive materials, heat, wrecked or
discarded equipment, rock, sand, cellar dirt, and agricultural and industrial
waste which affect the characteristics of wastewater (i.e., pH, temperature, TSS,
turbidity, color, BOD, COD, toxicity, odor).
POLLUTION shall mean the man-made, or man-induced alteration of the
chemical, physical, biological and radiological integrity of water.
PRETREATMENT or TREATMENT shall mean the reduction or elimination of
pollutant properties in wastewater or their alteration to a less harmful state
thereby rendering them less harmful to the facilities prior to or in lieu of
discharging or introducing such pollutants into the Commission's facilities. The
elimination, reduction or alteration can be accomplished by physical, chemical or
biological processes, process changes or by other means, except as prohibited by
40 CFR chapter 403.6(d).
PRETREATMENT STANDARDS AND REQUIREMENTS shall mean any
substantive or procedural requirement related to pretreatment, including
National pretreatment categorical standards and prohibitive discharge standards
imposed on a user.
PUBLICLY OWNED TREATMENT WORKS (POTW) shall mean the facility
defined by Section 212 of the Federal Water Pollution Control Act owned by the
Commission including any devices and systems used in the storage, treatment,
recycling and reclamation of municipal sewage and industrial waste. The
systems include sewers, pipes and equipment used to carry wastewater to the
treatment facility.
RECEIVING STREAM or WATER OF THE STATE shall mean all streams,
lakes, ponds, marshes, watercourses, waterways, wells, springs, reservoirs,
aquifers, irrigation systems, drainage systems and all other bodies or
accumulations of water, surface or underground, natural or artificial, public or
private, which are contained within, flow or border upon the State of Rhode
Island or any portion thereof.
REGULATED MEDICAL WASTE shall mean a special category of solid waste
that includes specific types of medical waste that includes solid, semisolid, or
liquid materials, but does not include domestic sewage materials. This waste is
subject to the handling and tracking requirements of Rhode Island DEM.
Categories of regulated medical waste are defined as blood, blood products,
body fluids, contaminated sharps, discarded cultures and stocks of infectious
agents and associated biologicals, isolation wastes, pathological waste and
oncological waste.
printed 11/94
11
RESIDENTIAL USERS shall mean persons only contributing sanitary
wastewater to the municipal wastewater system.
RHODE ISLAND POLLUTION DISCHARGE ELIMINATION SYSTEM
(RIPDES) PERMIT shall mean a permit issued pursuant to Section 402 of the
Federal Water Pollution Control Act (33 U.S.C. 1342).
SANITARY SEWER shall mean a sewer that is designed to carry liquid and
water-carried wastes from residences, commercial buildings, industrial plants,
and institutions together with minor quantities of ground, storm, and surface
wastes that are not discharged intentionally.
SEWAGE shall mean human excrement and gray water (household showers,
dish washing operations, etc.).
SEPTAGE shall mean the liquid, solid and gaseous contents of a septic tank.
SEPTIC TANK shall mean an underground tank used for the disposal of
domestic wastes.
SEWER shall mean a pipe or conduit, and other appurtenance provided to carry
wastewater or stormwater.
SEWER USER FEE shall mean a charge levied on users for use of the wastewater
treatment and collection system.
SHALL is mandatory.
SIGNIFICANT INDUSTRIAL USER shall mean any industrial user that is
classified under any of the following:
A.
Industrial user subject to categorical pretreatment standards;
B.
Any other industrial user that:
1) discharges an average of 5,000 gpd or more of process
wastewater; or
2) contributes a process waste stream which makes up 5 percent or
more of the average dry weather hydraulic or organic capacity
of the Commission's treatment plant; or
3) is designated as significant by the Commission on the basis that
the user has a reasonable potential for adversely affecting the
printed 11/94
12
POTW's operation or for violating any pretreatment standard or
requirement.
SIGNIFICANT NONCOMPLIANCE shall mean:
A.
Chronic violations of wastewater discharge limits, defined here as
those in which 66% or more of all of the measurements taken
during a six month period exceed (by any magnitude) the daily
maximum limit or the average limit for the same pollutant
parameter;
B.
Technical Review Criteria (TRC) violations, defined here as those in
which 33% or more of all of the measurements for each pollutant
parameter taken during a six month period equal or exceed the
product of the daily maximum limit or the average limit multiplied
by the applicable TRC (TRC=1.4 for BOD, TSS, fats, oil, and grease
and 1.2 for all other pollutants except pH);
C.
Any other violation of a pretreatment effluent limit (daily
maximum or longer-term average) that the Commission determines
has caused, alone or in combination with other discharges,
Interference or Pass Through (including endangering the health of
Commission personnel or the general public);
D.
Any discharge of a pollutant that has caused imminent
endangerment to human health, welfare or to the environment or
has resulted in the Commission's exercise of its emergency
authority to halt or prevent such a discharge;
E.
Failure to meet, within 90 days after the schedule date, a
compliance schedule milestone contained in a Commission
notification, permit or enforcement order, for starting construction,
completing construction or attaining final compliance;
F.
Failure to provide, within 30 days after the due date, required
reports such as baseline monitoring reports, 90-day compliance
reports, self-monitoring compliance reports and reports on
compliance with compliance schedules;
G.
Failure to accurately report noncompliance;
printed 11/94
13
H.
Any other violation or group of violations which the Commission
determines has adversely effected the operation or implementation
of the Industrial Pretreatment Program.
SLUDGE shall mean the solids, residues, and precipitate separated from or
created in wastewater by the unit processes of a publicly owned treatment works
or industrial pretreatment systems.
SLUG shall mean any discharge of a non-routine, episodic nature, including but
not limited to, an accidental spill or a non customary batch discharge.
SOURCE shall mean any building, structure, facility or installation from which
there is or may be the discharge of pollutants.
STANDARD METHODS shall mean methods for the examination of water and
wastewater published jointly by the American Public Health Association, the
American Water Works Association, and the Water Pollution Control Federation.
STANDARD INDUSTRIAL CLASSIFICATION (SIC) CODE shall mean a
classification pursuant to the Standard Industrial Classification Manual issued by
the U.S. Office of Management and Budget.
STORM SEWER shall mean a sewer that carries stormwater and other wash
waters or drainage, but excludes domestic, sanitary, commercial, and industrial
wastes. Also called a “storm drain”.
STORMWATER shall mean surface water and any other source of run-off. It is
normally collected in sewers separate from the sanitary sewers and receives
minimal, if any, treatment prior to discharge to receiving waters.
SUBDIVISION shall mean the division or re-division of a lot, tract or parcel of
land into two (2) or more lots, tracts, parcels. Any adjustment to existing lot lines
of a recorded lot by any means shall be considered a subdivision. The division of
property for purposes of financing constitutes a subdivision.
SURFACE WATER POLLUTANT shall mean stormwater or other wash water
or drainage carrying any pollutants which affect the characteristics of
wastewater.
SUSPENDED SOLIDS shall mean (1) insoluble solids that either float on the
surface or, are suspended in water, wastewater or other liquids; (2) solid organic
or inorganic particles (colloidal, dispersed, coagulated, flocculated) physically
held in suspension by agitation or flow or; (3) the quantity of material removed
printed 11/94
14
from wastewater in a laboratory test, as prescribed in "Standard Methods for the
Examination of Water and Wastewater" and referred to as nonfilterable residue.
TOXIC POLLUTANTS shall mean any substance listed as toxic under section
307 (a)(1) of the Federal Water Pollution Control Act, and listed under the
Hazardous Substances Right-to-Know Act, R.I.G.L.§28-21-1 et seq., and as may
otherwise be designated by the Commission.
TREATMENT PLANT EFFLUENT shall mean any discharge of pollutants from
the Commission's facilities into waters of the State.
TURBIDITY shall mean a condition in water or wastewater caused by the
presence of suspended matter, resulting in the scattering and absorption of light
rays and determined by measurement of light diffraction, usually reported in
arbitrary turbidity units.
USER means any person, firm, corporation, government or other entity that
discharges, causes or permits the discharge of wastewater into the Commission's
facilities.
WASTEWATER shall mean all the spent water of a community. It may include,
but not be limited to, a combination of the liquid and water-carried
wastes from residences, commercial buildings, industrial plants, institutions and
governmental facilities whether treated or untreated together with any
groundwater, surface water, and stormwater that may be present which are
contributing to the Commission's facilities.
WASTEWATER FACILITIES (FACILITIES) as used herein, shall mean the
structures, equipment, and processes required for the collection, treatment, and
disposal of wastewater and sewage sludge which are owned and operated by the
Commission.
WASTEWATER TREATMENT PLANT or TREATMENT PLANT shall mean
an arrangement of devices and structures for treating wastewater and sludge.
Sometimes used as synonymous with waste treatment plant, sewage treatment
plant, or wastewater treatment works.
ZERO DISCHARGE WASTEWATER PRETREATMENT SYSTEM shall mean
a wastewater pretreatment system with no discharge to the sewer system.
printed 11/94
15
ABBREVIATIONS
The following abbreviations shall have the designated meanings:
BOD
-
Biochemical Oxygen Demand
ASTM
-
American Society of Testing and Materials
COD
-
Chemical Oxygen Demand
CFR
-
Code of Federal Regulations
DEM
-
Department of Environmental Management
EPA
-
Environmental Protection Agency
gpd
-
gallons per day
l
-
liter
mg/l
-
milligrams per liter
m/l
-
moles per liter
POTW
-
Publicly Owned Treatment Works
NBC
-
Narragansett Bay Water Quality District Commission
NPDES
-
National Pollution Discharge Elimination System
RIDEM
-
Rhode Island Department of Environmental Management
RIGL
-
Rhode Island General Laws, as amended.
RIPDES
-
Rhode Island Pollution Discharge Elimination System
SIC
-
Standard Industrial Classification Code
TRC
-
Technical Review Criteria
TSS
-
Total Suspended Solids
TTO
-
Total Toxic Organics (as defined in 40 CFR 433.11(e))
WEF
-
Water Environment Federation
printed 11/94
16
ARTICLE 3-MUNICIPAL SEWER CONNECTION PERMITS
3.1 Municipal Permit Applications
Each municipality shall obtain a permit from the Commission for all existing
sewers connected to the Commission's facilities. Application for this permit shall
be made on a form provided by the Commission. The permit application is to be
prepared by the municipality at its own expense and submitted when requested
by the Commission.
3.2 Application Review
Each municipality shall furnish all necessary information and data in accordance
with any guidelines established by the Commission.
The Commission shall evaluate the adequacy of data furnished with the permit
application. If insufficient data has been furnished the Commission shall require
the municipality to provide additional data within a specified time. After
reviewing the data, the Commission may issue the permit. The Commission may
stipulate special conditions and terms upon which the permit will be issued.
3.3. Amendments by the Commission
The Commission may change the conditions of a permit from time to time as
circumstances, including law or regulations enacted or promulgated by the state
or Federal Government or its agencies, may require. A municipality may request
a hearing on proposed amendments to its permit in accordance with the
provisions of Article 10.
3.4 Municipal Applications to Amend Permit
Any municipality proposing a new connection or the elimination of an existing
connection to the Commission's facilities shall apply for an amendment to its
permit prior to constructing or eliminating the connection. The municipality shall
furnish all necessary data in accordance with any guidelines established by the
Commission. After reviewing the data, the Commission may issue or deny an
amendment to the permit for the proposed connection or for the elimination of
an existing connection. No new connection or elimination of an existing
connection may be made without first being granted such an amendment.
printed 11/94
17
ARTICLE 4-BUILDING SEWER CONNECTION PERMITS
AND REQUIREMENTS
4.1 Mandatory Connections
The owner of any building or property generating sanitary or industrial
wastewater situated within the District and abutting on any street, alley, or right-
of-way in which a public sewer is located, is required, at his or her own expense,
to construct a building sewer and connect it to the public sewer.
4.2 Direct Connections
No person(s) shall uncover, make any direct connection with or opening into,
use, alter, disturb, tamper with or increase flow by more than twenty percent
(20%) to any Commission owned sewer or appurtenance thereof without first
being granted a written permit from the Commission. The Commission may
require the owner at his or her own expense to perform appropriate testing of
any of the materials and/or integrity of the sewer connection.
4.3 Indirect Connections
The requirements of this Section 4.3 shall not apply to single or multifamily
residences containing less than three (3) dwelling units per structure, unless such
dwelling is part of a subdivision.
No person(s) shall make any indirect connection or increase the flow from any
structure by more than twenty percent (20%) to any Commission owned sewer
or appurtenance thereof without first being granted a written permit from the
Commission. Structures requiring such permits shall include but not be limited
to, industrial and commercial facilities, residences or multifamily residences
containing three (3) or more dwelling units per structure, all subdivisions,
publicly owned buildings, and non-profit institutions. The Commission may
require the owner, at his or her own expense, to perform appropriate testing of
any of the materials and/or the integrity of the sewer connection.
4.4 Municipal User Lists
Upon request, each municipality shall furnish the Commission with a list of all
users within the municipality. Each municipality that has authority over building
permits, shall require all persons proposing to connect to the facilities and who
are required to obtain a permit from the Commission to do so prior to the
municipality's issuing a building permit. Each municipality shall notify the
printed 11/94
18
Commission of all applications for building permits for structures subject to the
provisions of Sections 4.2 and 4.3 above.
