S.D. Codified Laws § 49-41B-24

Permit for energy conversion facilities, AC/DC conversion facilities, or transmission facilities--Complete findings by commission required within year of application

Last amended: 2015Year: 2025Length: 97 wordsOfficial source
Within twelve months of receipt of the initial application for a permit for the construction of energy conversion facilities, AC/DC conversion facilities, or transmission facilities, the commission shall make complete findings in rendering a decision regarding whether a permit should be granted, denied, or granted upon such terms, conditions or modifications of the construction, operation, or maintenance as the commission deems appropriate. Source: SL 1977, ch 390, § 18; SL 1980, ch 328, § 2; SL 1981, ch 341; SL 2006, ch 242, § 5; SL 2009, ch 243, § 3; SL 2015, ch 235, § 2.