ARSD 74:54:02:05
ARSD 74:54:02:05. Separate groundwater discharge plan not required for certain activities
Cite as S.D. Admin. R. 74:54:02:05
The following do not require a separately approved groundwater discharge plan if the discharge activity is subject to a review by the secretary as described in this chapter for conformance to chapter 74:54:01:
(1) Underground injection control (UIC) wells permitted under chapter 74:55:02 and Class V UIC wells permitted by the EPA;
(2) Individual and small on-site wastewater systems in compliance with chapter 74:53:01; and
(3) Wastewater treatment and disposal facilities with plans and specifications approved prior to construction by the secretary and which have been issued either a surface water discharge permit in accordance with chapter 74:52:01 or an EPA NPDES permit. Wastewater treatment and disposal facilities that are designed to discharge to groundwater must submit a groundwater discharge plan application.