4.5 Building Sewer Connection Permits Required
The owner(s) of any property subject to the provisions of Sections 4.2 and 4.3
above must obtain a building sewer connection permit for any direct or indirect
connection to the Commission's facilities. Such permit shall be effective for six
(6) months from the effective date of the permit and shall be renewable at the
Commission's option for one additional six (6) month period. Said renewal shall
be requested by the owner at least two (2) weeks prior to the expiration date.
4.6 Transfer of Permits Not Allowed
Building sewer connection permits are issued to a specific applicant for a specific
use and connection. A building sewer connection permit shall not be reassigned,
transferred or sold to a new owner, new user, different premises, or a new or
changed operation without written Commission approval.
4.7 Building Sewer Connection Permit Application
Persons seeking a building sewer connection permit must complete and file an
application with the Commission, together with any applicable permit fee. In
support of this application, the applicant shall submit the following information:
A.
Name of applicant and address of premise(s) which applicant
wishes to connect to the Commission's facilities;
B.
Overall site plan and plot plan;
C.
Detailed plans of the proposed sewer connection;.
D.
Any other pertinent features, specifications or information which
the Commission may require to assist in its evaluation of the
application.
The Commission may require that any and all designs and/or drawing plans
which include mechanical or plumbing components be stamped by a licensed
Rhode Island Professional Engineer. All applications for building sewer
connection permits must be signed by the owner of the premises and the licensed
plumber or licensed drain layer who is constructing the sewer connection. The
Executive Director shall evaluate the data furnished by the owner and may
require additional information pertinent to the application. Based on the
printed 11/94
19
application, the Executive Director may issue a building sewer connection
permit, subject to the terms and conditions enumerated in the permit.
The Executive Director may deny a request for a permit when the information
supplied indicates the user will be unable to reasonably meet the Commission's
standards. Any person denied a permit may request a hearing in accordance
with the provisions of Article 10 herein.
4.8 Expedited Permit Process
Application for an expedited permit must be made in accordance with the
Expedited Permit Process, R.I.G.L.§42-117-1 et seq. which requires that the
potential permittee file a Certificate of Critical Economic Concern at the time of
filing any necessary permit application with the Commission. Upon receipt of
said Certificate and in accordance with R.I.G.L.§42-117-1 et seq., the Commission
shall give priority to the handling and processing of the permittee's application.
4.9 Permit Conditions
Persons seeking building sewer connection permits shall be expressly subject to
specific permit provisions contained therein as well as to provisions of these
Rules and Regulations and all other regulations, user charges and fees
established by the Commission. Permit conditions may include, but are not
limited to, the following:
A.
Compliance with Federal, state, and other governmental laws, rules
and regulations;
B.
Requirement for the submittal of "as-built" plans within sixty (60)
days after the final inspection by the Commission, indicating pipe
and joint materials and applicable ASTM specifications on the
plans;
C.
Requirements for use of water-conserving fixtures in the proposed
structure or dwelling;
D.
Requirement for obtaining necessary town or city permit and
compliance with any applicable town or city requirements;
E.
Provisions for authorized Commission personnel and agents to
enter and inspect the premises;
printed 11/94
20
F.
Requirement for posting of performance bonds for materials
and/or labor costs associated with such permitted sewer
connection; and
G.
Any other reasonable conditions necessary to ensure compliance
with the provisions of R.I.G.L.§46-25-1 et seq.
4.10 Building Sewer Connection Plans
Persons seeking a building sewer connection permit must submit plans in
accordance with the requirements set out in Section 4.7 above. In addition, such
plans must meet the following specifications:
A.
All plans must show a "North" arrow and shall be oriented so the
"North" arrow points upward or to the right-hand side of the plan;
and
B.
All plans must be identified by titles which describe the nature of
the project or the work encompassed on the plan; and
C.
All plans submitted for sub-division developments must bear the
stamp, seal and signature of a licensed Rhode Island Professional
Engineer responsible for the design.
Such plans and specifications shall be in conformance with applicable and
appropriate standards of the ASTM and WEF or other standards the Commission
may require or deem appropriate. Review by the Commission does not
constitute any form of guarantee or insurance with respect to performance of the
sewers or other wastewater facilities proposed. The Commission does not
assume responsibility for means, methods or techniques used, or for the safety of
construction work on the site or for compliance with applicable laws and
regulations other than those found herein.
4.11 Flow Monitoring/Impact Analysis
Persons seeking a building sewer connection permit who anticipate the flow into
the sewer from their proposed structure or dwelling to exceed 2,000 gallons per
day must demonstrate to the Commission through flow monitoring that the
Commission sewer line to which the person proposes to connect has the capacity
to accept the proposed additional flow.
4.12 Discharge From Swimming Pools
printed 11/94
21
The Commission shall be notified by the owner of the proposed discharge of
water from a swimming pool to a public sewer. The Commission shall have the
right to approve or deny the request, designate the time and rate of flow
permitted, and to enter upon the premises to inspect the project prior to and
during that operation. If an owner fails to provide such notification or
disregards instructions, whether accidentally or intentionally, the owner will be
held responsible for any damage that may be caused from such discharge subject
to the enforcement powers contained in these Rules and Regulations, and the
Commission shall not be held liable for said violation.
4.13 Stormwater Connections
No person(s) shall make direct or indirect connections or shed stormwater from
roof down spouts, foundation drains, areaway drains, or other sources of
stormwater which in turn are connected to any public sewer unless the
Commission determines that a combined sewer is the only reasonable means
available for disposal and such connection receives Commission approval. It
shall be the responsibility of the user to execute, and bear the cost of, any and all
studies and/or evaluations required by the Commission in this regard. In
making this determination, the Commission shall consider the following factors:
(Not in any order of priority)
A.
The present condition of areaway basin at the point of the proposed
storm connection;
B.
The potential impact of the proposed connection on the existing
downstream connection;
C.
The economic impact of the proposed connection on the
Commission and the applicant;
D.
The mitigating measures taken by the applicant to eliminate storm
flow from the project;
E.
The alternative options available to the applicant to discharge into
natural waterways; and
F.
Any measures taken by the applicant to separate present and future
flows from the project.
4.14 Grease Removal Systems
printed 11/94
22
Grease removal systems must be installed at all connections to the Commission's
facilities from users conducting food preparation or food processing operations
including, but not limited to, restaurants, nursing homes, schools, hospitals, or
other connections which discharge or have the potential to discharge quantities
of grease to the Commission's facilities in excess of allowable standards.
Installation of a grease removal systems shall be required when the Commission
determines that such discharge could result in obstruction to flow in the sewer or
accumulations of grease which could result in obstruction to flow in the sewer.
Grease removal systems must be installed according to the following
specifications:
A.
No wastewater, other than from kitchen fixtures or food processing
equipment, shall discharge into the grease removal system unless
approved by the Commission in writing.
B.
Any user required to install a grease removal system must install
either (1) an outdoor passive in-ground grease interceptor, or (2) and
automatic electrical/mechanical grease removal unit.
C.
In-ground grease removal systems shall have a minimum depth of
four (4) feet and a minimum capacity of five hundred (500) gallons,
and shall have sufficient capacity to provide at least twenty four (24)
hour detention period for the process flow. The minimum process flow
shall be based on fifteen (15) gallons per seat or chair per day or based
upon actual water usage for existing facilities.
D.
A suitable sampling location shall be provided for sampling of the
discharges from grease removal systems. Any plans for such grease
removal systems as required in this Section shall be submitted for
Commission review and approval prior to installation. The
Commission must be notified seventy-two (72) hours prior to
installation of any grease removal device in order to inspect and
oversee the installation. All automatic electrical/mechanical grease
removal systems must have a sampling valve installed on the
discharge piping with a minimum clearance of eight (8) inches for the
installation of sampling bottles.
E.
The owner(s) shall be responsible for cleaning and maintaining the
grease removal systems and shall maintain records of the dates of
cleaning and means of disposal, subject to review by the Commission.
Any removal and hauling of the collected materials not performed by
the owner(s) must be performed by licensed waste disposal firms.
printed 11/94
23
F.
All dishwasher wastewater from the pre-rinse station must discharge
to the grease removal device. All other dishwasher wastewater must
bypass the grease removal device and be discharged directly into the
sewer system.
G.
Garbage disposal units may only be installed in facilities with properly
sized and operational in-ground passive type grease interceptors
which have been properly designed for retention of settleable solids.
Garbage disposal units are prohibited in all other commercial or
industrial facilities. Garbage disposal waste shall not be discharged
into automatic electrical/mechanical type grease removal systems.
4.15 Connection Costs
All costs and expenses incidental to the installation and connection of the
building sewer shall be borne by the owner(s). The owner(s) shall indemnify and
hold harmless the Commission from any loss or damage that may result from the
installation of the building sewer.
4.16 Building Sewers
A separate and independent building sewer shall be provided for every building;
except where one building stands at the rear of another or on an interior lot and
no private sewer is available or can be constructed to the rear building through
an adjoining alley, court, yard, or driveway, then the building sewer from the
front building may be extended to the rear building and the whole may be
considered as one building sewer.
4.17 Existing Building Sewers
Existing building sewers may not be used for direct or indirect connections for a
new building unless a permit has first been granted in accordance with Sections
4.2 and 4.3 of this Article.
4.18 Building Sewer Construction
The size, slope, alignment, materials of construction of a building sewer, and the
methods to be used in excavating, placing the pipe, jointing, testing, and back
filling the trench, shall all conform to the requirements of applicable
governmental codes or other Rules and Regulations of the Commission. In the
absence of code provisions or in accordance with, the materials and procedures
printed 11/94
24
set forth in appropriate specifications of the ASTM and WEF Manual of Practice
No. 9 shall apply.
4.19 Building Sewer Elevation
If the elevation at which the building sewer enters the building is lower than the
elevation of the crown of the public sewer at the point of connection, at least one
check valve shall be installed in the building sewer or building drain in an
accessible location to prevent backflow. In all buildings in which any building
drain is too low to permit gravity flow to the public sewer, sanitary sewage
carried by such building drain shall be lifted to the public sewer by a pump and
a check valve shall be installed in an accessible location to prevent backflow.
Whenever a check valve has to be installed in accordance with the provisions of
this paragraph, it shall be installed and maintained at the owner's expense.
4.20 Disconnection
In the event that an owner desires to disconnect the building sewer connection
from the Commission's sewer, the owner shall not be permitted to remove that
portion of the service line between the Commission sewer and the property line,
but at the owner's expense the service line shall be capped at said property line,
and the service line shall be removed from the property line to the structure.
New service lines to replace existing service lines shall not be approved by the
Commission until old service lines are removed and properly capped. Such cap
shall be installed to prevent the escape of wastewater gases or groundwater.
4.21 Clean Outs
Clean outs shall be installed where the distance from the building to the main
sewer is greater than one hundred (100) feet or where bends greater than forty-
five (45) degrees are used in the building sewer. Clean outs shall be made by
installing a "Y" and one-eighth (1/8) bends of the same diameter as the building
sewer, or a maximum of 4 inches. The clean outs shall ordinarily be installed at
the point of connection between the building sewer and the outside part of the
house plumbing system at curves on the building sewer to the main sewer. The
clean out shall be brought up from the building sewer to four (4) inches below
ground level and be properly capped. Locations of all clean outs shall be
recorded and turned over to the Commission.
4.22 Safety Requirements
printed 11/94
25
All excavations for building sewer installation shall be adequately guarded with
barricades and lights so as to protect the public from hazard. Streets, sidewalks,
parkways, and other public property disturbed in the course of the work shall be
restored in a manner satisfactory to the Commission and the municipality.
4.23 Interference with Traffic Flow
No contractor shall block any driveway, street, road or railroad at any time
without the permission of any controlling agencies. Every effort shall be made to
permit the movement of vehicular traffic at all times. Whenever it becomes
necessary to cross or interfere with roads, walks, or drives, whether public or
private, the contractor shall maintain, at his or her expense, safe bridges or other
means of ingress and egress.
4.24 Notice to the Commission
After a permit has been issued, the Commission shall be given forty-eight (48)
hours notice before any construction or excavation work is begun on any direct
or indirect connection. All work shall be performed by a licensed plumber or
drain layer. If the Commission has not been properly notified, it may require the
completed work to be uncovered for examination, at the owner's expense. (See
Article 10)
4.25 Sewer Alterations (Permits)
Any person(s) planning to initiate road construction which will modify or expose
structures such as, but not limited to, manholes, catch basins, and service
connections owned by the Commission must obtain a sewer alteration permit
before performing any alterations to the Commission's facilities. Any person
desiring to apply for this permit shall obtain a form provided by the Commission
and shall submit, together with the permit fee, an application containing the
following information:
A.
Name, company name, address and phone number.
B.
Description of the project along with a sketch or map identifying
the location of the project and a drawing which indicates at least
two points of reference with distance measurements corresponding
to each structure or connection to be altered.
printed 11/94
26
C.
