ARSD 74:36:18:05. Required contents of a complete application for a permit
Cite as S.D. Admin. R. 74:36:18:05
An application for a construction activity and continuous operation activity permit shall contain the following information to be considered complete:
(1) General company information, including the company name and address, the owner's name and agent, and the plant site manager or contact;
(2) Legal description and location of the construction or continuous operation activity, including a site map;
(3) Description of the proposed construction or continuous operation activity, including nature and description of equipment used;
(4) Description of the reasonably available control technology used to control the fugitive emissions; and
(5) For construction activities, the proposed date for commencement and termination of the construction activity.