0500-02-01-.06
Application For Certificate - Form And Content
Cite as Tenn. Comp. R. & Regs. 0500-02-01-.06
Applications for Certificate of Public Purpose and Necessity shall be submitted in twelve (12) copies and
shall contain the below described statements and information. Each copy of the application shall be bound in
a separate volume with an appropriate cover and the information and/or statements contained therein shall
appear in the order as described below:
(a)
There shall be a letter addressed to the Building Finance Committee from the chief officer of
the municipality, bearing the signature of such official and including the following:
1.
a statement requesting that the Building Finance Committee issue to the municipality a
Certificate,
2.
a statement outlining the scope of the project for which the Certificate is sought and the
reasons for its undertaking,
3.
a statement as to the aggregate cost of the project, sources and amounts of funding
available for implementation of the project and sources and amounts of anticipated
revenues to be derived from the project, and
RULES FOR MAKING APPLICATION
CHAPTER 0500-2-1
4.
a statement as to the aggregate amount of General Obligation bonds the municipality is
seeking authority to issue to finance the project.
(b)
Certified copies of all necessary and required resolutions and/or ordinances enacted or passed
by the governing body of the municipality empowering it to undertake the project and make
application to the Committee for a Certificate.
(c)
An Expenditure vs. Funding Statement, such statement to contain, on a single page where
possible, an itemized statement of all project expenditures tabulated in a single column on the
left hand side of such page and an itemized statement of all funding for the project tabulated
in a single column on the right hand side of such page. Each such column shall be totaled and
the total amounts of each column shall equal one another.
1.
Cost shall include all expenses to be incurred in undertaking the project including, but
not limited to, land cost, construction cost, cost of the services of architects and
engineers, legal and fiscal expenses and shall include interest accruing during the
construction period and for six (6) months thereafter on money borrowed in conjunction
with the project for which the petition is filed.
2.
Funds shall include all grants and/or loans from governmental agencies as well as monies
to be derived from the sale of bonds, or to be borrowed from commercial institutions, or
to be contributed from the general fund or any special fund of such municipality.
3.
There shall be included in the appendix to the application with reference to cost, the
following:
(i)
where fees or costs have been established by option, actual payment, invoice or
contract, a copy of the document establishing the basis for the cost or fee,
(ii)
where fees or costs have been established by estimate, the source of the estimate
and sufficient additional information concerning the estimate to establish that the
party making the estimate is well qualified and has sufficient experience and
knowledge with respect to the subject of the estimate as to make the estimate
reliable, and
(iii)
in the case of land cost, there shall be provided, in addition to any option or
contract establishing the purchase price, an independent appraisal of the
property by a qualified real property appraiser.
4.
There shall be included in the appendix to the application, with reference to sources of
funding the following:
(i)
where the source of funding is to be provided by a governmental agency either by
loan or grant, a copy of the application for such funding, copies of all necessary
approvals required in obtaining such funds, including approvals by the
development districts, state clearinghouse for Federal funding, etc., and a copy of
or a letter from the Federal or State agency from which funds are elicited,
indicating the status of the request and the probability of funding.
(ii)
where the source of funds is to be a loan from a commercial lending institution, a
copy of the loan agreement including a copy of any mortgages or security
agreements to be effected by and between the municipality and the lending
institution, in consideration for loan, and
RULES FOR MAKING APPLICATION
CHAPTER 0500-2-1
(iii)
where the source of funds is to be by the issuance of bonds, General Obligation
and otherwise, a copy of all proposed recitals to become a part of the bonds,
including bondholders remedies, lien rights, prepayment rights, penalties for
delayed payments, and the estimated interest rates, and/or amortization schedule
for the bonds.
(d)
A Payment vs. Revenue Statement, such statement to contain a tabulation of the estimated
annual payments which will be required to meet any indebtedness incurred by the
municipality in undertaking the project as well as a summary of anticipated revenues from the
project including estimated amounts and dates of receipt of such revenues. There shall be
included in the appendix to the application, with reference to Revenues, the following:
1.
where anticipated revenues are based on the sale of land, a detailed and thorough
discussion of the projected sale price of the land used in establishing projected revenues
and a discussion of the feasibility of the projected dates used in establishing the time at
which such revenues shall become available, and
2.
there shall be included in the appendix to the application, with reference to payments, a
complete amortization schedule for retiring the indebtedness incurred as a result of the
project.