Method(s) which will be utilized to prevent debris from entering
NBC sewers.
printed 11/94
27
ARTICLE 5-DISCHARGE REQUIREMENTS, LIMITATIONS,
AND PROHIBITIONS
5.1 Authority
The Commission may limit, reject or prohibit any direct or indirect discharge of
pollutants or combination of pollutants, as defined by applicable Federal or state
law or as described below, into the facilities. The Commission may, in its
discretion, affix labels to those tanks which contain substances which are
prohibited from being discharged to the facilities or which may not be
discharged to the facilities without adequate pretreatment.
5.2 General Discharge Limitations
In addition to those limitations in paragraphs 5.3, 5.4 and 5.5 below, no person
shall discharge or cause or allow to be discharged directly or indirectly into the
facilities any other substances, water or wastewater that either singly or by
interaction with other substances will or is likely to:
A.
Interfere with the operation of the facilities by:
1) harming either the sewerage system or wastewater treatment
process;
2) being otherwise incompatible with the treatment process; or
3) contaminating the sludge or contributing to sludge disposal
problems; or
B.
Violate applicable Federal or State law, including Federal or State
hazardous waste regulations, or the terms of the facility's Federal
and State permits, including but not limited to, the Commission's
Rhode Island Pollution Discharge Elimination System (RIPDES)
Permits; or
C.
Endanger the environment by adversely affecting receiving waters
or otherwise; or
D.
Endanger the health or welfare of persons.
5.31 Specific Discharge Limitations:
printed 11/94
28
No person shall discharge or cause or allow to be discharged either directly or
indirectly into the facilities any substance, water, or wastewater which has:
A.
Heat in amounts which will inhibit biological activity in the
Commission's facilities resulting in Interference, but in no case heat
in such quantities that the temperature at the Commission's
Wastewater Treatment Plant exceeds 40 degrees Centigrade (104
degrees Fahrenheit).
B.
Pollutants which result in the presence of toxic gases, vapors, or
fumes within the Commission's facilities in a quantity that may
cause acute worker health and safety problems.
C.
Any water or waste which by itself or by interaction with other
materials, emits chemical contaminants into the atmosphere of any
confined area of the wastewater system at levels in excess of short
term exposure limit Threshold Limit Value (TLV-STEL) established
for air borne contaminants by the American Conference of
Governmental Industrial Hygienists (ACGIH) or the National
Institute for Occupational Safety and Health.
D.
Concentrations of BOD or TSS which exceed specific threshold
values without payment of a surcharge to cover the additional costs
of treatment as determined by rates set and approved by the Public
Utilities Commission. For the Field’s Point Treatment Facility the
current threshold value for BOD is 350 mg/l and for TSS is 350
mg/l. For the Bucklin Point Treatment Facility the current
threshold value for BOD is 378 mg/l and for TSS is 228 mg/l.
(Note: All values subject to change upon subsequent Public Utilities
Commission rate filings.) Payment of a surcharge does not prevent
the Commission from initiating any actions available under Section
5.8 below, when the Commission determines that the General
Discharge Limitations in Section 5.2 above are violated.
Furthermore, payment of a surcharge shall not constitute an
affirmative defense to any action taken pursuant to Section 5.8
below.
E.
Unusual concentrations of dissolved solids such as, but not limited
to, sodium sulfate.
printed 11/94
29
F.
A discharge effluent with a pH lower than 5.0 or higher than 10.0 or
having any other corrosive properties capable of causing damage
or hazard to facility equipment or structures or which may be
injurious to Commission personnel.
G.
Any radioactive wastes or isotopes of such half-life or
concentration as may exceed limits established by state or Federal
laws or regulations.
printed 11/94
30
H.
Color or turbidity in such an amount that it will prevent the
Commission from discharging a treated effluent in compliance with
any state or Federal rules, regulations or permit requirements.
I.
Petroleum oil, non-biodegradable cutting oils, waste oils, or
products of mineral oil origin in amounts greater than 25 mg/l .
J.
Fats, wax, grease, or oils of vegetable or animal origin as measured
by Freon extraction in excess of one hundred (100) mg/l or
containing other substances which may solidify or become viscous
at temperatures between 0 degrees Centigrade (32 degrees
Fahrenheit) and 40 degrees Centigrade (104 degrees Fahrenheit).
Waters or wastes containing such substances, excluding normal
household waste, shall exclude all visible floating oils, fats and
greases. The use of chemical or physical means (such as
temperature variation, emulsifying agents, mechanical mixers) to
bypass or release fats, oils and greases into the wastewater facilities
is prohibited.
K.
Total oil and grease of mineral, animal, vegetable and other origins
is not to exceed 125 mg/l.
L.
Any garbage that has not been properly shredded to at least
particles less than one half inch (1/2") in any dimension. Garbage
grinders may be connected to public sewers from homes, hotels,
institutions, restaurants, hospitals, catering establishments, or
similar places where garbage originates from the preparation of
food in kitchens for the purpose of consumption on the premises or
when served by caterers, providing that all requirements of Section
4.14 are satisfied. The installation and operation of any garbage
grinder equipped with a motor of three-fourths (3/4) horsepower
(0.76 hp metric) or greater shall be subject to the review and
approval of the Commission.
M.
Chlorine demand in such quantities as to constitute a significant
load on the wastewater facilities or which may cause the effluent
from the Commission’s wastewater treatment facilities to violate
any state or Federal rules, regulations or permit requirements,
including, but not limited to, National Pollutant Discharge
Elimination System (NPDES) and R.I. Pollutant Discharge
Elimination System (RIPDES) permits.
printed 11/94
31
5.32 Specific Facility Limitations:
No person shall discharge or cause or allow to be discharged either directly or
indirectly into the facilities, any substance, water or wastewater which has
concentrations of the substances listed below in excess of the assigned discharge
limitations. There will be no waivers or exceptions granted with respect to
compliance with any of the limits listed below.
* All Parameters are for total metals, organics and cyanide.
A. Field's Point Discharge Limitations:
Parameter*
Daily Maximum
(Composite Sample
for 1 day) (mg/l)
Average
(10 day)
(mg/l)
Cadmium (Cd)
0.11
0.07
Chromium (Cr)
2.77
1.71
Copper (Cu)
1.20
1.20
Cyanide (CN)
0.58
0.58
Lead (Pb)
0.60
0.40
Mercury (Hg)
0.005
0.005
Nickel (Ni)
1.62
1.62
pH
5.0 -10.0 std. units
Silver (Ag)
0.43
0.24
TTO
2.13
2.13
Zinc (Zn)
2.61
1.48
B. Bucklin Point Discharge Limitations:
Parameter*
Daily Maximum
Concentration
Limit (mg/l)
Monthly
Average
(mg/l)
Arsenic (As)
0.20
0.10
Cadmium (Cd)
0.11
0.07
Chromium (Cr)
2.77
1.63
Copper (Cu)
1.20
1.20
Cyanide (CN)
0.50
0.50
Lead (Pb)
0.69
0.29
Mercury (Hg)
0.06
0.03
Nickel (Ni)
1.62
1.62
pH
5.5-9.5 std. units
Selenium (Se)
0.40
0.20
Silver (Ag)
0.40
0.20
Tin (Sn)
4.00
2.00
TTO
2.13
2.13
Zinc (Zn)
1.67
1.39
printed 11/94
32
5.4 General Discharge Prohibitions:
No person shall discharge or cause or allow to be discharged either directly or
indirectly into the Commission's facilities, any substance, water or wastewater
which may cause Pass Through or Interference.
5.5 Specific Discharge Prohibitions:
Certain substances are specifically prohibited from being discharged into the
Commission's facilities. These prohibited substances include, but are not limited
to, the following:
A.
Groundwater, stormwater, and surface waters, roof runoff,
tidewater, subsurface drainage, noncontact cooling water, and
uncontaminated industrial process waters, unless approved by the
Commission. (See Article 4)
B.
Slugs as defined in Article 2.
C.
Sludge or deposited solids of any type including those generated
from an industrial or commercial pretreatment process (e.g.,
hydroxide or degreaser sludge).
D.
Concentrated discharges as defined in Article 2.
E.
Batch discharges as defined in Article 2 unless prior written
approval is granted from the Commission.
F.
Any material identified as hazardous waste according to 40 CFR
Part 261 except as may be specifically authorized by the
Commission.
G.
Any wastewater having a lethal concentration of fifty percent
(LC50) as determined by a toxicity test of 96 hours or less using
100% of the industrial user's discharge and aquatic test species
chosen by the Commission.
H.
Gasoline, benzene, naphtha, fuel oil, or other flammable or
explosive liquids, solids, or gases.
I.
Any substances which by reason of their nature or quantity may
create a fire or explosion hazard in the Commission's facilities or be
printed 11/94
33
injurious to Commission personnel or to the operation of the
Commission's facilities including, but not limited to, waste streams
with a closed cup flash point of less than 60 degrees Centigrade
(140 degrees Fahrenheit) using the test methods specified in 40 CFR
261.21.
J.
Any solid or viscous pollutants in amounts which may cause
obstruction to the flow in a sewer or may result in Interference with
the operation of the waste treatment facilities such as, but not
limited to: grease, garbage with particles greater than one-half inch
(1/2") in any dimension, or any material which can be disposed of
as trash, ashes, bones, cinders, sand, mud, straw, shavings, metal,
glass, rags, feathers, tar, plastics, wood, underground garbage,
whole blood, hair and fleshings, entrails, paper dishes, cups, milk
containers, lime slurries, and grease from deep-frying operations.
K.
Any trucked or hauled pollutants except at discharge points
designated by the Commission.
L.
Black boils, pickling solutions, acids etches, acid activators, and
Brite dip acids.
M.
Solvents
including,
but
not
limited
to,
trichloroethylene,
trichloroethane, xylene, Freon, paint thinners and strippers.
N.
Cyanide, acid, or solvent-based stripping solutions.
O.
Concentrated plating baths or solutions.
P.
Waste oils.
Q.
Isolation Wastes or Regulated Medical Waste (See definitions under
Article 2).
R.
Any substance which may cause a public nuisance, cause hazard to
life or prevent entry into the sewers for maintenance or repair.
5.6 Federal Categorical Pretreatment Standards
Users subject to categorical pretreatment standards are required to comply with
applicable standards as set out in 40 CFR Chapter I, Subchapter N, as amended.
printed 11/94
34
5.7 Dilution Prohibition
No user shall, by increasing the use of wastewater or water, in any way, attempt
to dilute a discharge as a partial or complete substitute for adequate treatment to
achieve compliance with the limitations contained in the Federal Categorical
Pretreatment Standards, 40 CFR, or in any other pollutant specific limitation
developed by the Commission. The Commission shall, in its sole discretion, use
EPA formulas or any other reasonable method for determining discharge levels
where dilution is reasonably suspected.
5.8 Remedies
If any wastewater is discharged or is proposed to be discharged to the
wastewater facilities in violation of the limitations or prohibitions described in
Article 5, the Commission may in its sole discretion:
A.
Reject the wastes;
B.
Require a discharger to demonstrate and implement those in-plant
modifications which will reduce or eliminate the discharge of such
substances to conform with these Rules and Regulations;
C.
Require
pretreatment,
including
storage
facilities
or
flow
equalization necessary to reduce or eliminate the objectionable
characteristics or substances, so that the discharge will not violate
these Rules and Regulations;
D.
Require controls to be installed which will regulate the quantities
and rates of discharge;
E.
Require surcharge payments to be made to the Commission to
cover its added cost of handling, monitoring, and treating the
wastes which exceed threshold values in accordance with rates set
and approved by the Public Utilities Commission;
F.
Revoke a discharger's permit; and
G.
Take any other administrative sanctions, enforcement actions, and
remedial actions as may be desirable, necessary, or permitted to
achieve the purpose of these Rules and Regulations.
printed 11/94
35
ARTICLE 6-INTERFERENCE WITH COMMISSION PROPERTY
No person shall maliciously, willfully, or negligently break, damage, destroy,
uncover, deface, or tamper with any Commission owned structure, appurtenance
or equipment. No person shall dump garbage, fill, refuse, or other materials on
land easements, rights-of-way, or other structures, including manholes, which
are part of the wastewater facilities. Persons initiating construction activities that
may alter Commission structures must be permitted pursuant to the
requirements outlined in Article 4 above. Persons causing such Interference shall
be billed by the Commission for any actual damages, the cost of correcting the
Interference and may be subject to civil and/or criminal penalties pursuant to
R.I.G.L §46-25-25.2, and Article 10.
printed 11/94
36
ARTICLE 7-INSPECTION POWERS
7.1 General Powers
Inspections shall be conducted at the discretion of the Commission. Duly
authorized employees and agents of the Commission, upon presenting
identification and appropriate credentials, are authorized:
A.
To enter without delay and at reasonable times those premises
(public or private) of any person or class of user either receiving
services from the Commission or applying for services from the
Commission in which a discharge source or treatment system is
located or which records required to be maintained pursuant to
R.I.G.L.§46-25-25 are kept;
B.
