0720-36-.08
Building Standards
Cite as Tenn. Comp. R. & Regs. 0720-36-.08
(1)
An ODC shall construct, arrange, and maintain the condition of the physical plant and the
overall ODC environment in such a manner that the safety and well-being of the patients are
assured.
(2)
After the applicant has submitted an application and licensure fees, the applicant must submit
the building construction plans to the Commission. All facilities shall conform to the current
edition of the following applicable codes as approved by the Board for Licensing Health Care
Facilities: International Building Code (excluding Chapters 1 and 11) including referenced
International Fuel Gas Code, International Mechanical Code, and International Plumbing
Code; National Fire Protection Association (NFPA) NFPA 101 Life Safety Code excluding
referenced NFPA 5000; Guidelines for Design and Construction of Health Care Facilities
(FGI) including referenced Codes and Standards; U.S. Public Health Service Food Code; and
Americans with Disabilities Act (ADA) Standards for Accessible Design. When referring to
height, area or construction type, the International Building Code shall prevail. Where there
are conflicts between requirements in local codes, the above listed codes, regulations and
provisions of this chapter, the most stringent requirements shall apply.
(3)
The codes in effect at the time of submittal of plans and specifications, as defined by these
rules, shall be the codes to be used throughout the project.
(4)
The licensed contractor shall perform all new construction and renovations to ODCs, other
than minor alterations not affecting fire and life safety or functional issues, in accordance with
the specific requirements of these regulations governing new construction in ODCs, including
the submission of phased construction plans and the final drawings and the specifications to
each.
(5)
No new ODC shall be constructed, nor shall major alterations be made to an existing ODC
without prior written approval of the Commission, and unless in accordance with plans and
specifications approved in advance by the Commission. Before any new ODC is licensed or
before any alteration or expansion of a licensed ODC can be approved, the applicant must
furnish two (2) complete sets of plans and specifications to the Commission, together with
fees and other information as required. Plans and specifications for new construction and
major renovations, other than minor alterations not affecting fire and life safety or functional
issues, shall be prepared by or under the direction of a licensed architect and/or a licensed
STANDARDS FOR OUTPATIENT DIAGNOSTIC CENTERS
CHAPTER 0720-36
engineer and in accordance with the rules of the Board of Architectural and Engineering
Examiners.
(6)
Final working drawings and specifications shall be accurately dimensioned and include all
necessary explanatory notes, schedules and legends. The working drawings and
specifications shall be complete and adequate for contract purposes.
(7)
Detailed plans shall be drawn to a scale of at least one-eighth inch equals one foot (1/8” = 1’),
and shall show the general arrangement of the building, the intended purpose and the fixed
equipment in each room, with such additional information as the Commission may require.
An architect or engineer licensed to practice in the State of Tennessee shall prepare the
plans the Commission requires.
(a)
The project architect or engineer shall forward two (2) sets of plans to the Commission
for review. After receipt of approval of phased construction plans, the owner may
proceed with site grading and foundation work prior to receipt of approval of final plans
and specifications with the owner’s understanding that such work is at the owner’s own
risk and without assurance that final approval of final plans and specifications shall be
granted. The project architect or engineer shall submit final plans and specifications for
review and approval. The Commission must grant final approval before the project
proceeds beyond foundation work.
(b)
Review of plans does not eliminate responsibility of owner and/or architect to comply
with all rules and regulations.
(8)
Specifications shall supplement all drawings. They shall describe the characteristics of all
materials, products and devices, unless fully described and indicated on the drawings.
Specification copies should be bound in an 8½ x 11 inch folder.
(9)
Drawings and specifications shall be prepared for each of the following branches of work:
Architectural, Structural, Mechanical, Electrical and Sprinkler.
(10) Architectural drawings shall include where applicable:
(a)
Plot plan(s) showing property lines, finish grade, location of existing and proposed
structures, roadways, walks, utilities and parking areas;
(b)
Floor plan(s) showing scale drawings of typical and special rooms, indicating all fixed
and movable equipment and major items of furniture;
(c)
Separate life safety plans showing the compartment(s), all means of egress and exit
markings, exits and travel distances, dimensions of compartments and calculation and
tabulation of exit units. All fire and smoke walls must be identified;
(d)
The elevation of each facade;
(e)
The typical sections throughout the building;
(f)
The schedule of finishes;
(g)
The schedule of doors and windows;
(h)
Roof plans;
(i)
Details and dimensions of elevator shaft(s), car platform(s), doors, pit(s), equipment in
the machine room, and the rates of car travel must be indicated for elevators; and
STANDARDS FOR OUTPATIENT DIAGNOSTIC CENTERS
CHAPTER 0720-36
(j)
Code analysis.
(11) Structural drawings shall include where applicable:
(a)
Plans of foundations, floors, roofs and intermediate levels which show a complete
design with sizes, sections and the relative location of the various members;
(b)
Schedules of beams, girders and columns; and
(c)
Design live load values for wind, roof, floor, stairs, guard, handrails, and seismic.
