ARSD 74:27:08:12

ARSD 74:27:08:12. Permit application -- Completeness review

Last amended: 1993Year: 2026Length: 113 wordsOfficial source

Cite as S.D. Admin. R. 74:27:08:12

The secretary shall conduct a completeness review of each permit application received as follows: (1) Within 90 days after submission of an application or amendment for a Type IIB, III, or IV facility, within 90 days after completion of a Phase I application for a Type I or IIA facility, or within 30 days after submission of a renewal, the secretary shall notify the applicant in writing whether the application is complete; (2) If the application is incomplete, the secretary shall identify the items required to complete the application; and (3) The secretary shall determine the adequacy of the applicant's response to each incomplete item within 15 days after receipt of the response.