1680-05-03-.09
Special Prequalification Requirements
Cite as Tenn. Comp. R. & Regs. 1680-05-03-.09
(1)
Reservation of Right to Establish Special Prequalification Requirements. – Notwithstanding
any other provision in this chapter, the Department reserves the right to establish special or
additional prequalification requirements for bidders and/or subcontractors on a project-by-
project basis whenever, in the judgment of the Department, such special or additional
PREQUALIFICATION OF CONTRACTORS
CHAPTER 1680-5-3
prequalification requirements are in the best interest of the Department because of the
project’s size, scope, schedule, complexity, environmental sensitivity or any other special
circumstance related to the project.
(2)
Notice. – The Department will give notice of any special prequalification requirements and
procedures for bidders and/or subcontractors prior to the issuance of the proposal form for
the project. Notice shall be given by publication in appropriate newspapers and/or
publication on the Construction Division’s website, as the Department may determine.
(3)
Rejection of Ineligible or Non-Responsive Bidders or Subcontractors. – The Department
reserves the right to refuse to issue a proposal form to any bidder, reject the proposal of any
bidder, and/or decline to approve any subcontractor that does not, in the judgment of the
Department, meet the special prequalification requirements.