ARSD 74:29:05:20

ARSD 74:29:05:20. Land application of solution -- Written report

Last amended: 1988Year: 2026Length: 65 wordsOfficial source

Cite as S.D. Admin. R. 74:29:05:20

Following each land application cycle, a written report must be submitted to the department. This report must include the following: (1) The total amount of solution applied; (2) The total hydraulic loading rate per acre; (3) The total metals loading rate per acre; (4) The duration of the application cycle; (5) All sampling data; and (6) A general discussion of the success of the system.
ARSD 74:29:05:20: ARSD 74:29:05:20. Land application of solution -- Written report | Justis AI