During regular working hours and at other reasonable times, and
within reasonable limits and in a reasonable manner, to have access
to and to copy any records, inspect any monitoring equipment or
method required pursuant to R.I.G.L.§46-25-25 and sample and/or
analyze any effluents which the owner or operator of such
discharge source is required to sample and/or analyze under
R.I.G.L.§46-25-25 and any rules and regulations adopted pursuant
thereto; and
C.
During such on site inspections, to carry out all inspections,
surveillance, and monitoring procedures necessary to determine,
independent of information supplied by any person discharging
into the facilities, compliance or noncompliance with Commission
pretreatment requirements.
7.2 User Documentation
The Commission may, by regulation, order, permit, or otherwise, require any
person who discharges into the facilities to:
A.
establish and maintain records;
B.
make reports;
printed 11/94
37
C.
install, calibrate, use and maintain monitoring equipment or
methods (including where appropriate, biological monitoring
methods);
D.
sample and/or analyze discharges and effluents (in accordance
with the method, at the locations, at the intervals, and in the
manner as the Commission shall prescribe); and/or
E.
provide other information relating to discharges into the facilities of
the project as the Commission may reasonably require to ensure
compliance with prescribed pretreatment. Such information shall
include, but not be limited to, those records, reports and
procedures required by applicable State and Federal law.
printed 11/94
38
ARTICLE 8-WASTEWATER DISCHARGE PERMIT SYSTEM
8.1 Wastewater Discharge Permits Required
A.
Existing Sources:
All users connected to the Commission's wastewater facilities must
obtain a wastewater discharge permit. All users proposing to
connect to or discharge into any part of the Commission's
wastewater facilities must obtain a wastewater discharge permit
before connecting to or discharging to the facilities.
B.
New Sources:
New sources must obtain a wastewater discharge permit before
connecting to or discharging to the facilities. The user must be in
compliance with effluent limitations upon start-up of operation.
Any required pretreatment must be installed and operational in
accordance with plans and approved by the Commission. The
pretreatment system shall be inspected and approved by
Commission personnel before a wastewater discharge permit will
be issued.
8.2 Compliance Required
No permit holder shall discharge industrial wastewater in excess of the quantity,
rate of discharge, concentrations or any other limits specified in the permit. Any
person desiring to modify his or her permit must first apply for an amended
permit.
8.3 Expedited Permit Process
Application for an expedited permit must be made in accordance with the
Expedited Permit Process, R.I.G.L.§42-117-1 et seq. which requires that the
potential permittee file a Certificate of Critical Economic Concern at the time of
filing any necessary permit application with the Commission. Upon receipt of
said Certificate and in accordance with said Act, the Commission shall give
priority to the handling and processing of the permittee's application.
8.4 Wastewater Discharge Permit Application
Industrial users seeking a wastewater discharge permit must have completed
and filed with the Commission an application on the prescribed form, together
printed 11/94
39
with any applicable fee. In support of this application, the user shall submit the
following information:
A.
Name, business address, name of owner or business, name of
building owner, location of the facility (if different from business
address) and Standard Industrial Classification (SIC) number of the
applicant;
B.
Total water consumption from all sources and supporting
documentation when appropriate;
C.
Type, frequency, volume of discharge, and amount of raw
materials processed (average and maximum per day);
D.
Average daily and 30 minute peak wastewater flow rates, including
daily, monthly, and seasonal variations, if any;
E.
Site
plan,
floor
plans,
mechanical
and
plumbing
plans,
pretreatment plans and details to show all building connections
and appurtenance by size, location and elevation;
F.
Description of activities, pretreatment facilities and plant processes
conducted on the premises including all materials and types of
material which could be discharged;
G.
Type of product produced;
H.
Number of employees, number of shifts, and hours of work;
I.
The name and concentration of any pollutants in the discharge, for
a minimum of four consecutive operating days, as required under
Article 9, which are regulated by the Commission, the state, or the
Federal government; and a written statement as to whether or not
applicable pretreatment standards are being met, and if not,
whether
additional
in-plant
modification
and
additional
pretreatment is required for the user to meet such applicable
pretreatment standards;
J.
If additional pretreatment or in-plant modification will be required
to meet the pretreatment standards, the user will provide a
schedule by which to achieve the standards in the shortest possible
time. This schedule will be reported as the Pretreatment
printed 11/94
40
Compliance Schedule. The following conditions shall apply to this
schedule:
1) The schedule shall contain increments of progress in the form of
dates for the commencement and completion of major events
leading to the construction and operation of additional
pretreatment required for the user to meet the applicable
pretreatment standards (e.g. hiring an engineer, completing
preliminary plans, executing contracts for major components,
commencing
construction,
completing
construction).
No
increment shall exceed nine (9) months.
2) Not later than 14 days following each completion date in the
schedule, the user shall submit a progress report to the
Commission including at a minimum, whether or not, he or she
complied with the increments of progress. If such increment of
progress was not completed on time, the user shall also report
the date on which he or she expects to complete the increment
of progress, the reason for the delay, and the steps being taken
by the user to return to the schedule established. In no event
shall completion dates be more than 9 months apart;
K.
Signatory requirements; and
L.
Any other pertinent information as may be needed to evaluate the
permit application.
The Commission shall evaluate the data furnished by the user and may require
additional information. Based on the application, the Executive Director may
issue a wastewater discharge permit subject to the terms and conditions
enumerated in the permit. A fact sheet explaining the basis of the permit shall be
on file at the Pretreatment Office for inspection upon request.
The Executive Director may deny a request for a permit when the information
supplied indicates the user will be unable to reasonably meet the Commission's
standards. Any person denied a permit may request a hearing in accordance
with the provisions of Article 10.
8.5 Permit Conditions
Wastewater discharge permits shall be expressly subject to specific permit
provisions contained therein as well as to provisions of these Rules and
printed 11/94
41
Regulations and all other regulations, user charges and fees established by the
Commission. Wastewater discharge permits may include such conditions as are
reasonably deemed necessary by the Commission to prevent Pass Through or
Interference, protect the quality of the water body receiving the treatment plant's
effluent, protect worker health and safety, facilitate sludge management and
disposal, protect ambient air quality, and protect against damage to the
Commission's facilities. Such conditions may include, but are not limited to, the
following:
A.
The
average
and
maximum
wastewater
constituents
and
characteristics permitted in the process water discharges;
B.
Limits on rate and time of discharge or requirements for flow
regulation and equalization;
C.
Requirements for installation of inspection and sampling facilities
and specifications for self-monitoring;
D.
Requirements for the submission of periodic self-monitoring
compliance reports which shall include, but not be limited to,
volume or rates of flow, concentrations of controlled pollutants or
other information which relates to the generation of waste;
E.
Requirements for maintaining and submitting technical reports and
plant records relating to wastewater discharges;
F.
Daily average and daily maximum discharge rates, or other
appropriate conditions when pollutants subject to limitations and
prohibitions are proposed or present in the user's wastewater
discharge permit;
G.
Compliance schedules;
H.
Requirements for installation of pretreatment systems, spill and
slug-prevention control plans and solvent-management plans;
I.
Provisions for authorized Commission employees and agents to
enter and inspect the premises, including provisions for copying
records, inspecting monitoring equipment and sampling effluent;
J.
Compliance with Federal, state and other governmental laws, rules
and regulations;
printed 11/94
42
K.
Fees and costs including supplemental fees assessed because of the
special nature of the user's effluent in accordance with the
provisions of Article 5 and additional costs and fees based on the
costs of enforcing these regulations or the permit, as in accordance
with R.I.G.L. §46-25-5 (j);
L.
Signatory requirements; and
M.
Any other reasonable conditions necessary to ensure compliance
with the provisions of R.I.G.L.§46-25-1 et seq., or any state and
Federal laws, rules and regulations.
8.6 General Pretreatment Requirements:
Users shall provide wastewater treatment as required to comply with these Rules
and Regulations, and shall achieve compliance with all Federal, state, and
Commission pretreatment standards within the time limitations specified by the
Federal, State, and Commission pretreatment regulations. Any equipment or
systems required to pretreat wastewater to a level acceptable to the Commission
shall be provided, operated and maintained at the user's expense. The user is
responsible for following all equipment instructions provided by the
manufacturer. Detailed plans showing the pretreatment equipment, systems and
operating procedures shall be submitted to the Commission for review and shall
be acceptable to the Commission prior to construction and operation of the
facilities. The design of industrial process wastewater treatment systems must be
executed in accordance with the general laws of the State of Rhode Island (1956,
as amended) Title 5, Chapter 8. The following paragraphs set out the minimum
requirements for pretreatment and water using process plans. The Commission
may require additional documentation and/or detail of plans whenever it
determines that such information is necessary to evaluate the pretreatment
system or process operations.
Any review and inspection conducted by the Commission is for the sole purpose
of determining compliance with the technical provisions of these Regulations.
The Commission does not assume responsibility for means, methods or
techniques used, or for the safety of construction work, the site, or for
compliance by users with applicable laws and regulations other than this
Regulation.
Review by the Commission does not constitute any form of guarantee or
insurance with respect to the performance of the equipment and processes. The
review of such plans and operating procedures will in no way relieve the user
from the responsibility of modifying the equipment as necessary to produce an
effluent acceptable to the Commission under the provisions of this section. Any
printed 11/94
43
subsequent significant changes in the pretreatment equipment or method of
operation shall be reported to and be acceptable to the Commission prior to the
user's initiation of the changes.
A.
Pretreatment Plans:
The plans of pretreatment systems and process operations must be of
professional quality. The Commission may require that said plans be
stamped by a Professional Engineer registered in the state of Rhode
Island. The Commission may require that said plans/drawings include,
but not be limited to, the following:
1)
All treatment tanks, their size, material of construction, and
the projected daily flow(s) to each treatment tank;
2)
All pumps, piping, valves, mixers, controls, probes, etc.;
3)
A description of the treatment procedure for each treatment
process;
4)
A process schematic of the pretreatment system;
5)
A plant layout showing the pretreatment system, water using
process tanks and location of each tank in the facility;
6)
All sumps, pumps or effluent transfer stations;
7)
The wastewater sampling location;
8)
Side view or elevation drawings of all interconnected
pretreatment tanks showing inlet and outlet connections; and
9)
An original stamp and signature of a registered and licensed
Rhode Island Professional Engineer.
B.
Water Using Process Plans:
The Commission may require that water using process plans/drawings
include, but not be limited to, the following:
1)
All tanks, their contents and volume;
2)
Identification and quantification of the wastewater discharge
from each process tank or process operation, including:
a) continuous discharges - flowrate (gpm or gpd)
b) batch discharges - volume and frequency;
3)
Where the tank discharges (if the discharge is to pretreatment,
the specific pretreatment tank must be indicated);
4)
All floor drains, trenches and sumps, including their point of
discharge and discharge destination;
5)
The location of all sewer connections;
6)
Original stamp and signature of a registered and licensed
Rhode Island Professional Engineer.
printed 11/94
44
All process tanks with a batch or continuous discharge must be hard piped to the
point of discharge.
8.7 Installation of Zero Discharge Pretreatment Systems
Prior to installation of a Zero Discharge Pretreatment System, the user must
submit a Zero Discharge Pretreatment System design plan for Commission
acceptance. Said plan must be executed in accordance with the R.I.G.L.§5-8-1 et
seq. In order to obtain Commission acceptance, the user must demonstrate that
he or she will provide full pretreatment of all wastewater and will cease to
discharge process wastewater to the facilities by an effective date prescribed by
the Commission, and the user must obtain a Zero Discharge permit from the
Commission.
The Zero Discharge permit may require, among other things, that:
A.
The zero discharge system be installed as proposed and be fully
operational;
B.
All sewer drain lines in the facility to be capped off and sealed;
C.
The user notify the Commission in writing, and obtain a revised
Wastewater Discharge Permit from the Commission before
resuming discharge if he/she wishes to re-connect to the sewer;
and/or
D.
Commission personnel be authorized to enter such premises
without delay and at reasonable times for the purpose of inspection
and as otherwise authorized under R.I.G.L.§46-25-25.1.
8.8 Compliance Certification
Any user who discharges or proposes to discharge process wastewater into the
Commission's facilities without pretreatment shall submit a certification to the
Commission stating that all discharge limitations will be met, and explaining in
detail how discharge limitations will be met without pretreatment. Such
certification must be prepared, certified, and stamped by a registered Rhode
Island Professional Engineer.
8.9 Spill and Slug Prevention Control and Countermeasures Plan
A.
Users that store hazardous substances shall not contribute to the
Commission's facilities after the effective date of this ordinance
unless a spill prevention plan has been approved by the
printed 11/94
45
Commission. Approval of such plans shall not relieve the user from
complying with all other laws and regulations governing the use,
storage, and transportation of hazardous substances.
1)
The Commission may evaluate each significant user at least
once every two years, and other users as necessary, to
determine whether such user needs a plan to control slug
discharges. If the Commission decides that a slug control
plan is needed, the plan shall contain, at a minimum, the
following elements:
a)
Description of discharge practices, including non-
routine batch discharges;
b)
Description of stored chemicals;
c)
Procedures for immediately notifying the Commission
of slug discharges, including any discharge that would
violate a prohibition under Section 5.4 or 5.5, with
procedures for follow up written notification within
five days;
d)
If necessary, procedures to prevent adverse impact
from accidental spills, including inspection and
maintenance of storage areas, handling and transfer of
materials, loading and unloading operations, control of
plant site run-off, worker training, building of
containment structures or equipment, measures for
containing toxic organic pollutants (including solvents),
and/or measures and equipment for emergency
response.
