(1)
Contract payments shall be made in accordance with the payment terms and conditions
section of the contract. No payment shall be made until the contract is approved as required
by these Rules and Central Procurement Office Policy. The State is not liable to a
Contracting Party for services performed or goods delivered prior to the effective date of a
contract or the Contracting Party’s receipt of a notice to proceed sent by the Central
Procurement Office or a Delegated State Agency. Notwithstanding the foregoing, the Chief
Procurement Officer shall have the authority to authorize a Contracting Party to perform
services or commence work before a contract has been fully executed in accordance with
these Rules and Central Procurement Office Policy.
(2)
All contracts in which the State is to make one or more payments to a Contracting Party shall
provide that payments are to be made upon submittal of invoices by the contractor, after
COMPREHENSIVE RULES AND REGULATIONS OF THE
CHAPTER 0690-03-01
CENTRAL PROCUREMENT OFFICE
delivery of goods or the performance of the portion of the service to which each payment
represents, except that Grant Contracts may provide for advance payments in accordance
with these Rules and Central Procurement Office Policy.
(3)
Except as provided in this Rule, no payment shall be made for performance under a contract
unless a procuring State Agency official certifies that the contractor’s work progress has been
evaluated, is satisfactory, and is sufficient according to the terms of the contract to justify the
payment requested. This certification shall be documented by the appropriate procuring
State Agency staff’s written approval of each invoice submitted for payment.
(4)
All procuring State Agencies shall maintain adequate documentation to support all payments.