0720-43-.04
Approval Of Plans
Cite as Tenn. Comp. R. & Regs. 0720-43-.04
(1)
Plans and specifications submitted pursuant to these rules shall be approved only if the
proposed construction would be in compliance with the minimum standards of fire prevention,
fire protection, and building construction safety in effect at the time of initial submission.
(2)
No final approval of plans and specifications shall be valid unless the construction
represented by such plans and specifications has substantially progressed within twelve (12)
months after the effective date of any adopted revisions of the building or codes standards in
effect at the time of initial submission.
(3)
A copy of the approved plans and specifications shall be retained on the job site through
completion of the project and final inspection.
(4)
Construction shall proceed in accordance with the plans and specifications as approved
hereunder. If construction is completed in accordance with the approved plans and
specifications, the building represented by such plans and specifications shall be exempt
from subsequently adopted standards of fire prevention, fire protection, and building
construction safety, unless the non-conformity of the building to such standards poses a
serious life safety hazard.
(5)
No approval of, or failure to review, plans and specifications by the Department shall relieve
the owner, developer, designing architect or engineer of their respective responsibilities for
compliance with applicable laws, rules or codes respecting fire prevention, fire protection,
and building construction safety.