(e)
An Emergency Financing Statement, such statement to contain a thoroughly discussed plan
showing where the municipality shall obtain any emergency funding needed to meet expenses
in the event project revenues do not materialize on schedule.
(f)
Sworn Statements from the appropriate official to the municipality, such statements to
contain:
1.
the total assessed value of property within the municipality by assessor of property
(assessed value is the value of all property within the municipality to which the tax rate is
applied),
2.
a general tabulation of all outstanding General Obligation bonds issued, by the chief
fiscal officer of municipality, and
3.
a specific tabulation of all outstanding bonds issued under the authority of TCA 7-55-101
et. seq., and/ or TCA 13-16-201 et. seq., by the chief fiscal officer of municipality.
(g)
An Engineering Report, the engineering report shall contain the following information and/or
address itself to the following items with respect to the site:
1.
topographic and/or terrain conditions at the site,
2.
location of the site with respect to access to highways, rail and/or water transportation
facilities, including a discussion of any problems or inherent drawbacks to the use of the
site occasioned by the location of the site, with respect to these various modes of
transportation.,
3.
soil conditions at the site, including estimated quality of the soil with respect to industrial
usage of the site, estimated depth to rock., probability of ground water and/or internal
drainage problems with respect to site soil and any corrective measures to be taken with
respect to site soil conditions.,
4.
site configuration and any problems associated with the configuration of the site,
including the probability of wasted property,
RULES FOR MAKING APPLICATION
CHAPTER 0500-2-1
5.
site drainage, including a discussion of the nature of site drainage, provisions to handle
site drainage and any problems associated with site drainage. A discussion of flood
conditions relative to the site shall be included in this section of the report,
6.
provisions for serving the site with water, gas, electricity, and sewage collection:
(i)
with respect to water, the report shall include sufficient information to establish
that proposed water service to the site shall be adequate, including water for fire
protection. The discussion shall include an analysis of water pressures and
quantities, the basis for establishing storage capacities, basis for establishing
consumptive demands as well as the basis for establishing fire demands,
(ii)
with respect to sources of energy or power, a discussion of the manner and method
of supplying needed energy or power to the park, including the type of energy
sources available and to be supplied,
(iii)
with respect to sewage collection, a discussion of the manner and method of
collecting park waste and disposing of it. A discussion of estimated park waste
and the basis for such estimate, a discussion of sewer hydraulics and a discussion
of the capacity at the local treatment facility to handle the anticipated park waste,
(iv)
in the event that any of the above services are not to be provided, the report
should discuss in detail the impact on the park or site of not providing this
service.
7.
The engineering report shall contain sufficient maps to:
(i)
delineate the location of the site., with respect to local modes of transportation,
with respect to the municipality's business district and with respect to sources of
labor,
(ii)
to show all improvements proposed on the property,
(iii)
to indicate anticipated subdivision of the property,
(iv)
to show the present terrain features and topographic relief of the site (suggest a
minimum 10’ contour interval), and
(v)
to show the nature and extent of any proposed alternations to the site topography.
(h)
A Statement by an Attorney of Law, to the effect that there are or are no problems associated
with implementation of the project. In the event that legal complications do exist, the
statement shall discuss such problems and their probable impact upon the project.
(i)
A Statement as to Available Sources of Labor within a twenty-five (25) mile radius of the site
including a discussion of the basis of establishing available labor supplies.
(j)
A Discussion of any Environmental Problems anticipated and their effect upon the project.
(k)
A Plat and Legal Description of the Property.
(1)
An Appendix to the Application containing that information as requested by Section 0500-2-
1-.06 (c); (d) and any other information with regard to the feasibility of the project that the
municipality feels should be included or desires to place in the application.
RULES FOR MAKING APPLICATION
CHAPTER 0500-2-1