ARSD 74:36:20:06
ARSD 74:36:20:06. Timely and complete application for a construction permit required
Cite as S.D. Admin. R. 74:36:20:06
A person who constructs a new source or modification to an existing source required to have a construction permit shall submit a complete application to the department at least 180 days before the estimated date of commencing construction of the new source or modification to an existing source. An application is complete if it meets the requirements in ยง 74:36:20:07.