ARSD 74:05:08:13.02
ARSD 74:05:08:13.02. Facilities plan submittal
Cite as S.D. Admin. R. 74:05:08:13.02
Any applicant requesting assistance for a wastewater treatment works or storm water project must prepare a facilities plan. A facilities plan is not required from an applicant requesting funding for other types of projects. The facilities plan shall at minimum provide the information contained in subdivision 74:05:08:01(6). The applicant shall be notified of any deficiencies in the draft facilities plan submitted with the application. A completed facilities plan must be received by the department to initiate the environmental review process. The facilities plan is not considered complete until the following items are received:
(1) Information to address the deficiencies identified by the secretary;
(2) Receipt of evidence of advertisement of a public hearing;
(3) Minutes from the public hearing;
(4) Responses from the U.S. Fish and Wildlife Service; South Dakota Department of Game, Fish and Parks; Natural Resources Conservation Service; U.S. Army Corps of Engineers; and the State Historical Preservation Office; and
(5) Resolution of any issues identified in the public hearing or by the agencies listed in ยง 74:05:08:13.02(4).