B.
Each user shall provide protection from accidental discharge of
prohibited materials or other substances regulated by these Rules
and Regulations which may interfere with the Commission's
facilities by developing spill prevention plans. Equipment
necessary to implement these plans shall be provided and
maintained at the owner's or user's own cost and expense. Detailed
plans showing equipment and operating procedures to provide this
protection shall be submitted to the Commission for review, and
shall be approved by the Commission before construction. It is
understood that any review and inspection conducted by the
Commission is for the sole purpose of determining compliance
with the technical provisions of these Regulations. Review by the
printed 11/94
46
Commission does not constitute any form of guarantee or
insurance with respect to the performance of the equipment and
processes.
All existing users shall also complete such a plan as required by a
compliance schedule or permit. No new user proposing to
discharge into the facilities shall be permitted to introduce
pollutants into the facilities until accidental discharge procedures
have been approved by the Commission. Review and approval of
such plans and operating procedures shall not relieve the user from
the responsibility of modifying the user's equipment as necessary
to meet the requirements of these Rules and Regulations.
printed 11/94
47
8.10 Duration of Permits/Reissuance of Permits
Permits shall be issued for a specified time period, not to exceed five years. A
permit may be issued for a period of less than one year, or may be stated to
expire on a specific date. The user shall apply for permit reissuance at least one
hundred and eighty (180) days prior to the expiration of the user's existing
permit.
8.11 Modification of Permits
A user may apply for modification of a discharge permit by filing a new
application form showing substantial, significant and material changes that have
been proposed since filing the original application. No application for
modification will be considered unless it demonstrates such changes.
After review of the application and inspection of the facility, the Commission
may, at its discretion, modify the original permit. If such application is rejected,
the existing permit shall remain in full force and effect.
The terms and conditions of the permit may be subject to modification and
changed by the Commission during the life of the permit. The Commission may,
in its sole discretion, place further restrictions, limitations and conditions in a
permit to carry out the provisions of R.I.G.L.§46-25-1 et seq. The user shall be
informed of any proposed changes in his or her permit at least thirty (30) days
prior to the effective date of change. Any changes or new conditions in the
permit shall include a hearing on modifications to his or her permit in
accordance with the provisions of Article 10.
8.12 Transfer of Permits
Wastewater discharge permits may be reassigned or transferred to a new owner
and/or operator only if the permittee gives at least ninety (90) days advance
notice to the Commission and the Commission approves the wastewater
discharge permit transfer. The notice to the Commission must include a written
certification by the new owner and/or operator which:
A.
States that the new owner and/or operator has no immediate intent
to change the facility's operations and processes.
B.
Identifies the specific date on which the transfer is to occur.
C.
Acknowledges full responsibility for complying with the existing
wastewater discharge permit.
printed 11/94
48
Failure to provide advance notice of a transfer renders the wastewater discharge
permit void on the date of facility transfer.
8.13 Wastewater Discharge Permit Revocation
Wastewater discharge permits may be revoked for the following reasons:
A.
Failure to notify the Commission of significant changes in the
quantity
and
quality
of
wastewater
discharged
prior
to
implementing such changes.
B.
Misrepresentation or failure to fully disclose all relevant facts in the
wastewater discharge permit application.
C.
Falsifying self-monitoring reports.
D.
Tampering with monitoring equipment.
E.
Refusing to allow the Commission timely access to the facility
premises and records.
F.
Failure to meet effluent limitations.
G.
Failure to pay fines.
H.
Failure to pay user fees.
I.
Failure to meet compliance schedules.
J.
Failure to complete a wastewater survey or the wastewater
discharge permit application.
K.
Failure to provide advance notice of the transfer of a permitted
facility.
L.
Violation of any pretreatment standard or requirement, or any
terms of the wastewater discharge permit or the ordinance.
Wastewater discharge permits shall be voidable upon non-use, cessation of
operations, or transfer of business ownership. All wastewater discharge permits
are voidable upon the issuance of a new wastewater discharge permit.
printed 11/94
49
printed 11/94
50
8.14 Suspension of Permit
The Executive Director may suspend the wastewater discharge permit of any
user who ceases operations for any period exceeding one (1) month. The
suspension will not act as a revocation of the permit, but rather as a temporary
suspension of the user's rights under the permit while operations have ceased.
During such suspension, the user's connection to the facilities shall be plugged.
The user shall still be required to pay the permit fee, since the permit itself will
not be revoked. During such suspension, the user shall be disconnected from
the facility. The Commission shall have the authority to make periodic
inspections during this time to determine whether the user is continuing to
discharge regulated wastewater. Such discharge may be considered grounds for
revocation of the wastewater discharge permit.
The user shall give Commission personnel written notice five (5) working days
prior to reactivating operations. The user shall not reactivate operations until
after receiving written approval from the Commission following a Commission
inspection.
8.15 Reinstatement of Permit
Before any further discharge of industrial wastewater may be made by a user
whose permit has been revoked, the user must apply for, and be granted, a
reinstatement of the terminated permit, or a new permit, as the Executive
Director may require, and pay any delinquent fees and all fines, charges, and
other costs occasioned by the violation. Costs shall include, but not be limited to:
inspection, monitoring, sampling and related expenses; restitution to other
affected parties; reasonable attorney's fees incurred by the Commission in
enforcing the permit; disconnecting and reconnecting the user to the facility; and
other actual damages incurred due to the violation. Any such fines, fees, charges
and costs shall be paid for by the user before any new permit will be issued.
When all costs cannot be readily determined the Commission may require and
accept a bond or irrevocable letter of credit which it considers sufficient and
which will be subject to appropriate adjustment after all costs have been
determined.
printed 11/94
51
ARTICLE 9-WASTEWATER MONITORING AND REPORTING
9.1 Records and Monitoring
A.
All users who discharge or propose to discharge wastewater
directly or indirectly to the facilities shall maintain records which
substantiate any information supplied in permit applications. Such
records shall include, but not be limited to, pH tapes, chemical
usage data, log sheets, hazardous waste manifests, water meter
readings, effluent monitoring reports, self-monitoring compliance
reports and any other informational requirements of these Rules
and Regulations or required by a user's Wastewater Discharge
Permit or any applicable state and Federal laws and regulations.
These records are to be kept for a period of three (3) years unless
there is pending a dispute of litigation involving the subject of
these records, in which case these records are to be kept for a
period of three (3) years following resolution of such litigation or
dispute.
B.
Access to Information/Confidential Information
1)
All such records described in Section 9.1 (A) above shall be
available in accordance with R.I.G.L.§46-25-25.1 upon request,
to the Commission.
2)
Information and data (other than effluent data) about a user
obtained from reports, questionnaires, permit applications,
permits and monitoring programs and from inspections shall
be available to the public unless the user specifically requests
and is able to demonstrate to the satisfaction of the
Commission that the release of such information would
divulge processes or methods of production entitled to
protection as trade secrets of the user. Any such request must
be asserted at the time of submission of the information or
data. When such a confidentiality claim is asserted, the
information shall be treated as such until a determination is
made by the Commission. Effluent data shall be available to
the public without restriction.
3)
If the Commission determines that the information is entitled
to protection as a trade secret, the portions of a report which
might disclose trade secrets or secret processes shall not be
made available for inspection except by the State or EPA for
uses related to this ordinance, the permit or the pretreatment
printed 11/94
52
program. Confidential portions of a report shall be available
for use by the state or EPA in judicial review or enforcement
proceedings involving the person furnishing the report.
Effluent data will not be recognized as confidential
information.
C.
The Commission may require a user to install, at his or her own
cost, suitable monitoring or metering equipment to facilitate the
accurate
observation,
sampling,
and
measurement
of
the
wastewater discharge. Such equipment shall be maintained in
proper working order by the user and shall be kept safe and
accessible at all times. The monitoring and metering equipment
shall be located and maintained on the user's premises. When such
a location would be impractical or cause undue hardship to the
user, the Commission may allow such facility to be constructed in
the public street or sidewalk area, with the approval of the public
agency having jurisdiction over such street or sidewalk, and located
so the discharge will not be obstructed by public utilities,
landscaping or parked vehicles.
D.
When more than one user discharges into a common sewer, the
Commission may require installation of separate monitoring and
metering equipment for each user. When there is a significant
difference in wastewater constituents and characteristics produced
by different operations of a single user, the Commission may
require that separate monitoring and metering facilities be installed
for each separate discharge.
E.
Whether constructed on public or private property, the monitoring
facilities shall be constructed in accordance with these Rules and
Regulations and any applicable construction standards required by
the Commission or by local, state or Federal law.
9.2 Inspection and Sampling
The Commission shall have the right to enter the facilities of any user to ascertain
whether the purpose of these Rules and Regulations are being met and all
requirements are being complied with. Users shall allow the Commission ready
access to all parts of the premises for the purposes of inspection, sampling,
records examination and copying, and the performance of any additional duties.
A.
Where a user has security measures in force which require proper
identification and clearance before entry into their premises, the
printed 11/94
53
user shall make necessary arrangements with its security guards so
that, upon presentation of suitable identification, personnel from
the Commission, state, and/or United States EPA (U.S. EPA) will
be permitted to enter, without delay, for the purposes of
performing their specific responsibilities.
B.
The Commission, state and U.S. EPA shall have the right to set up
or require installation of, on the user's property, such devices as are
necessary to conduct sampling and/or metering of the user's
operations.
C.
The Commission may require the user to install monitoring
equipment, as necessary. The facility's sampling and monitoring
equipment shall be maintained at all times in a safe and proper
operating condition by the user at the user's expense. All devices
used to measure wastewater flow and quality shall be calibrated
periodically to ensure their accuracy.
D.
Safe and easy access must be provided for Commission personnel.
Any temporary or permanent obstruction to safe and easy access in
and around the facility to be inspected and/or sampled shall be
promptly removed and/or repaired by the user at the written or
verbal request of the Commission. The costs associated with said
removal and/or repair shall be borne by the user.
E.
Unreasonable delays in allowing Commission personnel access to
the user's premises shall be a violation of these Rules and
Regulations.
9.3 Monitoring And Analysis of Process Wastewater
Sampling and analysis of industrial wastewater for the purpose of compliance
determinations with respect to Article 5 prohibitions and limitations shall be
done through industry self-monitoring and through monitoring done by the
Commission. All analyses, including sampling results submitted in support of
any application reports, evidence or required by any permit or order shall be
performed in accordance with the techniques prescribed in 40 CFR Part 136 and
amendments thereto or, if 40 CFR Part 136 does not contain sampling or
analytical techniques for the pollutant in question, in accordance with
procedures approved by EPA. The Commission may, at its discretion, require an
independent laboratory to conduct the sampling and analysis at the user's own
cost.
printed 11/94
54
A.
Self-Monitoring Requirements:
1)
Self-monitoring results must be accompanied by a certified
laboratory analysis sheet, indicating the EPA approved test
procedure for each parameter analyzed. The user must also
submit a self-monitoring report with the results on a form
prescribed by the Commission.
2)
All Self-Monitoring Reports must be signed and certified in
accordance with Section 9.10 below.
3)
If any sampling performed by a user indicates any
violation(s) of discharge limitations, the user shall notify the
Commission within twenty-four (24) hours of becoming
aware of the violation(s). The user shall repeat the analysis
immediately for the parameters determined to be in
violation and submit the resampling results to the
Commission within thirty (30) days after becoming aware of
the violation(s).
B.
Sample Collection:
1)
Except as indicated in (3) below, wastewater samples collected
for
purposes
of
determining
user
compliance
with
pretreatment standards and requirements must be obtained
using
flow
proportional
composite
sample
collection
techniques. In the event that flow proportional sampling is
not feasible, the Commission may authorize the use of a time
proportional sampling.
2)
For automatic samplers, the intake line hose must be at least
1/4 in. (0.6 cm) internal diameter and the velocity in the intake
line must be maintained at least at 2 feet per second.
3)
Samples for oil and grease, temperature, pH, cyanide, phenols,
toxicity, sulfides, and volatile organic chemicals must be
obtained using a grab sample.
C.
Analysis of Wastewater Samples:
1)
Laboratory analysis and sample preservation of industrial
wastewater samples for user self-monitoring and compliance
monitoring by the Commission shall be performed in
accordance with EPA approved methods. Where applicable,
the laboratory must be certified by the state in which it is
located.
9.4 Baseline Monitoring Report
printed 11/94
55
Within one hundred and eighty (180) days after the effective date of a categorical
pretreatment standard, or the final administrative decision on a category
determination under 40 CFR 403.6(a)(4), whichever is later, existing significant
industrial users subject to such categorical pretreatment standards, and currently
discharging to or scheduled to discharge to the Commission's facilities shall be
required to submit to the Commission a report which contains the information
listed below. At least ninety (90) days prior to commencement of their discharge,
new sources, sources that become users subsequent to the promulgation of an
applicable categorical standard including existing users who have changed their
operation or processes so as to become new sources, shall be required to submit
to the Commission a report which contains the information listed below. A new
source shall also be required to report the method of pretreatment it intends to
use to meet applicable pretreatment standards, estimates of its anticipated flow
and estimates of the quantity of pollutants to be discharged.
