870-RICR-20-00-1
870-RICR-20-00-1. Rules and Regulations for the Renewable Energy Development Fund Programs (version Adoption, 01/09/2014 to 01/09/2014)
RHODE ISLAND COMMERCE CORPORATION
2014·2016 RULES AND REGULATIONS FOR THE RENEWABLE ENERGY
DEVELOPMENT FUND PROGRAMS
1.0 Authority
These Rules and Regulations are promulgated and adopted pursuant to the requirements
and provisions of RIGL §42-64-13.2; RIGL §39-2-1.2; and RIGL §39-26.
2.0 Purpose, Scope and Applicability
The purpose and scope of the Renewable Energy Development Fund as set forth in RIGL
chapter 42-64 are as follows:
2.1 To develop an integrated organizational structure to secure for the State of Rhode Island
and its people the full benefits of cost-effective renewable energy development from
diverse sources.
2.2 The [Rhode Island Commerce] Corporation shall, in the furtherance of its responsibilities
to promote and encourage Commerce, establish and administer a Renewable Energy
Development Fund as provided for in RIGL §39-26-7, may exercise the powers set forth
in that chapter, as necessary or convenient to accomplish this purpose, and shall provide
such administrative support as may be needed for the coordinated administration of the
renewable energy standard as provided for in Chapter 39-26 and the renewable energy
program established by RIGL §39-2-1.2.
"
2.3 The Corporation seeks to fulfill its legal obligations by providing and administering
programs in 4 areas as part of the Renewable Energy Fund:
(a) Small-scale Solar
(b)Commercial Development
(c) Pre-development Feasibility Studies
(d) Early Stage Commercialization
3.0 Key Definitions
For the purposes of these regulations, the following terms shall have the following
meanings:
3.1 "Affordable Housing" means any affordable housing or low and moderate income
housing as defined in RIGL Title 42, Chapter 128, or Title 45, Chapter 53, or such
other superseding statutes as may be implemented by the State of Rhode Island
from time to time.
3.2 HBoard of Directors" means the body as defined in RIGL §42-64-8
3.3 "Ccrporatlon" means the Rhode Island Commerce Corporation or any successor
corporation or new corporation empowered to perform the functions currently served
by the Rhode Island Commerce Corporation.
3.4 Early Stage Commercialization" means an innovative renewable energy technology
or innovative business model with the ability to transform the renewable energy
business sector. Technologies have completed or have nearly completed early
research stages.
3.5 "Emerging Technology" means new technologies in renewable energy that will
come to market within the next two (2) - five (5) years which have the ability to
transform the renewable energy business sector.
3.6 HEnergy Audit" means an inspection, survey and analysis of energy flows for
energy conservation in a building, process or system to reduce the amount of
energy input into the system without negatively affecting the output
3.7 "lnnevatlve Business Model" means a novel business structure with the ability
to help commercialize an emerging or existing renewable energy technology.
3.8 "One-line Electrical Drawing" means a diagram showing the number of photovoltaic
panels with voltage and kilowatt output, all disconnects, all combiners, all inverters
with input and output ratings, the size of the main electrical panel bussing in
amperes, the size of the main service disconnect, the size of the PV circuit breaker
in amperes, size and type of all raceways and the size and type of all conductors.
3.9 "Pre-development Feasibility Study" means the completion of project tasks prior to
construction of a renewable energy project. These tasks shall not include initial
feasibility assessments. Pre-development activities occur after a project is deemed
worthy of development and before construction takes place. Examples of Pre-
development Activities include but are not limited to:
(a)
Local and State Permitting.
(b)
Structural and Electrical Engineering.
(c)
National Grid Interconnection Studies.
(d)
National Grid Impact Studies.
(e)
Detailed Financial Analyses.
(f)
RFP Preparations.
3.10 "Renewable Energy Fund" and "REF" mean the Renewable Energy Development
Fund.
3.11 "Renewable Energy Fund Advisory Committee" means the body, as appointed
by the Program Manager of the REF, that may make recommendations regarding
a project to be voted on by the Board of Directors. The Renewable Energy Fund
Advisory Committee shall consist of no fewer than:
(a)
Two (2) employees of the RI Office of Energy Resources.
(b)
One (1) RI Commerce Corporation Staff person from Financial
Services.
(c)
The Director of the Science and Technology Advisory Council (STAC)
or her designated appointee.
