ARSD 20:44:18:01

ARSD 20:44:18:01. Wiring permit required

Last amended: 2025Year: 2026Length: 101 wordsOfficial source

Cite as S.D. Admin. R. 20:44:18:01

The following require a wiring permit: (1) Any electrical service entrance in excess of sixty amperes capacity A single wiring permit may be used for a temporary electrical service and a new service on a single project when both are installed by the same contractor, which must be stated on the wiring permit at the start of the project. Separate wiring permits are required if more than one contractor is involved; (2) Electrical wiring being performed under an owner's exemption; and (3) Any other electrical installation with an estimated inspection fee of thirty dollars or more as calculated in chapter 20:44:20.
ARSD 20:44:18:01: ARSD 20:44:18:01. Wiring permit required | Justis AI