ARSD 74:36:07:127. Existing municipal solid waste landfill revised plan submittal

Last amended: 2019Year: 2026Length: 72 wordsOfficial source

Cite as S.D. Admin. R. 74:36:07:127

The owner or operator of an existing municipal solid waste landfill that meets the requirements of § 74:36:07:105 shall submit a revised design plan to the secretary for approval: (1) At least 90 days before expanding operations to an area not covered by the previously approved design plan; and (2) Prior to installing or expanding the gas collection system in a way that is not consistent with the previously approved design plan.