(d)
One (1) staff person from the REF
3.12 "RIGL" means the Rhode Island General Laws.
3.13 "ROI" means Return on Investment.
4.0
Funding
All Funds will be awarded and disbursed through solicitations issued by the Corporation
in the Program areas of Small-scale Solar, Commercial Development and Pre-
development Feasibility Studies. Approximate release dates for each solicitation will be
available on the Corporation's website at the start of each calendar year. All dates are
subject to change depending on availability of funds and demand for each program. Each
solicitation will specify the specific incentive level, detailed instructions on how to apply,
program requirements, and the deadlines to apply.
In each calendar year, a minimum percentage of the REF's income will be available to
eligible projects in each Program area. The Corporation, at its discretion, may choose to
contribute more money to a particular program based on demand for a particular
program, available funds, or other factors. The minimum allocated percentages shall be:
Small scale solar: twenty percent (20%)
Commercial Renewable Energy Development: twenty percent (20%)
Early Stage Commercialization: twenty percent (20%)
Predevelopment Feasibility Studies: twenty percent (20%)
If the minimum percentage is not awarded during the calendar year, funds will roll over
into the same program for the following calendar year.
5.0 General Requirements
5.1 All requests for use of Renewable Energy Fund programs shall be submitted
to the Corporation on Renewable Energy Fund Applications which can be
downloaded from the Corporation's website.
5.2 The Corporation reserves the right to utilize 3rd party entities to carry out its
duties as administrator of the REF.
5.3 Applications for Small-scale Solar, Commercial Development, and Pre-
development Feasibility Studies will only be accepted during open
solicitation periods. Solicitations and schedules for future solicitations can be
found on the Corporation's website.
5.4 Incomplete applications will not be accepted by the Corporation.
5.5 All applications must be typed. No handwritten applications will be accepted
unless approved in writing by REF Staff in advance.
5.6 All applicants seeking funding through the REF for renewable energy
projects must be a resident of Rhode Island or an entity located in Rhode
Island.
5.7 All applications must be for new projects. No projects underway or complete
at the time of applying shall be eligible for funding.
5.8 All energy audits must be conducted by an independent 3rd party entity
suitable to the Corporation. Energy audits conducted by the same company
performing the renewable energy installation will not be accepted.
5.9 REF funding for construction projects may not be combined the Distributed
Generation Long Term Contracts Program.
5.10
REF funding may be combined with Regional Greenhouse Gas Initiative
(RGGI) funding programs and/or renewable energy funding programs
administered by the Federal Government.
5.11
Application Review Process:
a.
Renewable Energy Fund Staff will review all applications for
Completeness and Eligibility.
b.
All qualified applications may be reviewed by the Renewable
Energy Fund Advisory Committee. A consensus will determine
whether or not to recommend an application be presented to the
Board of Directors.
c.
Applications will be voted on by the Board of Directors for
approval.
5.12
Award Process
a.
Award letters shall be sent to applicants after approval by the
Board of Directors.
b.
Contracts in a form acceptable to the Corporation shall be
executed between the Corporation and the Applicant
c.
Work may begin on Projects.
d.
All grants for construction projects will be paid in full after
successful completion and inspection of the Project.
e.
All loan disbursements will be made in manner that is mutually
acceptable to the Corporation and the borrower as agreed to in
the Loan Agreement. The Corporation in its sole discretion may
cancel an award if mutually agreeable terms cannot be met.
5.13
If an applicant fails to provide and/or complete requested documentation
within 60 days of the award letter being issued, the award shall be
cancelled.
6.0 Small Scale Solar
6.1 Solicitations for funding:
a.
A minimum of two (2) solicitations will be released each calendar
year.
b.
Solicitations shall include all additional project requirements
which are subject to change between funding periods..
c.
Solicitations shall include all deadlines for application submission.
d.
Funding will be issued in the form of grants,
6.2 Eligible Sectors:
a.
Residential.
b.
Businesses.
c.
Affordable Housing.
d.
Non-profits.
6.3 Eligible Technologies:
a.
Solar Photovoltaic (PV).
b.
Solar Domestic Hot Water (SDHW).
6.4 Minimum Submission Requirements:
a.
Proof of Energy Audit,
b.
One-line electrical drawing (for PV only),
c.
Layout drawing including location of all major components.
d.
ROI/simple payback assuming no more than 3% utility inflation
rate, and
e,
Signed turnkey contract.