(12) Mechanical drawings shall include where applicable:
(a)
Specifications which show the complete heating, ventilating, fire protection, medical
gas systems and air conditioning systems;
(b)
Water supply, sewerage and HVAC piping systems;
(c)
Pressure relationships shall be shown on all floor plans;
(d)
Heating, ventilating, HVAC piping, medical gas systems and air conditioning systems
with all related piping and auxiliaries to provide a satisfactory installation;
(e)
Water supply, sewage and drainage with all lines, risers, catch basins, manholes and
cleanouts clearly indicated as to location, size, capacities, etc., and location and
dimensions of septic tank and disposal field; and
(f)
Color coding to show clearly supply, return and exhaust systems.
(13) Electrical drawings shall include where applicable:
(a)
A seal, certifying that all electrical work and equipment is in compliance with all
applicable codes and that all materials are currently listed by recognized testing
laboratories;
(b)
All electrical wiring, outlets, riser diagrams, switches, special electrical connections,
electrical service entrance with service switches, service feeders and characteristics of
the light and power current, and transformers when located within the building;
(c)
An electrical system that complies with applicable codes;
(d)
Color coding to show all items on emergency power;
(e)
Circuit breakers that are properly labeled; and
(f)
Ground-Fault Circuit Interrupters (GFCI) that are required in all wet areas, such as
kitchens, laundries, janitor closets, bath and toilet rooms, etc, and within six (6) feet of
any lavatory.
(14) The electrical drawings shall not include knob and tube wiring, shall not include electrical
cords that have splices, and shall not show that the electrical system is overloaded.
(15) In all new facilities or renovations to existing electrical systems, the installation must be
approved by an inspector or agency authorized by the State Fire Marshal.
STANDARDS FOR OUTPATIENT DIAGNOSTIC CENTERS
CHAPTER 0720-36
(16) Sprinkler drawings shall include where applicable:
(a)
Shop drawings, hydraulic calculations, and manufacturer cut sheets;
(b)
Site plan showing elevation of fire hydrant to building, test hydrant, and flow data (data
from within a 12-month period); and
(c)
Show “Point of Service” where water is used exclusively for fire protection purposes.
(17) The licensed contractor shall not install a system of water supply, plumbing, sewage, garbage
or refuse disposal nor materially alter or extend any existing system until the architect or
engineer submits complete plans and specifications for the installation, alteration or
extension to the Commission demonstrating that all applicable codes have been met and the
Commission has granted necessary approval.
(a)
Before the ODC is used, Tennessee Department of Environment and Conservation
shall approve the water supply system.
(b)
Sewage shall be discharged into a municipal system or approved package system
where available; otherwise, the sewage shall be treated and disposed of in a manner of
operation approved by the Department of Environment and Conservation and shall
comply with existing codes, ordinances and regulations which are enforced by cities,
counties or other areas of local political jurisdiction.
(c)
Water distribution systems shall be arranged to provide hot water at each hot water
outlet at all times. Hot water at shower, bathing and hand washing facilities shall be
between 105°F and 115°F.
(18) It shall be demonstrated through the submission of plans and specifications that in each ODC
a negative air pressure shall be maintained in the soiled utility area, toilet room, janitor’s
closet, dishwashing and other such soiled spaces, and a positive air pressure shall be
maintained in all clean areas including, but not limited to, clean linen rooms and clean utility
rooms.
(19) The Commission shall acknowledge that it has reviewed plans and specifications in writing
with copies sent to the project architect, the project engineer, the owner, the manager or
other executive of the institution. The Commission may modify the distribution of such review
at its discretion.
(20) In the event submitted materials do not appear to satisfactorily comply with 0720-36-.08(2),
the Commission shall furnish a letter to the party submitting the plans which shall list the
particular items in question and request further explanation and/or confirmation of necessary
modifications.
(21) The licensed contractor shall execute all construction in accordance with the approved plans
and specifications.
(22) If construction begins within one hundred eighty (180) calendar days of the date of
Commission approval, the Commission’s written notification of satisfactory review constitutes
compliance with 0720-36-.08(2). This approval shall in no way permit and/or authorize any
omission or deviation from the requirements of any restrictions, laws, regulations, ordinances,
codes or rules of any responsible agency.
(23) Prior to final inspection, a CD Rom disc, in TIF or PDF format, of the final approved plans
including all shop drawings, sprinkler, calculations, hood and duct, addenda, specifications,
etc., shall be submitted to the Commission.
STANDARDS FOR OUTPATIENT DIAGNOSTIC CENTERS
CHAPTER 0720-36
(24) The Commission requires the following alarms that shall be monitored twenty-four (24) hours
per day:
(a)
Fire alarms; and
(b)
Generators (if applicable).
(25) With the submission of plans the facility shall specify the evacuation capabilities of the
patients as defined in the National Fire Protection Code (NFPA). This declaration will
determine the design and construction requirements of the facility.