The information required by this section includes:
1)
Identifying Information:
The name and address of the facility including the name of the
operator and owners;
2)
Wastewater Discharge Permits:
A list of any environmental control wastewater discharge permits
held by or for the facility;
3)
Description of Operations:
A brief description of the nature, average rate of production, and
standard industrial classifications of the operation(s) carried out by
such user. This description should include a schematic process
diagram which indicates points of discharge to the Commission's
sewer system from the regulated processes;
4)
Flow Measurement:
Information showing the measured average daily and maximum
daily flow, in gallons per day, to the Commission's sewer system
from regulated process streams and other streams as necessary to
allow use of the combined waste stream formula set out in 40 CFR
403.6(e);
5)
Measurements of Pollutants:
a)
Identify the categorical pretreatment standards applicable to
each regulated process;
printed 11/94
56
b)
Submit the results of sampling and analysis identifying the
nature and concentration (and/or mass, where required by the
standard or Commission) of regulated process. Instantaneous
daily maximum and long term average concentrations (or mass,
where required) shall be reported. The sample shall be
representative of daily operations and shall be performed in
accordance with procedures set out in 40 CFR Part 136;
6)
Certification:
A statement reviewed by an authorized representative of the user
and certified by a qualified professional, indicating whether
pretreatment standards are being met on a consistent basis, and if
not, whether additional operation and maintenance and/or
additional pretreatment is required in order to meet the pretreatment
standards and requirements;
7)
Compliance Schedule:
If additional pretreatment and/or operations and maintenance will
be required to meet the pretreatment standards; the shortest schedule
by which the user will provide such additional pretreatment and/or
operations and maintenance shall be applied. The completion date in
this schedule shall not be later than the compliance date established
for the applicable pretreatment standard; and
8)
Signatory Certification
All baseline monitoring reports must be signed and certified in
accordance with Section 9.10 below.
9.5 Compliance Schedule Progress Report
The following conditions shall apply to the schedule required by Section 9.4 (7)
above. The schedule shall contain progress increments in the form of dates for
the commencement and completion of major events leading to the construction
and operation of additional pretreatment required for the user to meet the
applicable pretreatment standards (such events include hiring an engineer,
completing preliminary and final plans, executing contracts for major
components, commencing and completing construction, beginning and
conducting routine operation). No increment referred to above shall exceed nine
(9) months. The user shall submit a progress report to the Commission no later
than fourteen (14) days following each date in the schedule and the final date of
compliance including, as a minimum, whether or not it complied with the
increment of progress, the reason for any delay, and, if appropriate, the steps
being taken by the user to return to the established schedule. In no event shall
printed 11/94
57
more than nine (9) months elapse between such progress reports to the
Commission.
9.6 Report on Compliance with Categorical Pretreatment Standard Deadline
Within ninety (90) days following the date for final compliance with applicable
categorical pretreatment standards, or in the case of a new source following
commencement of the introduction of wastewater into the Commission's
facilities, any user subject to such pretreatment standards and requirements shall
submit to the Commission a report containing the information described in
Section 9.4 above. For users subject to equivalent mass or concentration limits
established in accordance with the procedures in 40 CFR 403.6(c), this report
shall contain a reasonable measure of the users long term production rate. For all
other users subject to categorical pretreatment standards expressed in terms of
allowable pollutant discharge per unit of production (or other measure of
operation), this report shall include the user's actual production during the
appropriate sampling period. All compliance reports must be signed and
certified in accordance with Section 9.10 below.
9.7 Periodic Compliance Reports
A.
Any significant industrial user subject to a pretreatment standard
shall, at a frequency determined by the Commission but in no case
less than twice per year, submit a report indicating the nature and
concentration of pollutants in the discharge which are limited by
such pretreatment standards and the measured or estimated
average and maximum daily flows for the reporting period. All
periodic compliance reports must be signed and certified in
accordance with Section 9.10 below.
B.
All wastewater samples must be representative of the user's
discharge. Wastewater monitoring and flow measurement facilities
shall be properly operated, kept clean, and maintained in good
working order at all times. The failure of a user to keep its
monitoring facility in good working order shall not be grounds for
the user to claim that analytical results are not representative of its
discharge.
C.
If a user subject to the reporting requirement in and of this Section
monitors any pollutant more frequently than required by the
Commission, using the procedures prescribed in Section 9.3 (B) of
these Rules and Regulations, the results of this monitoring shall be
included in the report.
printed 11/94
58
9.8 Notification/Reporting Requirements
A.
Report of Changed Conditions
Users are required to submit written notification to the
Commission in advance of any substantial change to the user's
pretreatment operations or system which might alter the nature,
quality or volume of its wastewater at least thirty (30) days prior to
instituting any such change, including the listed or characteristic
hazardous wastes for which the user has submitted initial
notification under 40 CFR 403.12 (p).
B.
Sampling Violations
If sampling performed by an user indicates a violation of discharge
limitations, the user must notify the Commission within twenty-
four hours (24) hours of becoming aware of the violation. The user
shall also repeat the sampling and analysis and submit the results
of the repeat analysis to the Commission within thirty (30) days
after becoming aware of the violation.
C.
Potential Problems
1) Notification of Accidental Spills
In the case of an accidental discharge into the facility, it is the
responsibility of the user to immediately telephone and notify
the Commission of the incident at its 24 Hour Emergency
Hotline number. The notification shall include location of
discharge, type of waste, concentration and volume, and
corrective actions. Within five (5) days following an accidental
discharge into the facilities, the user shall submit a detailed
written report describing the nature and cause of the discharge
and the measures to be taken by the user to prevent similar
future occurrences. Such notification shall not relieve the user
of any expenses, loss, damage or other liability resulting from
the discharge. Notification will not exempt the user from any
fines, civil or criminal penalties, or any other liability which
may be imposed by these Rules and Regulations or other
applicable state or Federal law.
2) In the case of any discharge, including but not limited to,
discharges of a non-routine, episodic nature, a non-customary
batch discharge, or a slug load which may cause potential
problems for the Commission (including a violation of the
prohibited discharge standards in Article 5), it is the
responsibility of the user to immediately telephone and notify
printed 11/94
59
the Commission of the incident at its 24 Hour Emergency
Hotline number. The notification shall include location of
discharge, type of waste, concentration and volume, and
corrective actions. Within five (5) days following an accidental
discharge into the facilities, the user shall submit a detailed
written report describing the nature and cause of the discharge
and the measures to be taken by the user to prevent similar
future occurrences. Such notification shall not relieve the user
of any expenses, loss, damage or other liability resulting from
the discharge. Notification will not exempt the user from any
fines, civil or criminal penalties or any other liability which may
be imposed by these Rules and Regulations or other applicable
state or Federal law.
3) Failure to notify the Commission of potential problem
discharges shall be deemed a separate violation of these Rules
and Regulations.
4) A notice shall be permanently posted on the user's bulletin
board or other prominent place advising employees whom to
call in the event of a discharge described in this Section.
Employers shall ensure that all employees, who may cause or
suffer such discharge to occur, are advised of the emergency
notification procedure.
D.
Selling, Closing or Moving a Business
Any user who will be selling, closing or moving a business from its
present location must notify the Commission in writing thirty (30)
days before disposing of any process waste associated with the
move or the cessation of business. The Commission has a
shutdown facility procedure which must be adhered to upon
selling, closing or moving a business or operation. Failure to notify
the Commission prior to discharging such waste into the facilities
may subject the user to civil or criminal penalties in accordance
with R.I.G.L.§46-25-25.2 and §46-25-25.3.
The facility shutdown procedure includes, but is not limited to, the
following:
1)
An inventory specifying the amount of each chemical and each
solution on the premises, whether in storage drums or in process
tanks;
2)
A written plan detailing how each chemical and solution is to be
disposed of (i.e., discharged to sewer with or without pretreatment,
sold, returned to the supplier or hauled off as hazardous waste);
printed 11/94
60
3)
The information required in items D 1. and 2. above must be
reviewed and approved by the Commission prior to any solutions
or chemicals being disposed of. Only those solutions approved by
the Commission may be discharged to the sewer system. The NBC
must be informed at least 48 hours in advance of when chemicals
are to be shipped off site or discharged to the sewer. A copy of
each hazardous waste manifest form for any chemicals or solutions
disposed of off site must be submitted to the Commission as soon
as they are completed. A copy of each sales receipt, credit slip, etc.
for any chemicals or solutions that are sold or returned to the
supplier must be submitted to the Commission as soon as they are
completed.
printed 11/94
61
9.9 Hazardous Waste Notification
A.
Any user, except as specified in subpart E. below, which discharges
to the Commission's facilities any substance which, if disposed of,
would be listed or characterized as hazardous waste under 40 CFR
part 261, shall notify the Commission in writing of such discharge.
B.
All hazardous waste notifications shall include:
1)
The name of the hazardous waste as set forth in 40 CFR part
261;
2)
The EPA hazardous waste number;
3)
The type of discharge (continuous, batch, or other); and
4)
A certification that the user has a program in place to reduce
the volume and toxicity of hazardous waste generated to the
degree it has determined to be economically practical.
C.
In addition to the information submitted in sub-section B above,
users discharging more than 100 kg of hazardous waste per
calendar month to the Commission's facilities shall include the
following information to the extent such information is known and
readily available to the user:
1)
An identification of the hazardous constituents contained in
the waste;
2)
An estimation of the mass and concentration of such
constituents in the wastes stream discharged during that
calendar month; and
3)
An estimation of the mass of constituents in the waste stream
expected to be discharged during the following twelve (12)
months.
D.
Discharge of more than 15 kg of non-acute hazardous wastes in a
calendar month, or of any quantity of acute hazardous wastes as
specified in 40 CFR 261.30(d) and 261.33 (e) requires a one-time
notification.
E.
Dischargers are exempt from the requirements of paragraphs A-C
of this Section 9.9 during a calendar month in which they discharge
no more than 15 kg of hazardous waste unless the wastes are acute
hazardous wastes as specified in 40 CFR 261.30 (d) and 261.33(e).
9.10 Signatories and Certification
All wastewater discharge permit applications and user's reports shall contain a
certification statement as outlined in 40 CFR §403.6(a)(2)(ii) and shall be signed
by an authorized representative of the user.
printed 11/94
62
ARTICLE 10-ENFORCEMENT
10.1 Administrative Enforcement Remedies
The Commission may implement any combination of the following
administrative and/or judicial responses if a user is in violation of any provision
of state or Federal requirements, the Rhode Island General Laws Title 46 Chapter
25 (the Act), these Rules and Regulations, a permit or an order issued by the
Commission.
A.
Notice of Violations
Whenever the Commission finds that any user has violated or is
violating these Rules and Regulations, the Act, a permit or order
issued by the Commission, the Commission may serve upon said
user written notice of the violation. The Notice is a warning to the
user that the noncompliance must be corrected within a reasonable
time. The issuance of a Notice of Violation does not preclude the
Commission from taking any additional enforcement action as it
deems necessary and appropriate. The Notice may direct the user
to submit written proposals for achieving compliance, it may direct
the user to increase the frequency of self-monitoring or it may
require the user to comply with any other requirements which the
Commission feels are necessary and appropriate to address
noncompliance. Submission of any plan to achieve compliance
shall in no way relieve the user of liability for any violations
occurring before or after receipt of the Notice of Violation. Nothing
in this section shall limit the authority of the Commission to take
any action, including emergency actions or any other enforcement
action, without first issuing a Notice of Violation.
B.
Compliance Orders
When the Commission finds that a user has violated or continues to
violate these Rules and Regulations, the Act, a permit or order
issued by the Commission, or any other pretreatment standard or
requirement, the Commission may issue an order to the user
responsible for the discharge, directing that the user come into
compliance within a reasonable time period established by the
Commission. Compliance Orders may also contain such other
requirements as might be reasonably necessary and appropriate to
address the noncompliance, including, but not limited to, the
installation of pretreatment technology and/or additional self-
monitoring and management practices designed to minimize the
printed 11/94
63
amount of pollutants discharged to the sewer. A Compliance
Order does not relieve the user of liability for any violation,
including any continuing violation. Issuance of a Compliance
Order shall not be a prerequisite to taking any other action against
the user, including, but not limited to, assessment of an
Administrative Fine.
C.
Cease and Desist Orders
When the Commission finds that a user is violating the Rules and
Regulations, the Act, a permit, or any order issued by the
Commission, or any other pretreatment standard or requirement,
or that the user's violations are likely to reoccur and/or continue,
the Commission may issue an order to the user directing the user to
halt all illegal or unauthorized discharges to the Commission's
facilities immediately.
1)
If the Commission determines that an emergency exists the
Cease and Desist Order may be given verbally and/or
telephonically.
2)
Issuance of a Cease and Desist Order shall not be a
prerequisite to taking any other action against the user,
including but not limited to, assessment of an Administrative
Fine.
