S.D. Codified Laws § 49-41B-5

Mailed notice to adjacent owners--County without plan or ordinances--Prior to permit application

Last amended: 2026Year: 2025Length: 91 wordsOfficial source
If the proposed site for an energy conversion facility or AC/DC conversion facility is located in a county that does not have a comprehensive plan or has not adopted zoning ordinances, the applicant must provide written notice of intent to apply for a permit for the construction of the facility, by certified mail, to each adjacent property owner, at least three months before filing the application as required in § 49-41B-11 . Source: SL 1977, ch 390, § 5; SL 2006, ch 242, § 2; SL 2026, ch 187, § 1.
S.D. Codified Laws § 49-41B-5: Mailed notice to adjacent owners--County without plan or ordinances--Prior to permit application | Justis AI