870-RICR-10-00-1
870-RICR-10-00-1. Rules and Regulations for the Expedited Permit Process (version Amendment, 05/22/2008 to 05/22/2008)
STATE OF
RHODE ISLAND AND PROVIDENCE PLANTATIONS
ECONOMIC DEVELOPMENT CORPORATION
RULES AND REGULATIONS FOR THE
EXPEDITED PERMIT PROCESS
Date of Public Notice: March 17, 2008
Date of Public Hearing: March 31, 2008
Effective Date: May 22, 2008
STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS
RHODE ISLAND ECONOMIC DEVELOPMENT CORPORATION
RULES AND REGULATIONS FOR THE EXPEDITED PERMIT PROCESS
Section 1.00. Purpose
The State of Rhode Island and Providence Plantations, in an effort to create new high wage job
opportunities in Rhode Island, to create new or renovated office, research and manufacturing space
capacity in Rhode Island, to promote a vigorous and growing economy, to prevent economic stagnation,
to encourage the creation of new job opportunities, to reduce the level of public assistance, and to
increase revenues to the State and its municipalities, has developed an expedited permit review process, as
set forth in Rhode Island General Laws, § 42-117-1 et seq., for projects of critical economic concern. The
purpose of these rules and regulations is to implement the requirements of Chapter 117, Title 42 of the
Rhode Island General Laws to provide a mechanism for business and industry to secure any necessary
licenses or permits in an expeditious manner without waiving the lawful conditions of said licenses or
permits.
Section 2.00. Legal Authority
These rules and regulations are promulgated pursuant to the requirements and provisions of the
Expedited Permit Process Act, R.I.G.L. § 42-117-1 et seq., and the Administrative Procedures Act,
R.I.G.L. § 42-35-1 et seq..
Section 3.00. Definitions
For the purposes of these regulations, the following terms shall have the following meanings:
3.01 "Authorization for Expedited Permit Review" (or “Authorization”) means an authorization
issued by the Rhode Island Economic Development Corporation (or “Corporation”) as
set forth in R.I.G.L. § 42-117-4.
2
3.02 "Board of Directors of the Rhode Island Economic Development Corporation" (or “Board”)
means the board of directors of the Corporation established pursuant to R.I.G.L. § 42-64-1
et. seq.
3.03 "Governor" means the Governor of the State of Rhode Island and Providence
Plantations (or “State”).
3.04 “High Wage Full Time Employee” (or “High Wage Employee”) means any
employee of a person or an employee of a contractor of such person as certified
pursuant to these regulations who: (a) was not previously working full time in Rhode
Island for the Project’s applicant and will work a minimum of thirty (30) hours per
week at the Project; and (b) will earn no less than One Hundred Five percent (105%)
of the average annual income in Rhode Island.
3.05
"Operational Stage" means the point at which the project is implemented and the
Project's effect is realized.
3.06
"Person" means any natural person, company, corporation, quasi-public corporation,
partnership, or any type of business entity.
3.07 "Project of Critical Economic Concern" (or, “Project”) means an undertaking designated
by the Board to be significant, in its Operational Stage, by its ability to enhance, promote
and encourage business, commerce and manufacturing in Rhode Island and stimulate
jobs and relieve underemployment and unemployment in Rhode Island pursuant to
R.I.G.L. § 42-117-3 and to create new high wage job opportunities in Rhode Island or to
create new or renovated office, research and manufacturing capacity in Rhode Island. In
order to qualify as a Project, the applicant shall demonstrate to the Corporation’s
satisfaction that:
(a) (i) in addition to any construction jobs at the Project, (A) at least One Hundred
(100) new full time jobs shall be created by the Project; and (B) the average annual
income for all of the new full time jobs created by the Project shall be no less than One
Hundred Five Percent (105%) of the State’s average annual income; and (C) no less than
Fifty Percent (50%) of the new full time jobs created by the Project shall be comprised
of High Wage Employees; or
(ii) the Project shall be comprised of the construction or rehabilitation of no less
than Fifty Thousand (50,000) Square Feet of space that is used for office, research or
manufacturing uses and such office, research, industrial or manufacturing uses shall
comprise no less than Fifty Percent (50%) of the total Project; and
3
4
(b) The municipality (ies) in which the Project is located have demonstrated support for
the Project and have utilized their municipal powers to coordinate permitting of the
Project to the maximum extent reasonably allowed by law.
3.08
"State Agency" means any office, department, board, commission, bureau, division,
authority, public corporation, agency or instrumentality of the State.
Section 4.00. Request for Authorization for Expedited Permit Review
All requests for an Authorization shall be submitted to the Corporation, on application forms that
may be obtained from the Corporation. Requests shall describe how the proposed Project will enhance,
promote and encourage business, commerce and industry, stimulate jobs and relieve underemployment
and unemployment in Rhode Island. Each request for an Authorization shall be accompanied by (a) a
completed application for a state agency permit; (b) a certification from such person applying for an
Authorization and/or its tenant(s) reflecting the employment or development requirements set forth in
these Regulations and evidence reasonably satisfactory to the Corporation that such requirements are
reasonably anticipated to be achieved by the Project; and (c) plans reflecting the Project’s conformance
with Section 3.07 of these regulations.