D.
Consent Orders
When the Commission is able to reach an agreement with the user
responsible for the noncompliance, the Commission and the user
may enter into Consent Orders, assurances of voluntary
compliance, or other similar documents establishing the agreement
with the user. Such orders typically include; specific actions to be
taken by the user within a particular time frame, a schedule for
payment of the fines and enforcement costs, and stipulated
penalties. Consent Orders shall have the same force and effect as
Administrative Orders and shall be judicially enforceable.
E.
Suspension of Permit or Service
The Commission may suspend wastewater treatment service
and/or a permit to effectively halt or prevent any actual or
threatened illegal or unauthorized discharge of pollutants into the
Commission's facilities. The Commission shall notify the user of
the suspension, by certified and regular mail, at which time the
user may utilize the hearing procedures included herein.
printed 11/94
64
F.
Emergency Suspensions:
1)
Whenever the Commission determines that suspension of
wastewater treatment service or of a permit is necessary to
stop an actual or threatened discharge presenting or causing
an imminent or substantial endangerment to the health or
welfare of persons, the POTW, or the environment, the
Commission may give the user informal notice of the
suspension. Informal notice shall consist of a telephone call to
the discharging facility's owner or any agent or officer of a
corporation. The Order to suspend discharging shall become
effective notwithstanding the inability to contact the user. A
registered or certified letter, return receipt requested, which
states the existence of the violation and the action deemed
necessary will be sent within five (5) days to the user. No
request for a hearing prior to the issuance of this Emergency
Order to suspend discharging may be made.
2)
Any user notified of an emergency suspension of their
wastewater treatment service and/or suspension of their
wastewater discharge permit shall immediately stop or
eliminate its contribution. In the event of a user's failure to
immediately comply voluntarily with the Suspension Order,
the Commission shall take such steps as deemed necessary,
including immediate severance from the sewer facilities to
prevent or minimize damage to the Commission, its receiving
stream, or any individuals. The Commission shall allow the
user to recommence its discharge when the endangerment has
passed, unless proceedings are initiated to terminate the user's
permit.
3)
A user which is responsible, in whole or in part, for imminent
endangerment to the health and welfare of persons shall
submit a detailed written statement describing the causes of
the harmful contribution and the measures taken to prevent
any further occurrence to the Commission within five (5) days
of the occurrence that lead to the emergency suspension.
G.
Termination of Permit and/or Wastewater Treatment Service:
Grounds for termination of a permit and/or wastewater treatment
service, include but are not limited to, the following:
printed 11/94
65
1)
Failure to apply for and/or obtain a required permit from the
Commission prior to discharge into the Commission's
facilities.
2)
Violation of any of the conditions outlined in the user's permit.
3)
Violation of any of the provisions of these Rules and
Regulations, the Act, or any permit or order issued by the
Commission, or any applicable state or Federal law.
Any user issued an Administrative Order terminating their permit
and/or their wastewater treatment service shall be entitled to a
hearing pursuant to Section 10.4.
H.
Security Requirements
1)
Performance Bonds. The Commission may decline to reissue
a permit to any user which has failed to comply with the
provisions of the Rules and Regulations, the Act, any order or
previous permit issued hereunder unless such user first files
with it a satisfactory bond, payable to the Commission, in a
sum not to exceed a value determined by the Commission to
be necessary to achieve consistent compliance.
2) Liability Insurance. The Commission may decline to reissue
a permit to any user which has failed to comply with the
provisions of these Rules and Regulations, the Act or any
previous permit issued hereunder, unless the user first
submits proof that it has obtained financial assurance
sufficient to restore or repair Commission damage caused by
its discharge.
I.
Administrative Fines/Penalties
Notwithstanding any other section of these Rules and Regulations,
any user who is found to have violated any provision of these Rules
and Regulations, or permits and orders issued hereunder, shall be
fined in an amount not to exceed Twenty-Five Thousand Dollars
($25,000.) per day per violation. Each day during which
noncompliance occurs or continues shall be deemed a separate and
distinct violation.
1)
Such assessments may be added to the user's next scheduled
sewer service charge.
2)
Unpaid charges, fines and penalties shall constitute a lien
against the individual user's property.
printed 11/94
66
3)
Interest on the unpaid balance of charges, fines and penalties
shall accrue at a rate established by the Commission and
approved by the Public Utilities Commission.
4)
Users desiring to dispute fines assessed by the Commission
must file a written request for hearing within ten (10) days of
receipt of the order assessing the fine, in accordance with the
hearing procedure outlined below.
5)
The Commission may impose escalating fines in instances of
repeated violations.
6)
The Commission may calculate the fine in accordance with
the penalty matrix outlined below.
7)
Nothing in this section shall limit the authority of the
Commission to impose the maximum Administrative
Penalty for violation of any provision of Federal or State
laws or regulations, these Rules and Regulations, or any
permit or order issued pursuant thereto.
10.2 Calculation of Administrative Penalty
Penalties may be calculated according to the following penalty
matrix for violations of R.I.G.L.§46-25-25 et seq. of the Rhode Island
General Laws and all Rules and Regulations, permits and orders
issued pursuant thereto. In accordance with R.I.G.L.§46-25-25.2,
penalties are assessed for each day of noncompliance.
TYPE OF VIOLATION
Deviation from
Standard
I
II
III
Major
$25,000.
to
$10,000.
$10,000.
to
$5000.
$5000.
to
$1000.
Moderate
$10,000.
to
$5000.
$5000.
to
$1000.
$1000.
to
$500.
Minor
$5000.
to
$1000.
$1000.
to
$500.
$500.
to
$100.
printed 11/94
67
A.
Type of Violation
Refers to the nature of the legal requirement allegedly violated.
“Type” includes, but is not limited to, the following examples:
printed 11/94
68
Type I
1)
Violations
of
legal
requirements
identified
by
the
Commission as directly related to the protection of the
public health, safety, welfare, or environment.
2)
Violation of wastewater discharge limits.
3)
Violations of compliance schedule milestones.
4)
Failure to provide reports (compliance schedules, self
monitoring data, BMR & FCMR)
5)
Failure to accurately report noncompliance.
6)
Failure to obtain required permit from the Commission.
7)
Failure to take remedial action to mitigate a known harm.
8)
Any other violation or group of violations that the
Commission considers to be significant including a pattern
of Type II and Type III violations.
Type II
1)
Violation of legal requirements indirectly related to public or
environmental protection, e.g., late reports, (but with
notification of the Commission that sampling has been
performed.)
2)
Failure to comply with an equipment or design specification
or any other operational methods or procedure required by
the Commission or specified in the Rules and Regulations,
which is indirectly related to protection of the public health
and welfare and/or the environment, e.g. the discharge of
non-contact cooling water without approval.
3)
A pattern of Type III violations.
Type III
1)
Violation of legal requirements identified by the Executive
Director as important but incidental to the protection of the
plant workers and environment, e.g. late sampling.
B.
Deviation from Standard
Refers to the degree to which the violation is out of compliance
with the requirement allegedly violated. The Commission will
evaluate the circumstances of each case to assess whether a
violation is a minor, moderate or major deviation from the standard
with reference to the following factors:
printed 11/94
69
1)
the extent to which the act or failure to act was out of
compliance;
2)
environmental conditions;
3)
the amount, toxicity, and/or nature of the pollutant;
4)
the duration of the violation;
5)
the areal extent of the violation;
6)
whether the user took reasonable and appropriate steps to
prevent and/or mitigate the non-compliance;
7)
the user's history of noncompliance;
8)
the degree of willfulness or negligence, including but not
limited to, how much control the violator had over the
occurrence of the violation and whether the violation was
foreseeable;
9)
willingness to participate in supplemental environmental
projects which are directly related to addressing compliance
problems of the industry within which the violation took
place. Such projects are subject to the approval and control
of the Commission;
10)
the economic benefit achieved by noncompliance;
11)
any other factor(s) that may be relevant in determining the
amount of a penalty, provided that, said other factor(s) shall
be set forth in the Notice of Violation, order or other written
notice of the Assessment of Penalty.
10.3 Administrative Hearings
A.
Right to Hearing
Any Order or Assessment of Penalty shall inform the user that a
written request for a hearing on the alleged violations, order,
and/or penalty must be filed within ten (10) days after service of
the notice to preserve the user's right to hearing. The notice will be
deemed properly served upon the user if a copy is served upon
him or her personally, or sent by registered or certified mail to his
or her last known address, or if he or she is served with notice by
any other method of service now or hereafter authorized in civil
actions under the laws of the State. In an emergency situation, if
written request for a hearing is not made by the user within ten (10)
days of the service of notice, the user will be foreclosed from
hearing regarding any penalty assessed. In a non-emergency
situation if written request for a hearing is not made by the user
within ten (10) days of the service of notice, the user will be
foreclosed from hearing regarding both the order and any penalty
assessed.
printed 11/94
70
B.
Hearing Request and Conference Option
As stated immediately above, a written request for hearing must be
filed within ten (10) days from service to preserve the user's rights.
At that time, the user may also request a conference with the
Commission prior to the scheduling of an administrative hearing.
Said conference will include appropriate members of the
Commission from the pretreatment and enforcement staffs.
Violations and penalties will be explained and discussed. Electing
this option does not foreclose and/or affect the user's right to
hearing provided that the written request for hearing was filed
within ten (10) days of service as noted above. The purpose of this
option is to provide the user with an informal forum within which
to discuss the alleged violations and to expedite conclusion and/or
resolution of outstanding enforcement actions. If resolution is not
reached within ninety (90) days from the date of the scheduled
conference the Commission shall schedule the matter for formal
hearing. In any event, either party may request a formal hearing at
any point during the conference proceedings.
C.
Scheduling of Hearing/Appointment of Hearing Officers
If a user wishes to proceed directly to hearing, without exercising
the conference option, the Executive Director shall appoint a
Hearing Officer within ten (10) days of the receipt of said hearing
request. If the user requests a conference prior to hearing, the
appointment of a Hearing Officer shall be postponed until further
request by Commission staff and/or the user. The Hearing Officer
shall set the procedures and schedules for actual hearing.
D.
Designation of Hearing Officers
Notwithstanding any other provisions of the bylaws or any other
Rule and Regulation of the Commission, and in accordance with
the criteria promulgated by the Commission, the Board of
Commissioners shall designate certain persons to act as hearing
officers in cases arising under these Rules and Regulations.
With the adoption of these Rules, the Executive Director is
empowered to appoint persons who are duly designated by the
Board of Commissioners and who are not involved in the
enforcement action to act as hearing officers. A person designated
as a hearing officer shall be a person who meets specific
qualifications adopted by the Board of Commissioners.
printed 11/94
71
The Hearing Officer shall:
1)
Have the right to issue subpoenas in the name of the
Commission to compel the appearance of witnesses and the
production of any books, records or other documentation.
2)
Take evidence.
3)
Transmit in a timely manner a report of the evidence and
hearing, including transcripts and other evidence, together
with findings of fact and conclusions of law and
recommendations of action to the Executive Director. The
Hearing Officer may also issue findings as to the number of
days during which the violation occurred and appropriate
penalties. In establishing any penalty, the Hearing Officer
and the Executive Director shall take into account the factors
used to determine the severity of a violation outlined in
Section 10.8 of this Article.
E.
Other Hearings
All other provisions for public hearings not specifically described
herein shall be in accordance with R.I.G.L.§42-35-9 et seq.
F.
Orders by the Executive Director
After the Executive Director has reviewed the Administrative
Decision of the Hearing Officer, he or she may issue an order to the
violator to cease and desist committing such violations, assess fines,
to remedy such violations, to revoke the violator's discharge
permit, and to recover statutory enforcement costs. Such
enforcement costs include, but are not limited to, the costs of
implementing any action, as well as any administrative costs
incurred therein, such as the reasonable expenses of the Hearing
Officer, stenographer, staff, expert witnesses and reasonable
attorney's fees. The decision may include a finding as to the
number of days during which the violation occurred. Every day in
which the violation occurred shall be deemed a separate offense.
The Superior Court shall have jurisdiction to enforce such order
and the Executive Director may institute civil or criminal
proceedings in the name of the Commission.
10.4 Equal Access to Justice Application
Within thirty (30) days of the conclusion of any administrative hearing or within
thirty (30) days of the informal disposition or termination of any hearing by the
Commission, the prevailing party may apply to the Hearing Officer for the
award of reasonable litigation expenses incurred by that party in connection with
printed 11/94
72
the proceeding, in accordance with the provisions of R.I.G.L.§42-92-1 et seq. The
Hearing Officer shall not award fees or expenses to the prevailing party if he or
she finds that the Commission was substantially justified in the actions leading to
the hearing and in the hearing itself. The Hearing Officer, may at his or her
discretion, deny fees or expenses if special circumstances make an award unjust.
The decision of the Hearing Officer shall be made part of the record and shall
include written findings and conclusions. The Executive Director may not
review the award. Any party dissatisfied with the fee determination by the
Hearing Officer may appeal to the Superior Court. The terms "substantial
justification" and "prevailing party" shall be defined in R.I.G.L.§42-92-1 et seq.
