ARSD 74:36:20:15
ARSD 74:36:20:15. Contents of construction permit
Cite as S.D. Admin. R. 74:36:20:15
A construction permit shall include the following:
(1) The signature of either the secretary or the chairman;
(2) The name of the person, company, political subdivision, agency, or institution granted a permit;
(3) The type of operation;
(4) The facility and mailing address;
(5) The date the construction permit was granted;
(6) A number for administrative reference;
(7) The timeline for submitting a timely and complete application for a minor source operating permit or Part 70 source operating permit;
(8) A statement granting a construction permit by the board or secretary and any conditions that the board or secretary may impose to ensure compliance with the act and the Clean Air Act;
(9) Emission limits and standards, including operational requirements and limits for all regulated emission units, necessary to ensure compliance with applicable requirements of the act and the Clean Air Act;
(10) Monitoring, recordkeeping, and reporting requirements necessary to determine compliance with the construction permit;
(11) A severability clause to ensure the continued validity of the various permit requirements if any portions of the permit are challenged; and
(12) Provisions stating the following:
(a) The permittee must comply with all conditions of the permit. Any permit noncompliance constitutes a violation and is grounds for enforcement action;
(b) The construction permit does not convey any property rights of any sort or any exclusive privilege; and
(c) The permittee shall provide any information, including records, requested in writing by the department to determine compliance.