6.5 Minimum Evaluation Criteria:
a.
Technical Feasibility,
b.
Financial Feasibility,
c.
Cost per kWh of energy produced,
d.
Anticipated amount of renewable energy and related benefits
expected from the proposed project. Related benefits include but
are not limited to job creation, environmental benefits, and
community benefits, and
e.
Experience of Project Team.
7.0 Commercial Scale Project Funding
7.1 Solicitations for funding:
a.
A minimum of two (2) solicitations will be released each calendar
year.
b.
Solicitations shall include all additional project requirements
which are subject to change between funding periods.
c.
Solicitations shall include all deadlines for application submission.
d.
Funding will be issued in the form of grants.
7.2 Eligible Sectors:
a.
Businesses.
b.
Institutions.
c.
Non-profits.
d.
Municipalities.
7.3 Eligible Technologies:
a.
Those technologies set forth in RIGL § 39-26-5.
b.
All projects must have the ability to generate electricity.
7.4 Minimum Submission Requirements:
a.
Proof of Energy Audit,
b.
One-line electrical drawing.
c.
Layout drawing including location of all major components.
d.
ROI/simple payback assuming no more than 3% utility inflation
rate, and
e.
Signed turnkey contract.
7.5 Minimum Evaluation Criteria:
a.
Technical Feasibility,
b.
Financial Feasibility,
c.
Cost per kWh of energy produced,
d.
Anticipated amount of renewable energy and related benefits
expected from the proposed project. Related benefits include but
are not limited to job creation, environmental benefits, and
community benefits, and
e,
Experience of Project Team.
8.0 Pre~development Feasibility Study
8,1 Solicitations for Funding:
a,
A minimum of two (2) solicitations will be released per calendar
year,
b.
Solicitations shall include additional project requirements which
are subject to change between funding periods.
c.
Solicitations shall include all deadlines for application submission,
d.
All awards will be funded as low-interest loans contingent upon
the ability for the project to be successful.
8,2 Eligible Sectors:
a,
Businesses,
b.
Institutions.
c.
Non-profits,
d.
Municipalities.
8.3 Eligible Technologies:
a.
Those technologies set forth in RIGL § 39-26-5.
b.
Technologies being studied must have the ability to generate
electricity or provide a direct benefit to the electric grid.
8.4 Minimum Submission Requirements:
a,
For Municipal Projects:
i.
Any municipality applying for a pre-development feasibility
study must include evidence of a Town/City Council vote in
favor of the proposed project.
ii.
The applicant must have evidence of Its legal ability to
borrow money on behalf of the municipality.
b.
Detailed scope of work,
c.
Detailed project budget,
d.
Contracts with all major subcontractors working on the Study,
e.
Clear evidence of cost-sharing specific to the Study, and
f.
The municipality must have an ordinance in place allowing
development of the proposed project.
8.5 Eligibility Requirements:
a.
Technical Feasibility,
b.
Financial Feasibility,
c.
Cost per kWh of energy produced,
d.
Anticipated amount of renewable energy and related benefits
expected from the proposed project. Related benefits include but
are not limited to job creation, environmental benefits, and
community benefits.
e.
Experience of Project Team
8.6 The Corporation and the REF Advisory Committee may choose to fund all,
part, or none of a Predevelopment FeasIbility Study based on the likelihood
of development.
8.7 Loans will be repaid upon completion of the project.
8.8 If the project is found to be technically and economically feasible but the
project is not commenced or completed the loan must be repaid to the
Corporation.
9.0 Early Stage Commercialization
9.1 Funding:
a.
All program requirements shall be available on the Corporation's
website.
b.
All funding will be issued in the form of a low-interest loan.
9.2 Eligible Sectors
a,
Businesses
b.
Institutions
9.3 Eligible Technologies:
a.
Those technologies set forth in RIGL § 39-26-5.
b.
Projects must have the ability to generate electricity or optimize
the integration of renewable energy into the electric grid.
c.
Projects may qualify for funding as an Emerging Technology or
an Innovative Business Model.
9.4 General Requirements
a.
Applicant must have other investments secured or be actively
pursuing other forms of investment.
b.
Applicant must submit a business plan
9.5 Evaluation Criteria
a.
Other funds leveraged,
b.
Technical Merit / Feasibility,
c.
Market Potential,
d.
Economic Impact for the State of Rhode Island,
e.
Team credentials and experience.
f.
Scope of Work/Project Budget.