10.5 Petitions for Declaratory Rulings
Any person affected by any statutory provision administered by the Commission
or affected by any rule or order of the Commission may, in accordance with
R.I.G.L.§42-35-8 and these Regulations, petition the Executive Director for a
declaratory ruling as to the applicability of such statute, rule or order. The
petition shall clearly and concisely identify:
A.
The precise statute, rule or order under which a declaratory ruling
is sought;
B.
How the petitioner is affected by the statute, rule or order;
C.
The petitioner's position on how the applicable statute, rule or
order should be interpreted, including citations to any applicable
documents or law that support the petitioner's position.
10.6 Judicial Remedies
If any person discharges sewage, industrial wastes, or other wastes into the
wastewater disposal system contrary to the provisions of the Rules and
Regulations, the Act, a permit or order issued by the Commission, or any other
pretreatment requirements, the Commission may commence an action for
appropriate legal and/or equitable relief in the Superior Court.
A.
Injunctive Relief
Whenever a user has violated or continues to violate the provisions
of the Rules and Regulations, the Act, a permit or order issued by
the Commission, or any other pretreatment requirements, the
Commission may petition the Court for the issuance of a
preliminary or permanent injunction or both (as may be
appropriate) which restrains or compels the activities on the part of
the user.
printed 11/94
73
B.
Civil Penalties
1)
Any user who has violated or continues to violate the Rules
and Regulations, the Act, a permit or order issued by the
Commission, or any other pretreatment requirements shall
be liable to the Commission for a civil penalty of not more
than $25,000 per violation per day for each day during which
the violation occurs plus actual damages incurred by the
Commission for as long as the violation occurs. In addition
to the above described penalty and damages, the
Commission may recover reasonable attorney's fees, court
costs, and other expenses associated with the enforcement
activities, including sampling, monitoring and analysis
expenses.
2)
The Commission shall petition the Court to impose, assess
and recover such sums. In determining the amount of
liability, the Court shall take into account all relevant
circumstances, including, but not limited to, the extent of
harm caused by the violation, the magnitude and duration,
any economic benefit gained through the user's violation,
corrective actions by the user, the compliance history of the
user, and any other factor as justice requires.
C.
Criminal Prosecution
Any user who willfully or negligently violates any provision of the
Rules and Regulations, the Act, a permit or order issued by the
Commission or any other pretreatment requirements, shall upon
conviction, be guilty of a misdemeanor, punishable by a fine not to
exceed $25,000 per violation per day or imprisonment for not more
than one year.
10.7 Costs
In addition to such administrative, civil, or criminal fines as may be imposed,
any user who violates any provision of the Rules and Regulations or any
condition of a permit, or plan approval related thereto, shall be financially
responsible and liable to the Commission, in addition to normal service charges
and surcharges for industrial investigation and monitoring of compliance with
these Rules and Regulations, including, but not limited to, the following:
A.
Cost of mileage, labor and materials incurred in detecting and
correcting the violation;
printed 11/94
74
B.
Laboratory analysis costs associated with detecting and correcting
the violation;
C.
Additional treatment costs caused by the violation or association
with detecting and correcting the violation;
D.
Costs of any additional equipment acquired or expended by the
Commission for detecting or correcting the violation.
E.
Repair and/or replacement of any part of the facility damaged by
the violation;
F.
Any liability, damages, fines or penalties incurred by the
Commission as a result of the violation;
G.
Costs incurred in enforcing compliance, including prosecution
and/or settlement of outstanding violations;
H.
Other costs as are associated with the prosecution, negotiation
and/or settlement of a violation.
10.8 Annual Publication of Users in Significant Noncompliance
The Commission shall publish annually in the largest daily newspaper circulated
in the service area, a description of those users who are found to be in significant
noncompliance, as defined in Article 2 of these Rules and Regulations, with any
provisions during the period since the previous publication. Users found to be in
significant noncompliance must reimburse the Commission for their pro-rata
share of the cost of the public notice.
10.9 Denial of Access
If the Commission or its duly authorized employees and agents, upon presenting
identification and appropriate credentials, are denied access to carry out
inspection, surveillance, and monitoring procedures as described under
R.I.G.L.§46-25-25.1 et seq., the Executive Director may immediately institute civil
proceedings, including proceedings for necessary injunctive relief, or criminal
proceedings in Superior Court.
10.10 Inspection of Connections
If any person shall construct, install, alter or repair any sewer or connect to any
sewer in violation of the requirements of these Rules and Regulations, the
printed 11/94
75
Commission may, in its discretion, order or direct such person to uncover and
fully expose any or all portions of such sewer or connection and afford the
Commission and its representatives adequate opportunity for examination and
inspection of the work. If the connection and appurtenances thereto shall be
found not to be in full accord with the requirements of these Rules and
Regulations and the standards established under its provisions, then the
Commission may serve the offender with a written notice as provided in Article
10.
printed 11/94
76
10.11 Affirmative Defenses To Discharge Violations
A.
Upset Provisions
1)
For the purposes of this section, "Upset" means an exceptional
incident in which there is unintentional and temporary
noncompliance with Pretreatment Standards because of
factors beyond the reasonable control of the user . An Upset
does not include noncompliance to the extent caused by
operational error, improperly designed treatment facilities,
inadequate
treatment
facilities,
lack
of
preventive
maintenance, or careless or improper operation.
2)
An Upset shall constitute an affirmative defense to an action
brought for noncompliance with Pretreatment Standards if the
requirements of paragraph (3) are met.
3)
A user who wishes to establish the affirmative defense of
Upset
shall
demonstrate,
through
properly
signed,
contemporaneous operating logs, or other relevant evidence
that:
a)
An Upset occurred and the user can identify the cause(s)
of the Upset;
b)
The facility was at the time being operated in a prudent
and workman-like manner and in compliance with
applicable operation and maintenance procedures;
c)
The user has submitted the following information to the
Commission within 24 hours of becoming aware of the
Upset (if this information is provided orally, a written
submission must be provided within five (5) days);
i) A description of the discharge and cause of
noncompliance;
ii) The period of noncompliance, including exact dates
and times or, if not corrected, the anticipated time the
noncompliance is expected to continue;
iii) Steps being taken and/or planned to reduce,
eliminate and prevent recurrence of the noncompliance.
4)
In any enforcement proceeding the user seeking to establish
the occurrence of an Upset shall have the burden of proof; and
5)
The user shall control production or all discharges to the
extent necessary to maintain compliance with Pretreatment
Standards upon reduction, loss, or failure of its treatment
facility until the facility is restored or an alternative method of
treatment is provided. This requirement applies in the
situation where, among other things, the primary source of
power of the treatment facility is reduced, lost or fails.
printed 11/94
77
B.
Bypass
1)
"Bypass" means the intentional diversion of waste streams
from any portion of the user's treatment facility.
2)
"Severe property damage" means substantial physical damage
to property, damage to the treatment facilities which causes
them to become inoperable, or substantial and permanent loss
of natural resources which can reasonably be expected to
occur in the absence of a bypass. Severe property damage
does not mean economic loss caused by delays in production.
3)
A user may allow Bypass to occur where it does not violate
pretreatment standards or requirements, and only if it is
necessary to assure efficient maintenance and/or operation.
These bypasses are not subject to the provisions (4), (5) and (6)
below.
4)
If a user knows in advance of the need for a Bypass, it shall
submit prior notice to the Commission, if possible at least ten
days before the date of the Bypass.
5) A user shall orally notify the Commission of an unanticipated
bypass that exceeds applicable pretreatment standards or
requirements within 24 hours of becoming aware of the
Bypass. A written submission shall also be provided within
five days of becoming aware of the Bypass, including exact
times and dates, and if the Bypass has not been corrected, the
anticipated time it is expected to continue; and steps taken or
planned to reduce, eliminate, and prevent recurrence of the
Bypass.
6)
Bypass is prohibited and the Commission may take
enforcement action against an individual user for a Bypass,
unless:
a)
Bypass was unavoidable to prevent loss of life, personal
injury or severe property damage;
b)
There are no feasible alternatives to Bypass, such as use
of auxiliary treatment facilities, retention of wastes or
maintenance during normal periods of downtime. This
condition is not satisfied if adequate back-up equipment
should have been installed to prevent Bypass which
occurred during normal periods of equipment downtime
or preventative maintenance; and
c)
The user submitted notices as required by paragraph (B)
of this section.
printed 11/94
78
The Commission may approve an anticipated Bypass, after considering its
adverse effects, if the Commission determines that it will meet the three
conditions listed in this section.
printed 11/94
79
ARTICLE 11-INTERPRETATION OF REQUIREMENTS
11.1 Construction
The provisions of these Rules and Regulations with respect to the meaning of
technical terms and phrases, the restrictions as to what wastes may be discharged
into interceptors, the regulations with respect to making connections to
interceptors and other technical matters shall be interpreted and administered by
the Executive Director.
11.2 Captions
Captions and headings are for reference only and shall not limit or otherwise
affect the meaning of the paragraphs thereunder.
11.3 Severability
If any provision of these Rules and Regulations or the application thereof to any
person or circumstances is held invalid by a court of competent jurisdiction, the
remainder of the Rules and Regulations shall not be affected thereby. The
invalidity of any section or sections or parts of any section or sections shall not
affect the validity of the remainder of these Rules and Regulations.
printed 11/94
80
ARTICLE 12-AMENDMENT TO RULES AND REGULATIONS
The Rules and Regulations set down herein may be amended, from time to time,
as may, in the opinion of the Commission, be necessary. Whenever the
Commission shall amend any such Rules and Regulations, it shall do so and give
notice of such amendment in accordance with the procedures outlined in R.I.G.L.
§42-35-1 and §46-25-1 et seq.
printed 11/94
81
ARTICLE 13-(Reserved)
printed 11/94
82
ARTICLE 14-SEPTAGE DISCHARGE PERMIT SYSTEM
14.1 Septage Permitting System
Licensed septage haulers shall obtain a valid permit from the Commission and
comply with all the conditions of this permit and these Rules and Regulations.
The septage hauler permit shall be valid for one year with renewal July first of
each fiscal year. The permit may be suspended or revoked according to the
policies outlined in Article 8 of these Rules and Regulations. Haulers shall apply
for this permit on forms provided by the Commission and shall submit, together
with the permit fee, an application containing the following information:
A.
Name, company name, address, telephone number.
B.
Vehicle identification, make, and capacity.
C.
Copy of septage hauler's license from the Rhode Island Department
of Environmental Management.
D.
Any additional information requested by the Commission.
E.
Signed and notarized statement certifying that the information
presented in the application is correct.
14.2 Septage Sources
Septage discharged to the receiving facilities of the Commission must have been
generated from residential septic systems, within the boundaries of the State of
Rhode Island.
14.3 Septage Load Tickets
Septage haulers shall purchase load tickets from the Commission prior to arrival
at the plant, and present tickets whose summed value is equivalent to the gallon
capacity of the truck, regardless of whether the truck is full or partially full.
printed 11/94
83
14.4 Septage disposal
A.
Septage shall only be discharged to one of the Commission's
authorized septage receiving facilities, or other authorized location
as the Commission may designate. The septage hauler shall be
responsible for cleaning the area surrounding the discharge
disposal location after discharge.
B.
Septage shall be discharged only within the hours specified by the
Commission, and only under the supervision of the Commission.
Gallonage and hours for delivery of waste may be reduced,
extended, increased, or otherwise changed or altered by and at the
discretion of the Commission. Commission personnel may require
that the load be dumped over a period of a half-hour or more,
depending upon the flow and characteristics of the incoming
sewage at the Commission's treatment plant.
C.
Each septage hauler shall furnish the following items to the
Commission personnel upon arrival at the septage receiving
facility:
1)
Load manifest form (provided by the Commission) which
states the hauling company, hauler name, vehicle license
number, quantity and source (owner and address) of the
septage, probable content of the septage, and a certification
statement signed by the hauler and generator, attesting to
the accuracy of the information provided on the load
manifest form.
2)
Previously purchased load ticket(s) corresponding to the
capacity of the truck.
3)
Four (4) grab samples of the septage taken by the septage
hauler under supervision by the Commission. The
Commission reserves the right to refuse to accept any load
that is suspected of being or has been determined through
sampling and analysis to be detrimental to the operations of
the plant, the safety of its workers, or to the health or welfare
of the public.
D.
The hauler shall keep a copy of his/her official permit in the truck,
and display the Commission issued permit sticker on the
windshield.
E.
If the Commission, plant, and/or sewerage system can accept some,
but not all of the septage offered for disposal, priority will be given
printed 11/94
84
printed 11/94
85
to such waste which is generated within the geographic boundaries
of the Narragansett Bay Water Quality Management District.
14.5 Septage Prohibitions
Septage haulers shall not discharge specifically prohibited waters, wastewaters,
or substances to the Commission facilities in accordance with Article 5 herein.
14.6 Septage Records
Vehicles shall be maintained and records shall be kept in accordance with the
Rhode Island DEM's Rules and Regulations for Hazardous Waste Generation,
Transportation, Treatment, Storage and Disposal.
14.7 Compliance Required
No statement contained in this Article shall exempt the hauler from complying
with all Federal, state or local requirements.