Section 5.00. Procedure for Review
The Board shall review the request for an Authorization at a regularly scheduled meeting, provided
a completed application is received at least two weeks prior to a meeting, enabling the Expedited Permit
Process Review Committee to review it and prepare a recommendation to the Board. The Expedited Permit
Process Review Committee shall consist of:
1.
A Deputy Director of the RIEDC
2.
A designated RIEDC Project Manager
3.
RIEDC Corporate Counsel
Pursuant to R.I.G.L. § 42-117-4, the Board shall issue a written decision within forty-five (45) days
of its receipt of a complete request. If the Board finds the proposed project to be a Project of Critical
Economic Concern, the Corporation shall issue an Authorization. If not, the Authorization shall be denied.
Section 6.00. No Right to Review
A review for an Authorization shall not constitute a “contested case” under the Administrative
Procedures Act, R.I.G.L. § 42-35-9. No opportunity to object to a request shall be afforded, nor shall
5
judicial review be available from a decision rendered by the Board.
Section 7.00. Reconsideration of Board Decision
Any affected person may request in writing reconsideration of the Board's decision. Requests for
reconsideration will be granted only where it can be demonstrated that there have been (i) significant
changes in the proposed project's ability to meet the criteria as set forth in Section 3.07, or (ii) significant
changes in factors or circumstances relied upon by the Board in reaching its decision. The Board shall
consider the request for reconsideration at its next regularly scheduled meeting.
Section 8.00. Validity of Authorization
An Authorization shall be valid as to each and every state agency by which the Project must be
licensed or permitted until the Project reaches its Operational Stage, or two (2) years from the date of
issuance, unless extended for an additional period of up to two (2) years at the discretion of the
Corporation's Executive Director. Upon written request to the Executive Director, the Corporation may,
at its discretion, reissue a valid Authorization to a successor in interest, upon an affirmative finding by
the Executive Director that the Project continues to meet the criteria for authorization.
Section 9.00. Rescission of Authorization
The Corporation may, by majority vote of the Board, revoke any Authorization upon a finding
that
(a) the Project has been significantly altered in size, scope or impact since the Corporation's
issuance of the Authorization; or
(b) a state agency permit application has not been filed within three (3) months of the date of the
Authorization's issuance.
Section 10.00. Action by State Agency
An Authorization may be filed with each and every state agency with licensing or permitting
authority over a Project. The state agency shall give priority to the Project in the handling and processing
of the application in accordance with RIGL Section 42-117-6 so that (a) within three (3) months of the
submission of a substantially complete application, the state agency must render a written report on the
status of the application. The report shall contain information, which will enable the person to make a
sound business decision as to whether to proceed with the application. The report shall be delivered to
the applicant and the Corporation. If the application is not granted, then the state agency shall on the
6
fourth, fifth and sixth months of the anniversary of the submission render a written report on the status of
the application. If at the end of the sixth month, a decision has not been rendered on the application,
then, in addition to the applicant and the Corporation, a copy of the written report shall be delivered by
the agency monthly thereafter to the Governor until a decision to accept or reject the application has
been made.
Section 11.00. Liberal Application
The terms and provisions of these rules and regulations shall be liberally construed to allow the
Board and the Corporation to effectuate the purposes of state law, goals, and policies.
Section 12.00. Performance
An entity which has been granted a Certificate of Critical Economic Concern shall provide a
report to the RIEDC certifying that it has met the jobs projections, tax generation, and other provisions
stated in the application which justified the approval of the Certificate, in accordance with the timeframe
specified in the application. This report shall be made at the time of completion of the project, or, for
phased projects, at the completion of each phase.
Section 13.00. Penalties
An entity failing to meet the jobs projections, tax generation, and other provisions stated in the
application that justified the approval of the Certificate shall be subject to a revocation of the Certificate
and any other penalties permitted by law.
Section 14.00. Severability
If a court of competent jurisdiction invalidates any provision of these rules and regulations, or
their application to any local government unit or circumstance, the remaining rules and regulations will
not be affected. The invalidity of any section or sections, or parts of any section or sections, shall not
affect the validity of the remainder of these rules and regulations.
7
The foregoing rules and regulations, after due notice and an opportunity for hearing, are hereby adopted
and filed with the Secretary of State this 2nd day of May, 2008, to become effective twenty (20) days
after filing, in accordance with the provisions of R.I.G.L. § 42-35-2(a), § 42-35-3, and § 42-117-8.
May 2, 2008
______________________________
Robert I. Stolzman, Secretary
Adopted by RIEDC Board of Directors: April 28, 2008
Filed with Secretary of State: May 2, 2008